Beruflich Dokumente
Kultur Dokumente
Content
DNV Rules for Marine Operations, 1996, Pt.2 Ch.5 Lifting Capacity Checks
1. December 2010
Slide 2
Special planned, non-routine operations of limited durations, at sea. Marine operations are normally related to temporary phases as e.g. load transfer, transportation and installation.
DNV Standard for Certification No. 2.7-3 Portable Offshore Units June 2006 (New revision is coming)
Routine operations
1. December 2010
Slide 3
1. December 2010
Slide 4
http://webshop.dnv.com/global/
The 1996 DNV Rules for Marine Operations is not in the Webshop.
1. December 2010
Slide 5
Content
DNV Rules for Marine Operations, 1996, Pt.2 Ch.5 Lifting Capacity Checks
1. December 2010
Slide 6
Part 1 - General
Part 2 - Operation Specific Requirements Pt.2 Ch.1 - Load Transfer Operations Pt.2 Ch.2 - Towing Pt.2 Ch.3 - Special Sea Transports Pt.2 Ch.4 - Offshore Installation Pt.2 Ch.5 - Lifting Pt.2 Ch.6 - Sub Sea Operations Pt.2 Ch.7 - Transit and Positioning of Mobile Offshore Units
Operations
1. December 2010
Slide 7
Part 2 Chapter 5
Crane capacity
Rigging capacity,
Part 2 Chapter 6
Dynamic loads are accounted for by using a Dynamic Amplification Factor (DAF).
DAF in air may be caused by e.g. variation in hoisting speeds or motions of crane vessel and lifted object.
The given table is applicable for offshore lift in air in minor sea states, typically Hs < 2-2.5m.
DAF must be estimated separately for lifts in air at higher seastates and for subsea lifts !
Table 2.1 Pt.2 Ch.5 Sec.2.2.4.4
1. December 2010
Slide 9
1. December 2010
Slide 10
where:
SKL = Skew load factor extra loading caused by equipment and fabrication tolerances.
Fsling <
MBLsling sf
Safe working load, SWL, and MBL, of the shackle are checked by :
and
Lifting points:
The load factor f = 1.3, is increased by a consequence factor, C = 1.3, so that total design faktor, design , becomes:
A lateral load of minimum 3% of the design load shall be included. This load acts in the shackle bow !
Table 4.1
1. December 2010
Content
DNV Rules for Marine Operations, 1996, Pt.2 Ch.5 Lifting Capacity Checks
1. December 2010
Slide 14
The Recommended Practice; DNV-RP-H103 Modelling and Analysis of Marine Operations was issued april 2009 and revised 2010.
A Simplified Method for calculating hydrodynamic forces on objects lifted through wave zone is included in chapter 4.
This Simplified Method supersedes the calculation guidelines in DNV Rules for Marine Operations, 1996, Pt.2 Ch.6.
1. December 2010
Slide 15
Task :
Objectives :
Reduced Costs
Increased Safety
the horizontal extent of the lifted object is small compared to the wave length
the vertical motion of the object is equal the vertical crane tip motion
vertical motion of object and water dominates other motions can be disregarded
The intention of the Simplified Method is to give simple conservative estimates of the forces acting on the object.
1. December 2010
Slide 17
The Simplified Method is unapplicable if the crane tip oscillation period or the wave period is close to the resonance period, Tn , of the hoisting system
Tn = 2
M + A33 K
Heave, pitch and roll RAOs for the vessel should be combined with crane tip position to find the vertical motion of the crane tip
If operation reference period is within 30 minutes, the most probable largest responses may be taken as 1.80 times the significant responses
If the vessel heading is not fixed, vessel response should be analysed for wave directions at least 15 off the applied vessel heading
1. December 2010
Slide 18
8 .9
Hs g
Tz 13
Operation procedures should in this case reflect that the calculations are only valid for waves longer than:
HS g
A lower limit of Hmax=1.8Hs=/10 with wavelength 2 =gTz /2 is here used.
T z 10 . 6
1. December 2010
Slide 19
The wave amplitude, wave particle velocity and acceleration can be taken as:
a = 0 .9 H S
T z2 g
4 2 d
2 vw = a T z
e
4 2 d
2 Tz g
2 aw = a T z
d :
v w = 0 .30
g Hs e
aw = 0.10
1. December 2010
0 .35 d Hs
g e
0.35 d Hs
Slide 20
Slamming forces are short-term impulse forces that acts when the structure hits the water surface.
AS is the relevant slamming area on the exposed structure part. Cs is slamming coeff.
2 2 v s = v c + v ct + v w
vc = lowering speed vct = vertical crane tip velocity vw = vertical water particle velocity at water surface
F = V g
V = Aw a 2 + ct2
a = wave amplitude ct = crane tip motion amplitude w = mean water line area in the wave surface zone
1. December 2010 Slide 21
Varying buoyancy, F , is the change in buoyancy due to the water surface F = V g elevation.
V is the change in volume of displaced water from still water surface to wave crest or wave trough.
Drag force
Drag forces are flow resistance on submerged part of the structure. The drag forces are related to relative velocity between object and water particles.
The drag coefficient, CD, in oscillatory flow for complex subsea structures may typically be CD 2.5.
v r = vc +
vct2 + v w2
vc = lowering/hoisting speed vct = vertical crane tip velocity vw = vertical water particle velocity at water depth , d Ap = horizontal projected area
Mass force
Mass force is here a combination of inertia force, Froude-Kriloff force and diffraction force.
