Sie sind auf Seite 1von 34

Contents

Introduction To Project management

Definition of Project General Introduction to Project Management Definition of project Management

Project management Theory

Project Lifecycle
Initiation Planning Execution Closure

Project Management Processes

Project Integration Management Project Plan

Purpose Development

Execution Example of Project Plan Content The Office of Science Restructuring Project

Summary

Bibliography

Project Management In The Construction Industry

Introduction To Project Management

Definition of a Project

To understand project management you must understand the term project. The definition of a project is a unique endeavor to produce a set of deliverables within a clearly specified time, cost and quality constraints. (Project management guidebook, empowering managers to succeed 2003, PMG 2003) A project is a series of tasks, arranged in a defined sequence or relationship that produces a pre-defined output or effect. A project always has a start, middle and an end (Project management Institute, Body of Knowledge 1999, PMBOK) The difference between a project and standard business operations are shown below in bullet form; Unique in Nature. They do not involve any repetitive processes. Every project undertaken is different from the last, where as operational activities often involve undertaking repetitive (identical) processes.

Have a defined timescale. Projects have a clearly specified start and end date within which the deliverables must be produced to meet a specified customer requirement. Have an approved budget. Projects are allocated a level of financial expenditure within which the deliverables must be produced to meet a specified customer requirement.

Have limited resources. At the start of a project an agreed amount of labour, equipment and material is allocated to the project. Involve an element of risk. Projects entail a level of uncertainty and therefore carry business risk.

Achieve beneficial change. The purpose of a project, typically, is to improve an organization through the implementation of business change.

General Introduction to Project Management

Project management began in its early form in the late 19th century, driven by government large scale coordinated project that were underway and the managers that found themselves having to organize a huge labour workforce at the site as well as coordinating another large production workforce and unprecedented raw materials in the factory. The complexity of the project naturally drove management practices towards project management processes. At the turn of the century Fredrick Winslow Taylor began to analyse the approach towards management, looking at scientific reasoning and applying this to the labour force to demonstrate how, by analyzing individual processes improvements could be made.

Taylors associate Henry Gantts then added an important visual tool, the Gantts chart, around 1917 that focused on the individual task, outlining and focusing on each element to produce a powerful analytical tool that has remained virtually unchanged until today. The Gants chart dramatically advanced the science of project management. The next major step forward in project management occurred after World War 2, specific techniques emerged for planning and managing huge budgets and workforce. The most well known were the Pert (Program Evaluation and Review Techniques) and CPM (Critical Path Method), which became synonymous for project scheduling techniques. Although some changes and minor tweaks were made but not much changed until the 1990s, Project Management until this point had been used mainly on large government projects like the nuclear weapons race. With the advent of computers and software the project management tools became easier to use, more readily available and quicker to use, therefore more suitable for smaller (although still large) projects and different disciplines. Toney Sisk states. This view of business as an organism implies that in order for a business to survive & prosper, all of its functional parts must work in concert towards specific goals In Modern terms in the construction industry each project employs a project manager, who puts together a team and ensures the integration and communication of the workflow horizontally across different departments and organizations.

Definition of Project Management

Project management is the skills, tools and management processes required to undertake a project successfully. (PMG 2003) According to the PM guidebook, Project Management comprises:

A set of skills. Specialist knowledge, skills and experience are required to reduce the level of risk within a project and thereby enhance its likelihood of success.

A suite of skills. Various types of tools are used by project managers to improve the projects chances of success. Examples include document templates, registers, planning software, modeling software, audit checklist and review forms. A series of Processes. Various management techniques and processes are required to monitor and control time, cost, quality and scope on projects. Examples include time management, cost management, quality management, change management, risk management and issue management. (PMBOK 1999) The project management institute defines project management as the application of knowledge, skills, tools and techniques to project activities in order to meet or exceed stakeholders needs and expectations from a project. (PMBOK 1999) Although the definitions are slightly different in their description, there core meaning is exactly the same and is widely accepted by the profession itself as an accurate statement.

