Beruflich Dokumente
Kultur Dokumente
A PROJECT REPORT
Submitted by
of
BACHELOR OF ENGINEERING
in
MECHANICAL ENGINEERING
BONAFIDE CERTIFICATE
India Private Limited who carried out the project work under my supervision.
SIGNATURE SIGNATURE
ii
CERTIFICATE OF EVALUATION
S.No Name of the Title of the project Name of the internal guide
students
3. S. Santhakumar
(11808114092)
record of work done by the above students who carried out the project work under our
guidance during the year 2011- 2012 in partial fulfillment of the award of Bachelor of
iii
ACKNOWLEDGEMENT
We take this opportunity to express our sincere gratitude to our chairman Col.
D.Sc for his kind words and enthusiastic motivation which has inspired us a lot in
M.E, Ph.D for being a source of inspiration throughout my study in this college.
We thank our Head of the Department Mr. M. K. Jawahar, M.E and our
internal guide Mr. D Satish Kumar M.B.A, M.E (Ph.D) for their guidance and
encouragement at each and every stage of our project work and also guiding us
With profound respect, we express our deep sense of gratitude and sincere
thanks to our external guides, Mr. S Ram Kumar (Manufacturing Engineer – CCS)
and Mr. D. Karthikeyan (Design Engineer-CCS) for their invaluable guidance and
iv
Space for pasting project
certificate
v
TABLE OF CONTENTS
ABSTRACT xi
LIST OF TABLES ix
LIST OF FIGURES x
1. INTRODUCTION 1
2. LITERATURE REVIEW 6
vi
3.4 FOURTH CONCEPT WORKING 13
3.4.1 Advantage 14
3.4.2 Requirements 15
3.5 FIFTH CONCEPT WORKING 15
3.5.1 Advantages 15
3.6 RESULTS AND DISCUSSIONS 17
4. FINAL MODEL 18
4.1 REQUIREMENTS 18
4.2 FINAL MODIFICATIONS IN FIFTH 18
CONCEPT
4.3 STANDARD PARTS AVAILABLE 20
4.3.1 Pneumatic compact cylinders 20
4.3.1.1 Application 21
4.3.2 Stopper Cylinders 21
4.3.2.1 Application 21
4.3.3 Linear Swivel Clamp cylinder 22
4.3.3.1 Application 22
4.3.4 Induction Motor 22
4.3.4.1 Application 23
4.3.5 Proximity Sensors 23
4.3.5.1 Application 24
4.4 PARTS TO BE FABRICATED 24
4.5 ASSEMBLY OF THE FINAL MODEL 28
PROPOSED
4.6 MATERIALS USED 29
4.6.1 Mild Steel 29
4.6.2 Aluminum 30
4.6.3 Nylon 31
vii
5. COST ANALYSIS 32
6. CONCLUSION 45
7. REFERENCES 46
8. APPENDICES 47
viii
LIST OF TABLES
ix
LIST OF FIGURES
x
ABSTRACT
minute problems affected the final output. So a problem that created many issues in
The problem criteria relates with the post tube milling process that is the condenser
and radiator tube cleaning. The present cleaning method is done manually.
Limitations of the present method are that the tubes are produces at high speeds (for
example 240 tubes/ min). It is not possible to control the rate of production of the
tubes, so it requires more manpower for the cleaning process. It leads to many
manpower is required, remains of burrs and coolant, more time is required for the
entire process.
This project is aimed to design an automation process for this on going issue. In
total, 5 concepts were modeled in CATIA. The fifth concept was accepted by
Visteon for which complete modeling, drafting and costing was done. Since the
less manpower, customer satisfaction, work accuracy and cost effective process.
xi
CHAPTER 1
INTRODUCTION
Visteon Automotive India Private Ltd was established in the year 1997. Their
key products are classified under 4 different sections namely,
i. Interiors
ii. Lighting
iii. Electronics
iv. Climate
This project is assigned under the Climate Control Division. Three scopes were
defined, namely lean manufacturing, quality improvement and machine system
development. Visteon mainly concentrates on the quality of their product, hence
Quality improvement is chosen.