FM =
Crane tip acceleration and water particle acceleration are assumed statistically independent.
1. December 2010
Slide 22
The hydrodynamic force is a time dependent function of slamming impact force, varying buoyancy, hydrodynamic mass forces and drag forces. In the Simplified Method the forces may be combined as follows:
Fhyd = ( FD + Fslam )2 + ( FM F ) 2
The structure may be divided into main items and surfaces contributing to the hydrodynamic force
Water particle velocity and acceleration are related to the vertical centre of gravity for each main item. Mass and drag forces contributions are then summarized :
FM =
Di i
Mi
FD =
FMi and FDi are the individual force contributions from each main item
1. December 2010 Slide 23
The static and hydrodynamic force should be calculated for different stages. Relevant load cases for deployment of a protection structure could be:
Load Case 1
Slamming impact force, Fslam, acts on top of buckets. Inertia force to be included.
Varying buoyancy force, F , drag force, FD and hydrodynamic part of mass force, FM are negligible.
Load Case 2
Varying buoyancy, F , drag force, FD and mass force, FM, are calculated. Velocity and acceleration are related to CoG of submerged part of structure.
1. December 2010 Slide 24
Load Case 3
Varying buoyancy, F , drag force, FD and mass force, FM are calculated on the rest of the structure. Drag- and mass forces acts mainly on the buckets and is related to a depth, d, down to CoG of submerged part of the structure.
Load Case 4
Drag force, FD and mass force, FM are calculated individually. The total mass and drag force is the sum of the individual load components, e.g. : FD= FDroof + FDlegs+ FDbuckets applying correct CoGs
1. December 2010 Slide 25
1. December 2010
Slide 26
Capacity Checks
The capacities of crane, lifting equipment and lifted object are checked as for lift in air. The following relation should be applied:
Ftotal DAF = Mg
where Fstatic-max is the maximum static weight of the submerged object including flooding and weight inaccuracy factor Fhyd is the hydrodynamic force Fsnap is the snap load (normally to be avoided)
1. December 2010 Slide 28
Ftotal : is the characteristic total force on the (partly or fully) submerged object. Taken as the largest of;
Snap forces shall as far as possible be avoided. Weather crietria should be adjusted to ensure this.
The following criterion should be fulfilled in order to ensure that snap loads are avoided:
Fstatic-min = weight before flooding, including a weight reduction implied by the weight inaccuracy factor.
1. December 2010
Slide 29
A33 = 0.76
a2 b
1. December 2010
Slide 30
A33/A33o
1.1 1 0 0.5
The following simplified approximation of the added mass in heave for a three-dimensional body with vertical sides may be applied :
1 2
and
=
h + Ap
Ap
1.5
ln [ 1+ (h/sqrt(A)) ]
A33 1 +
A 33o 2( 1 + 2 )
2.5
where
A33o = added mass for a flat plate with a shape equal to the horizontal projected area of the object
A volume of water partly enlosed within large plated surfaces will also contribute to the added mass, e.g.:
The volume of water between large plated mudmat surfaces and roof structures.
1. December 2010
Slide 32
Recommended reduction:
if p< 5
if 5 < p < 34
e^-P/28 BucketKC0.1-H4D-NiMo BucketKC0.6-H4D-NiMo BucketKC1.2-H4D-NiMo BucketKC0.5-H0.5D-NiMo BucketKC1.5-H0.5D-NiMo BucketKC2.5-H0.5D-NiMo BucketKC3.5-H0.5D-NiMo PLET-KC1-4 Roof-A0.5-2.5+ Hatch20-KCp0.5-1.8 Hatch18-KCp0.3-0.8 BucketKC0.1 BucketKC0.6 BucketKC1.2 RoofKCp0.1-0.27 RoofKCp0.1-0.37 DNV-Curve Mudmat CFD
A33 =e A33 S
No reduction applied in added mass when perforation is small. A significant drop in the added mass for larger perforation rates. Reduction factor applicable for p<50.
1. December 2010 Slide 33
10 p 28
if 34 < p < 50
1. December 2010
Slide 34
Highest upwards hydrodynamic force when bucket is fully submerged occurs when the object is located in a wave trough.
Buoyancy, Vg
1. December 2010
Slide 35
Content
DNV Rules for Marine Operations, 1996, Pt.2 Ch.5 Lifting Capacity Checks
1. December 2010
Slide 36
Criteria :
Static and dynamic loads on lifted structure, crane, cable and rigging shall not exceed capacity requirements
Challenges :
The resonance period of the lifting system increases with cable length. Dynamic forces may increase due to resonant amplification induced by the vertical crane tip motion.
the subsea structure is lowered into deepwater and is unaffected by wave forces
the vertical motion of crane tip and subsea structure dominates other motions can be disregarded
RAO in heave, pitch and roll are combined in order to find the vertical motion at the crane tip
Dynamic force computed applying harmonic oscillation at crane tip with period T=9s and amplitude a=1m
Dynamic force slightly larger at the crane tip than at the lifted object
Transfer functions for dynamic load in cable and crane tip motion are combined with a wave spectrum S()
Most probable largest response for dynamic force in cable is found by:
A duration time t =30 minutes gives Fd=530kN in this case
Fd<0.9*Fstatic in order to avoid risk of snap loads due to slack slings; Fd < 68t
Capacity requirement of crane and cable governs for cable lengths above L>2250m due to weight of cable
.. Questions ??
1. December 2010
Slide 49
1. December 2010
Slide 50