Theory of Project Management

To begin we need to understand what constitutes a theory. A theory consists primarily from concepts and casual relationships that relate these concepts (Whetten 1989). It is possible to broadly characterize a target theory of production / operations management (Koskela 2000). This can also apply to project management if it is considered as being a special type of production / operations management In a recent report by the Project management institute (1999) on the future of project management, all items with regard to future developments and how the industry can advance and progress are detailed, however surprisingly there is no mention of any project management theory even when the future of the profession is in focus. This is not the first time it has been omitted, in their analysis of project management

research, spanning forty years, Kloppenberg and Opfer (2000) have nothing to report on the theory of project management. It can only therefore only be concluded that either; There is no theory of project management The theory of project management is insignificant to the profession

This is a much debated topic with many different views, in a paper by Lauri Koskela & Greg Howell called the underlying theory of project management is obsolete (PMI, 2002), it debates the topic and states that prior literature has generally agreed that there is no specific theory of project management, (Shenar 1998, Turner 1999), however according to Lauri Koskela & Greg Howell this is an inaccurate and damaging conclusion. In a wider study on the topic (Koskela & Howell 2002), argued that both the PMI & Kloppenberg and Opfer are wrong. Project management as practiced today is indeed a theoretical process, however this theory is narrow and needs further development and enrichment. They argue that it is the lack of understanding and development of the theory that is a major problem associated with project management. Frequent project failures (Kharbanda & Pinto 1996), lack of commitment towards project management methods (Forsberg & al. 1996), and slow rate of methodological renewal (Morris 1994). Thus they conclude that an explicit theory is the crucial and single most important issue for the future of the project management profession. A theory of project management should be prescriptive and reveal how actions taken contribute to the set goals and objectives (Kosela 2000). As a general basis there are three possible actions; Design of the system employed in designing and making Control of those systems in order to realize the production intended Improvement of those systems

Project management and indeed all production has three kinds of goal; General product production Internal goals, such as cost minimization and level of utilization

External goals, needs of customer, quality, flexibility and dependability

Kosela basically argues that the theories of project are the same as theories of production. The reasoning behind this is that project can be seen as a special type of production. This is evident from the definition of a project according to the Project management Institute (2000): A project is a temporary endeavor undertaken to create a unique product or service. According to the crystallization of Turner (1993) (PMBOK Guide 1999) as a starting point for the reconstruction of the theory of project, scope management is the raison detre of project management. He defines the purpose of scope management as follows; An adequate or sufficient amount of work is done. Unnecessary work is not done The work that is done delivers the stated business purpose (WBS)

From a theoretical viewpoint Turner claims the following; 1. Project management is about managing work. 2. Work can be management by decomposing the total work effort into smaller chunks of work, called activities and tasks (PMBOK Guide 1999) 3. The conceptionalization and principle of decomposition serves three essential purposes of project management. Although not specifically mentioned it is an implicit assumption associated with decomposition, this is that task are related if at all by sequential dependence. When the PMBOK Guide (1999) is studied it reveals that activities and task are the unit analysis in the core project management processes, scope management, time management and cost management. It also states that these management controls are centralized. This view is also supported by the description of Morris (1994). first, what needs to be done; second, who is going to do what; third, when actions are to be performed; fourth, how much is required to be spent in total, how much has been spent so far, and how much has still to be spent.. Central to this is the Work Breakdown Structure (WBS) When comparing the crystalisation of project management to the theories of opera-

tions management in general, it is easy to recoginise that it rests on the transformation theory of production, which has dominated product thinking in the 20th century. For example, Starr (1966) formulates; Any production process can be viewed as an input-output system. In other words, there is a set of resources which we call inputs. A transformation process operates on this set and releases it in a modified form which we call outputs. The management of this transformation is what we mean by production management. Their argument does have a lot of merit when comparing production with the discipline and processes of project management there are many similarities; however this is an in-depth and complex topic and currently has no professional endorsement. This theory based on operations is an argumentative one, there is surprisingly, at present no clear academically or professionally agreed theory for project management as a discipline, which considering the quantity of projects undertaken and the financial expenditure of these project extremely surprising and if koskela (2002) is correct then a rather alarming omission on the part of a so called professional industry. Project Lifecycle Project lifecycle consist of four all encompassing phases, Project Initiation, Project Planning, Project Execution and Project Closure. There are many other descriptions for the four phases however the content of each phase is universally agreed. The fast track approach does not adhere strictly to this phase on a macro level but does using a sequential design procurement package approach follow each phase accordingly.

You must remember that the definition of a project is a one off scheme unique in all aspects, therefore the descriptions below may change accordingly to the project or clients need / demand.

Project Lifecycle Diagram Project Management Guidebook - 2003 Project Initiation (concept)

This is the initial stage of any project where a business opportunity is identified, usually by the client and his advisers, and a business case put together to provide the solution or recommendations required to fulfill the business plan. A feasibility study is then carried out to look at the various business options and identify the final business plan solution. Once the final business plan is put together a project is then initiated to deliver the approved business solution. A term of reference is then completed and a project manager appointed. The project manager then identifies the appropriate project team required and starts to assemble this team establishing a project office.