1
iv. Remains of burrs and coolant
v. Complaint from customer end since manual cleaning process is not efficient
vi. More time is required for the entire process
Our project concern is to design an automation process for this on going issue.
2
cleaned and moreover maintenance of the setup is the major problem in this type of
cleaning.
Focus Focus
Area Area
Manual loading
In trays
Core
Assembly Focus
Area
3
1.3 TUBE DATA AND DIMENSIONS
Condenser and Radiator tubes are manufactured with different dimensions in
Visteon in order to meet the requirements of the customer. Maximum tube length is
approximately 700mm and minimum length is around 346mm. The various
dimensions of the radiator tube part family are shown in Table 1.1. Condenser and
radiator tube are manufactured in the same way through the milling process. The tube
resembles a scale which is hollow as shown in Figure 1.3.
702 mm
18.5 mm
4
1.4 CAUSE AND EFFECT FOR INEFFECTIVE CLEANING
After considerations and experimentations, it is found that the various reasons
for ineffective cleaning is based on the 4M’s which are Man , Machine, Material and
Method as shown in figure 1.4.
The physical ability of a person mainly depends upon his strength, skill and
training. When any one of these is lacking then there is a possibility for ineffective
cleaning. Here the machine indicates the Tube Mill. The tube mill has a cutting speed
of around 4 cuts per second. Since the machine speed is too high it requires the tube
being milled requires coolant which becomes the main reason for the post tube mill
cleaning process
The method of cleaning is completely dependant upon the manual labor. So the
first set would be perfectly cleaned whereas at the end of the shift, there would be a
drop in the efficiency of cleaning. Material properties have a greater effect. While
brazing a material, if it not done properly then remains of burrs would lead to
problems like erosion.
Man Machine
Speed
Training
Training
Skill
Skill Lubricant
Strength
Strengt
h
Coolant Ineffective
Cleaning
Cost Manual
Properties cleaning
Brazing Stacking
Material Method
2.1.1 Aluminium
Aluminium is a lightweight, reasonably cheap metal widely used for packaging
and transport. It has only been widely available and used for the last 60 years. Raw
aluminium has low strength and high ductility (ideal for foil). Strength is increased by
alloying, e.g. with Si, Mg, Cu, Zn, and heat treatment. Some alloys are cast, others are
used for wrought products. Aluminium is quite reactive, but protects itself very
effectively with a thin oxide layer. The surface can be "anodized", to resist corrosion
and to give decorative effects. Design strengths are high strength-to-weight ratio,
high stiffness-to-weight ratio, high electrical and thermal conductivity, easy to shape
and easy to recycle. Design weaknesses are the difficulty to arc weld.
Steels are the most important engineering materials, and cover a wide range of
alloys based on iron and carbon. The strength of iron-carbon alloys, particularly after
heat treatment, has been exploited for thousands of years (since the "Iron Age").
6
Modern steels and ferrous alloys have mostly been developed since the Industrial
Revolution. Mild steel contains 0.1-0.2%C. They are cheap, strong steels used for
construction, transport and packaging. All steels have a high density and a high
Young's modulus. The strength of mild steel is improved by cold working. It is
inherently very tough. Mild steel rusts easily, and must be protected by painting,
galvanizing or other coating. Design strengths are high strength-to-weight ratio, high
stiffness-to-weight ratio, and good strength with high toughness, high stiffness very
cheap, easy to shape, easy to weld and easy to recycle. Design weaknesses are high
density, poor electrical and thermal conductivity.
Figure 2.1 indicates the variation of Young’s modulus and density for various
materials
7
CHAPTER 3
AUTOMATION IN TUBE CLEANING AND STACKING PROCESS
Hopper
Secondary
conveyor
Main
conveyor
Blowing
holes
9
3.1.1 Limitations
i. Tubes with different dimensions cannot be arranged.
ii. Since the tubes are produced at 240 pieces/min (average) it is very difficult to
arrange in a single plane.
iii. Slip of tubes may occur frequently.
iv. Cleaning is not done completely.
v. Frequent monitoring is required. Thereby increasing the labor cost.
vi. Automation is less.
Loading
end
Unloading
end
3.2.1 Limitations
i. It is a semi-automatic process. Automated stacking is not possible which the
main target is.
ii. The setup is not cost efficient.
iii. Blowing cannot be done for different dimensions.
iv. Many number of moving parts.
Plate B
Stacker A
Plate A
Stacker B
Arm A
Arm B
13
3.4.1 Advantages
i. Fully automated.
ii. The setup is cost efficient in concern to the previous concept.
iii. Less number of moving parts.
iv. Less manpower is required.
v. Slip of tubes is not possible.
vi. Payback years are less.
Vertical arm
Hopper
Unloading
end
Bin Loading
14
3.4.2 Requirements
i. Minute modifications required for satisfying cost factor.
ii. Alternate method to replace Servo mechanisms.
iii. Base and support columns should be provided to the entire setup.
3.5.1 Advantages
i. Cost efficient.
ii. Servo parts are completely eliminated.
15
iii. A single labor is enough to maintain the whole process whereas, currently 5
labors are required.
iv. Any dimension can be cleaned.
v. Payback years are less.
vi. No complication in automation.
Arm A
Stacker 1
Linear
guide rail
Suction
unit
Linear rotary
clamp cylinder
Cleaning
area
16
3.6 RESULTS AND DISCUSSIONS
In total, 5 concepts were made in due course of finalizing the design concept of
tube cleaning semi automatic process
1st Concept – cannot clean tubes of different dimensions, slip of tubes and
ineffective cleaning
2nd Concept – too many moving parts, cost is high
3rd Concept – space constraints were imposed
4th Concept – semi automatic process was requested due to cost factor
The 5th Concept was accepted by Visteon since number of elements used is less, cost
was less and it is a semi automatic process. Standardization of elements was adopted
in the 5th Concept. Automation products for standardization were referred from
MISUMI, SMC, FESTO books and catalogues.
17
CHAPTER 4
FINAL MODEL
The Fifth concept was accepted by Visteon in which certain modification was
required in terms of implementation. FESTO, MISIMI and SMC are the leading
producers of automated parts. So standardization of parts was referred from those
catalogues.
4.1 REQUIREMENTS
After certain considerations such as space, damage to parts and implementation,
the following changes were required
i. Linear guide for the suction unit should be provided so that for different
dimensions, the suction unit can be adjusted.
ii. Another cylinder mechanism to transfer tubes from stacker 1 to stacker 2 so
that damage of tubes can be eliminated.
iii. Columns supporting cylinders can be replaced by L clamp structures as
holding device in order to reduce space.
18
iii. L clamp structures were provided for cylinders (as in Figure 4.1) as holding
devices in order to reduce space.
L clamp
structure
Additional
cylinder
19
4.3 STANDARD PARTS AVAILABLE
The standardization of parts was done. MISUMI FESTO and SMC catalogues
and books were referred for the standard parts available. Cylinders such as linear
cylinders, stopper cylinders and linear rotary clamp cylinders were chosen. Sensors
and control valves come along with the cylinders. Exceptional to cylinders, three other
places require sensors for part detection so inductive proximity sensors are used. The
linear guide is driven by induction motor.
20
4.3.2.1 Application
Except stopper cylinder and twist cylinders, other cylinders used in this
automation process are pneumatic compact cylinder.
4.3.2.1 Application
This cylinder is been used to stop/ lock the cylinders once it has been dropped
into the stacking end and also to hold the bin while cleaning process takes place.