Graph taken from the Project Managers Guidebook Method 123 empowering managers to succeed

Project Planning Stage.

This stage can only progress once the project scope is identified and defined in terms of reference; from here the project enters its detailed planning stage. The main focus of this stage is to ensure that the activities performed in the execution phase of the project are properly sequenced, resourced, executed and controlled. This entails the following project management documentation to be drafted and signed off; Project Plan Known as a work breakdown plan (WBS) this plan includes a hierarchical set of phases, tasks and activities to be undertaken. When the WBS is complete the activities and tasks are assessed, sequenced, resources allocated and a project schedule is established. (See attached Project Plan Template) Resource plan Although having identified the resources in the WBS this is an in-depth plan allocating in detail, type of resource, quantity of resource, human resource and skill set, items, purpose, specification and quantity of material and equipment. Small breakout schedules are then compiled for each resource to enable there separate monitoring. (See attached Resource Plan Template) Financial Plan This is a detailed breakdown cost plan that identifies the costs associated with the resource plan. The expense schedule provides a quantified breakdown that can be used to monitor the forecast spending vs. the actual spending.

Quality plan To ensure the quality of the project a detailed plan is developed that identifies and clearly defines the quality expectations of the delivered project. This

identifies and clearly defines the quality expectations of the delivered project. This not only the entails the delivered product but the management procedures and processes to ensure that the clients expectations are met or exceeded in the delivered end product. Acceptance Plan This is a plan that documents the sign of or acceptance from the client on each deliverable. This includes documents, plans and finished product. The need for this document is to safe guard all parties and ensure that sign off occurs in a structured manner before works proceed in earnest.

Communication Plan This is the establishment of the reporting process for the project, who, when, where and how are the issues to be decided on and documented. Responsibility for the individuals involved is also detailed with regard to who, when, where and how. Procurement Plan Identifies the products or service to be sourced from specialist suppliers. It also provides detailed information of the product, the reason for the products selection, procurement timeframe for the product and the selection process for the preferred supplier along with the ordering process.

Graph taken from the Project Managers Guidebook Method 123 empowering managers to succeed

Project Execution

This phase is usually the longest and involves the execution of all activities and tasks as detailed in the Project Plan. During there execution a series of management tools and processes are undertaken to monitor, control and communicate the status of the deliverables. The following are execution able processes that occur during the phase, all elements have there own independent registers; (PMBOK 199) Construction / build deliverables this is the physical construction of each item to the clients acceptance / sign off. Monitor and control Is the process of a series of management tools initiated by the project manager that controls and records the activities of the deliverables. Time management Records the time spent by staff on the project. Time is a scarce resource and once lost is difficult to get back. Cost management costs and expenses incurred on the project are identified, recorded, approved and paid. This is via expense forms and other project expenditure forms related to project expenses. Quality management This is a control process including physical and managerial processes to ensure both the journey and the final product meet or exceed the clients satisfaction. Change management simply put its a process to record changes to the project. This can be design, timeframe, materials, quality expectation or deliverable, regardless of the discipline its the method to record and communicate the changes.

Risk management is the process whereby all risks to the project in its entirety are assessed resolved and recorded. A risk can be identified at any stage as in all project it tends to be an organic process that evolves during its phased development. Issue management Sometimes referred to, as key issue management is a method by which any element affecting the project delivery or process is identified, timeframe assigned for resolution and issue resolved and recorded. Normally also recorded within the change management register. Procurement management Process of procuring and ordering materials and services within an agreed timeframe to the project teams and clients satisfaction inclusive of contract administration and contract close out. Communication management describes the process required to ensure the timely and appropriate generation, collection, dissemination, storage and ultimate disposition of project information. It consists of communications planning, information distribution, performance reporting, and administrative closure.

Graph taken from the Project Managers Guidebook

Method 123 empowering managers to succeed

Closure
Once the project is complete and accepted as such by the client it is now time for the formal closure of the project. By using the formula as above the project should have been a successful one that met or surpassed its objectives. Project closure includes the following documentation and actions to formally close out the project; Identifying all outstanding items, activities, risks or issues. Handover plan to transfer the delivered project to the client. Detailing activities required so the client is self sufficient, conclude contracts, resources and handing over warranties etc. Communicate the projects closure to all parties.

Graph taken from the Project Managers Guidebook Method 123 empowering managers to succeed

Representative Construction Project Life Cycle, per Morris

Full Installation Operation Substantially

Complete

Major Contract

Let

Project Go Decision

Phase 1 3

Phase 2 Phase 4

Phase

Above is a typical construction lifecycle graph as described and illustrated by Morris (1994); Feasibility project formulation, feasibility studies, strategic design and approval. A go/no go decision is made at the end of this time.

Planning and Design base design, cost and schedule, contract terms and conditions, and detailed planning. Major contracts are let at the end of this phase. Production manufacturing, delivery, civil works, installation, and testing. The facility is substantially complete at the end of this phase. Turnover and start up final testing and maintenance. The facility is in full operation at the end of this phase.

Project Management Processes Project management is an integrated discipline, where action or inaction in any one area can and will usually affect others areas. These interactions are not always clearcut and can affect different aspects in a subtle but damaging way. PMBOK (1999) using an example as a scope change that will not affect the project cost, but it may affect team morale or product quality. These interactions and developments that occur during the project may/will require trade offs among the project objectives, to enhance in one area another may suffer. It is the project managers role to have a complete overview of the project and ensure the end objective is met and any trade offs are insignificant come the end of the project. Project management processes show these interactions with each other and show how project management processes interlink. PMBOK (1999) categorizes the processes into two major groups; Project management processes that describe and organize the work. Product-orientated processes that specify and create the project product. Typically defined these are as shown in the project lifecycle as demonstrated in the previous pages. These two processes overlap and interact continually, for example how can the work program be completed without an understanding of the process involved in producing the product. The project management processes are then sub divided into five more groups, these groups link together because of the results they produce. These results or outcomes

groups link together because of the results they produce. These results or outcomes become an input into another group and the interaction continues in this manner.

PMBOK
Links among

Project Groups in a Phase


As demonstrate above in the chart the five process groups are as follows; (PMBOK1999) Initiating processes to recognize a phase should begin and committing to do so Planning process developing and maintaining a suitable scheme that accomplishes the business need that the project was undertaken to address. Executing process coordinating resources, material and people to complete the task/plan Controlling process that monitor and measure the progress and ensure the project objectives are met. Closing process agreeing acceptance and sign off for the project or phase and documenting the fact.

These five elements or processes are not only a one-time event, they also overlap and affect following elements. As demonstrated below in graph form.

Level of Activity

Executing

Processes Planning Processes

Initiating

Closing

Processes Controlling Process

Processes

Phase Start

Time

Overlap of Process Groups in a Phase as Demonstrated in PMBOK

These processes are all detailed and documented in the Project Plan, it is this plan that documents and controls the entire project process. The plan at initial stage may include generic resources and undated durations while the final plan reflects the specific resources and explicit dates as formulated through the organic developments that are a project.

Overview of Project Management Processes taken from PMBOK (1999)

Project Integration Management Project Plan

Purpose

The project plan is the key document in the projects successful management and is developed at the initial project stage. This document is an organic one and is developed as the project develops. The two major processes are; Project plan development taking the results of other planning processes and putting them into a consistant, coherent document. Project plan execution carrying out the project plan by performing the activities included therein. The project plan provides a statement of how and when the project objective are to be achieved, by detailing the major milestones, products activities and resources on the project. It is a customized document developed for each project from a standard template, tailored to suit the project. It is used as a baseline against which all project activities and processes are monitored throughout the project, on a stage-by-stage basis. PMBOK (1999) states that the project plan is used for the following disciplines; Guide project execution. Document project planning assumptions. Document project planning decisions regarding alternatives chosen. Facilitate communication among stakeholders. Define key management reviews as to content, extent and timing. Provide a baseline for progress measurement and project control.

Inputs to Project Plan Development

Graph taken from PMBOK (1999)

Development
The project plan has tools and techniques that make up its contents, there are three main elements as shown below (PMBOK 1999); Project planning methodology - This is any structured plan used to guide and direct the project team during the development of the project plan. It can include a variety of soft and hard tools such as project management software and facilitated start up meetings.

Stakeholders skills and knowledge Each stakeholder does/can have different skills and knowledge base, which can assist with the project in many ways. The project must be structured in such a way that stakeholders can contribute. Project Management Information Systems (PMIS) Project management information systems consist of tools and techniques used to gather, integrate, and disseminate the information from the other processes.