21
4.3.3 Linear swivel clamp cylinders/ twist cylinders
Twist Clamp Cylinder combines linear and 90-degree rotary motion with an
internal pin/cam mechanism (a typical twist cylinder is shown in Figure 4.4). The
rotary action moves a clamping arm away from the work piece, allowing for easy
loading and unloading of parts. As the cylinder extends, the pin follows the groove
and creates 90 degrees of rotary motion
4.3.3.1 Application
The linear swivel clamp cylinder/ twist cylinder is used to twist the position of
stacker 2 from vertical to horizontal so that it drops the tubes in the stacking end.
22
in small appliances. Their speed is determined by the frequency of the supply current,
so they are most widely used in constant-speed applications, although variable speed
versions, using variable frequency drives are becoming more common. The
advantages of using an induction motor are that it is maintenance free, four quadrant
operations are possible and losses are less.
4.3.4.1 Application
Here Induction motor is used to drive the linear drive over which the vertical
arm is used to slide horizontally.
4.3.4.1 Application
The proximity sensors are used here to sense the part in stacker 1, presence of
tubes in the stacking end and cleaning process completion
The standard parts are readily available in the market, but certain parts have to
be machined according to the requirements. The major parts are the Bottom Support,
Extracting end plate, Guide column, Linear guide rail, Linear guide slide, Stacker 1,
24
Stacker 2, Stacker 1 & 2 Tube carry, Tube locker, Stacking end plate and Unloading
end plate as shown in Table 4.1.
4. Guide rail
25
5. Guide slide
6. Guide column
7. Stacker 1
8. Stacker 2
26
9. Tube locker
27
13. Stacker1 Tube carry
15. Extractor
Figure 4.7 indicates the overall view of the model with all the standards parts
and the other parts listed in table 4.1
28
Figure 4.7 Assembly of the final model proposed
4.6.2 Aluminium
Aluminium is the third most abundant element (after oxygen and silicon), and
the most abundant metal, in the Earth's crust. It makes up about 8% by weight of the
Earth's solid surface. Aluminium metal is too reactive chemically to occur natively.
Instead, it is found combined in over 270 different minerals. The chief ore of
aluminium is bauxite. Aluminium is remarkable for the metal's low density and for its
ability to resist corrosion. The most useful compounds of aluminium, at least on a
weight basis, are the oxides and sulfates. Despite its prevalence in the environment,
aluminium salts are not known to be used by any form of life. The yield strength of
pure aluminium is 7–11 MPa, while aluminium alloys have yield strengths ranging
30
from 200 MPa to 600 MPa. Aluminium has about one-third
the density and stiffness of steel. It is easily machined, cast, drawn and extruded. It
has the following advantages:
i. Corrosion resistant
ii. Excellent strength-to-weight ratio
iii. High thermal electrical conductivity
iv. Durable
v. Reflective
vi. Non-combustible
vii. Does not spark
4.6.3 Nylon
31
CHAPTER 5
COST ANALYSIS
Material cost was established for the individual parts based on the weight,
density and cost per kg. The standard part’s cost were referred from Visteon’s
suppliers such as MISUMI and FESTO
i. BOTTOM SUPPORT
Bottom support
Leg
33
Legs for bottom support
Diameter = 0.1 m, thickness = 0.07 m, density = 7860 kg/m3
Material = Mild Steel
Volume = r2 h
= 3.14 X 0.052 x 0.07
Volume = 0.0005495 m3
Mass = Density x Volume
= 7860 x 0.0005495
Mass = 4.324 kg
Total Mass (6 nos.) = 4.324 x 6 = 25.94 = 26 kg (approx.)