Execution
Project Plan execution is the main process for carrying out the project plan. The majority of the budget is expended during this phase and therefore the biggest risk for the success of the project. During this phase it is critical that the project manager and project team direct and coordinate the technical and organizational interfaces that exist in the project. PMBOK (1999) states that it is the project process that is most directly affected by the project application area in that the product of the project is actually created here. There are six main elements that make up the tools and techniques of the project plan execution, PMBOK categorizes these as listed below; General management skills These are skills like leadership, communication and negotiating, all essential to effective project management. Product skills and knowledge there must be an appropriate knowledge and understanding of the products to be used and their methodology.

understanding of the products to be used and their methodology. Work authorization system this is a formal process whereby work is sanctioned formally to commence, either a package or specific activity, always in writing on larger projects, occasionally verbally on smaller projects. Status review meeting these are the regular scheduled project meetings. They are held between different levels of project team, suppliers, contractors, clients and stakeholders. Project Management information system as described before. Organizational procedures any and all of the organizations involved in the project may have formal or informal procedures useful during project execution.

A Project Plan consists of many disciplines, below is an example of an actual Project Plan contents sheet taken from an actual construction project for the office of science as illustrated below; Project Plan For The Office of Science Restructuring Project

Table of Contents

Introduction Mission Need Project Description. Description of Desired end State 2.1.1 SC Organization 2.1.2 Roles, Responsibilities, Authorities, Accountability. 2.1.3 Systems and Processes. 2.1.4 Laboratory M&O Contracts. 2.1.5 Relationships with other D&O Offices. Management Principles

Management Principles Requirements Assumptions Project Accountability Project Management Organization and Responsibility Project Management Team Project Implementation Team Work Breakdown Structure Support Contractors

Project Baselines Scope Cost Project Resource Requirements Restructuring Cost Estimate Schedule Phase 1 Phase 2 Phase 3 Analysis and Assessments

Baseline Change Control Process

Project Controls and Reporting System Project Controls System Project Reporting Project Review

8.0 Transitions To Operations 8.1 Phase 1 Objections and Training 8.2 Phase 2 Objections and Training 8.3 Phase 3 Objections and Training

8.3 Phase 3 Objections and Training 9.0 9.1 9.2 9.3 9.4 9.5 9.6 Appendices Project Management Team Project Implementation Team Work Breakdown Structure Project Management Cost estimate Restructuring Cost Estimate Project Schedule

The plan above demonstrates the core processes and elements as discussed earlier, it is as previously stated an organic document and is developed as the project continues, with detailed documents, team units, detailed planning for phases as they progress. It is the responsibility of the project manager to ensure that the plan is updated as works proceed.

Summary

Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholders needs and expectations from a project. (PMBOK 1996)

a project. (PMBOK 1996) Project management involves more than just what a project manager does, all team manager engage in some level of project management, whether meeting deadline, communicating with others, or estimating task durations. Everyone involved in the project contributes to its success. The lack of agreement regarding the theory of project management, as detailed previously, is an area that requires greater immediate attention from all professional and academic bodies. Although I agree with some of the conclusions offered by Lauri Koskela & Gregory Howell (2002), who argue that project management theory can be related to current production theory and treated as special production, there is no agreement by any professional body that this theory is relevant. Therefore as such an important profession involved in such a diverse range of industries, where huge amounts of money are expended it is inexcusable that there is no agreed theory. One of the most important conclusions of Lauri Koskela & Greg Howells (2002) paper was their finding that the current problems associated with most project failure was the lack of theory, or the errors in the current project management practices caused by the lack of a profession to establish an agreed theory. They state management tools not utilized and exceeding budget and time over runs as a basic flaw in the current thinking and methodology of project management. For project management to develop as a profession it is essential that a theory is developed, processes refined and universally agreed upon however, there are three major problems currently, one of the major causes of problems associated with projects in my 22 years experience, stems from people attitudes. The Them & us scenario, regardless of any new theory and refinements, attitude towards a team approach is the key to success. Until we learn to respect each other and each others discipline and work as one-unit projects will always fail. Maybe project management theory is a mix of production theory, management theory and behaviour science, particularly as every project is unique therefore we are people reliant. Another key aspects is the project life cycle, as shown in the main text there are processes that need to be finished before others commence, sequential processes, again however, in todays globally competitive market place one of the key factors in selection of a project management team by a client is a team that can say YES to the clients demands, on time, cost and quality, particularly on time. This means that the word fast track is a generally used term for the majority of projects, commencing before they are properly researched and designed, this provides an uncertain end product with regard to quality and an uncertain end cost.

vides an uncertain end product with regard to quality and an uncertain end cost. Also there is a lack of understanding towards the actual processes that occur during construction, packages are awarded in this scenario that interlink with others, however due to lack of understanding and communication with the project team errors and delays occur as works are delayed by this overlap, the sequence of works. The above statements are supported by Lauri Koskela & Greg Howell (2002) who state that the present doctrine of project management suffers from serious deficiencies in its theoretical base, it rests on a faulty understanding of the nature of work in projects, and deficient definitions of planning, execution and control. They also conclude that in the present big, complex and speedy (fast track) projects, traditional project management is simply counterproductive; it creates self-inflicted problems that seriously undermine performance. The lack of project management theory as shown in previous professional and academic papers (PMBOK 1999 and Kloppenberg and Opfer 2000) is a worrying omission, this combined with the problems on many project ( An example, wembley football stadiums, current 2 year over run) and the papers by Koskela & Howell (2002) & Koskela & Rubin Vrijhoef (2003), can only bring us to one conclusion. The conclusion from the academic and professional research available, is that the final statement in the Koskela (2002) paper is an accurate one. This states The present evidence is strong enough for the claim that a paradigmatic transformation of the discipline of project management is needed. The transformation required implies that a more intimate relation between theory and practice must be created in project management. Theory and practice have to be developed concurrently, similarly to other science-based fields, where theory is explicated, tested and refined in a continuous dialog between the scientific and practitioner communities.

Bibliography

The Art of Project Management: How to Make Things Happen / Scott Berkun, OReilly Media Inc, Sept 2005 A Call for Paper on Project Management Theory Lauri Koskela. CPM in Construction Management Sixth Edition James J. OBrian, Fredric L. Plotnick Mcgraw-Hill, c 2006 Construction Change: What Can I Do Penoyre & Prasad White Paper W/L1: Drivers Of Change In The Construction Industry Egan, Latham & Industry Initiatives The Dynamic Baseline Model for Project Management Project Management Consulting / AEW Services, April 2001. The Future of Project Management Project Management Institute, 1999 The History of Project Management Toney Sisk The Human Resource Management Implications of Lean Construction: Critical Perspectives & Conceptual Chasms / Stuart Green / Paper, 2002 International Project Management / Owen Jay Murphy, Thompson Southwestern, c 2005 Lean Thinking Banish Waste & Create Wealth in Your Corporation / J. Womack Free Press, c July 2003 Project Management Guidebook Empowering managers to succeed Methods 123, 2003

Methods 123, 2003 Project Management Body of Knowledge PMI, 1999. Project Lifecycle Bright Interactive Ltd 1999-2006 Project Lifecycle - Build Bright Interactive Ltd 1999-2006 The Prevalent theory of Construction is a Hindrance for Innovation Lauri Koskela & Ruben Vrijhoef The Project Lifecycle: Four Basic Phases Project Management Wisdom, 2001 Project Lifecycle Models: How They Differ and When to Use Them Business eSolutions. Project Lifecycle Definition Mariosalexandrou.com Project Management History Allen Web Project Managers Memorandum of Agreement and Conditions on Engagement Project Management Panel / c 1999 The Portable MBA in Project Management / Edited by Eric Verzuh John Wiley & Sons, c 2003 Project Management: A Profession based on Knowledge or Faith? International Journal of Project Management. Turner. J. Rodney. Vol 17, No 6, pp 329-330 Reforming Project Management: The role of Lean Construction Lauri Koskela & Gregory Howell Researching the Unanswered Questions of Project Management Project Management Research at the Turn of the Century. Proceedings of PMI Research Conference 2000. Morris, Peter W.G 2000. Pp 87-101 RIBA Journal: Architects & The Changing Construction Industry

RIBA Journal: Architects & The Changing Construction Industry RIBA July 2000 Journal The Theory of Project Management: Explanation to Novel Methods Lauri Koskela & Greg Howell, 2002 Theory of Constraints Management / Dee Bradbury Jacob & William T McCelland Goldratt Institute, 2001 History of Project Management Process Quality Associates Inc

Is There an Underlying Theory of Software Project Management (A critique of the transformation and normative views of project management) A Work in Progress Copyright, Glen B. Alleman, 2004 The Underlying Theory of Project Management is Obsolete Lauri Koskela & Gregory Howell / PMI, 2002. Why Projects Fail 1001 Reasons / Andrew A. L. Tan Venton Publishing, c 2004

Das könnte Ihnen auch gefallen