Cost of Mild Steel = 70 per kg
Material Cost = 26 x 70
Material Cost = Rs. 1820.000
Leg
35
iii. EXTRACTING END PLATE
Secondary plate
Legs
Secondary plate
Diameter = 0.460 m, thickness = 0.050 m, density = 2700 kg/m3
Material = Aluminium
36
= 2700 x 0.0023
= 6.21 kg
Cost of Aluminum = 300 per kg
Material Cost = 6.21 x 300 = Rs. 1863.000
Volume = r2 h
= 3.14 x 0.042 x 0.08
= 0.0004 m3
Total Volume (4 nos.) = 0.004 x 4
= 0.0016 m3
37
iv. STACKING END PLATE
Secondary plate
Legs
Secondary plate
Diameter = 0.230 m, thickness = 0.350 m, density = 2700 kg/m3
Material = Aluminium
38
= 0.0008 m3
Volume = r2 h
= 3.14 x 0.042 x 0.08
= 0.0004 m3
Total Volume (4 nos.) = 0.004 x 4
= 0.0016 m3
39
v. STACKER 2
Length= 0.800 m, breadth = 0.420 m, thickness= 0.035 m, density = 2700 kg/m3
Material = Aluminum
Guide column
Leg
Base plate
Similarly the costs for other parts were calculated and the entire estimate was
made. The Bill of Materials includes the details about the material used; density of the
respective material used, dimensions such as length, breadth, thickness, diameter,
mass and volume are indicated. The material cost/ kg indicates the price of the
material currently available in market. Costs of standard parts available in market are
also included. Material costs are calculated for every part and overall material cost is
estimated to be Rs. 143631.470. The machining cost for the entire setup accounts to
Rs. 29050 (more details in Appendix 3). Hence the overall cost including material and
machining cost accounts to Rs 172681.47
41
Table 5.2 Bill of Materials
S No. Product Part Number Type Source Quantity Dimensions Material Approx.
Description mm Cost
1. Bottom support Part 1 1850*1450 / Thick Mild Steel 46153.000
100
2. Unloading end Part 1 800*500 / Thick 10 Aluminum 4536.000
/ leg dia 80 / thick
80
3. Extracting end Part 1 830*370,460*50 / Aluminum 3969.810
Thick-10 / leg dia
80 / Thick 80
4. Stacking end Part 1 1000*450/Thick Aluminum 5593.050
10/230*350/thick
30/Leg dia 80/
Thick 80
5. Guide column Part 2 1500*100/thick 20/ Tube( 9384.975
LEG- square)
100*100/Thick
20/50*50/thick 500
6. Stacker2 Part 1 800*35/thick 420 Aluminum 6075.000
42
21. Horizontal Part 1 1035*100 / thick 20 Mild Steel 254.500
column of
linear guide
22. Vertical 150921 SLE- Assembly Festo 1 Cadenas 2000.000
Support 50-480-KF-A- PARTsolutio
Cylinder G
Table 5.3 Analysis and comparison of cost for the five concepts
CONCEPT NO. ANALYSIS AND COST COMPARISION
43
4 Automation requirements are fulfilled. Number of servo
mechanisms is reduced.
5 Automation requirements are fulfilled. All heavy moving
parts are eliminated. Servo mechanisms are also eliminated.
44
CHAPTER 6
CONCLUSION
The problems in manual cleaning of condenser and radiator tubes are erosion in
tubes; stacking of tubes is difficult; more manpower is required; remains of burrs and
coolant; more time is required for the entire process. To overcome these problems
automation is recommended. Accordingly, five concepts were developed and 3D
models were generated in CATIA. The fifth concept meets all the requirements such
as automated stacking; automated loading of tubes in bins and automated cleaning. It
would benefit them in terms of automation, less manpower, customer satisfaction and
work accuracy. Standardization of parts and costing were done. The cost of the fifth
model is less when compared to the other four because the investment in this
automation process is less and has minimum number of payback years. Hence fifth
model is recommended for the automation of condenser and radiator tubes stacking
and cleaning process.
45
CHAPTER 7
REFERENCES
Websites
1. www.festo.com
2. www.us.misumi-ec.com
3. www.smcin.com
46
APPENDIX 1
Gantt Chart of Project Timeline in Visteon
47
APPENDIX 2
Project review in Visteon
48
APPENDIX 3
Total cost including material and machining cost for the final model
49