ABDUL WAHAB ORAKZAI UNIVERSITY OF AZAD JAMMU AND KASHMIR MUZAFFARABAD SESSION 2008-2012
2.
3.
EMPLOYER
(WAPDA)
CONSULTANTS
KHAN KHWAR
HYDROPOWER PROJECT
INTRODUCTION
The Khan Khwar HPP is located on the river Khan Khwar, a right bank tributary of the River Indus in the Shangla District (KPK). The intake structure is located on the right bank of Khan Khwar. The diverted water crosses the ridge between Khan Khwar valley and Indus valley via an underground water way conduit of some 5.14km length. The Powerhouse is located at the right bank of Indus River. The maximum power output of this plant will be 72 MW, corresponding to a turbine design discharge of 35 m3/s at a max. gross-head of 257 m. The Khan Khwar HPP will produce an annual energy of some 306 GWh, out of which approximately 105 GWh/a will be available during a 04 hour/day period of peaking operation.
2) KE-04 (E&M) i. Contract price ..Rs 732.445 mil. (original) Rs. 848.880 mil. (revised) ii. Schedule Completion Date/Period .Oct 11, 2008 (46 Months) after Approval of EOT of 362 days
2. Weir Structure
Type Height Above River Bed Crest Length Crest Elevation
3. Stilling Basin
Length Width
60 m 54 m
4. Headrace Tunnel
Type Length Size Discharge Capacity Circular 4535 m 3.85 m (int. dia) 35 m3/sec. External 50.7 x 33.6 x 39.0m 50.7 x 19.6 x 16m 586.00 masl
5. Powerhouse
Type Size Machine Hall Machine Hall Floor Ele.
6. Pressure Shaft
Length of Shaft Shaft Size (dia) 183m 3.25 m
125 m 3.25 m
8. Tailrace Tunnel
Covered Tunnel Length Open Channel Length
9. Head
Max. Operation Level Min. Operation Level Max. Gross Head Min. Gross Head
MAIN FEATURES
Electro Mechanical 1. Hydro Mechanical Equipment 2 No a Francis Turbines
Speed Discharge 500 rpm 16.5 m3 / s (each) 01 No 428 rpm 02 m3/s 2 No. Generators 500 rpm 34 MW (each)
b Auxiliary Unit
Speed Output 428 rpm 04 MW
3. Energy Output
72 MW
306 GWH
Remaining Work:
Under MOU # 2 approved by the authority Pak Rs. 1,100.0 Million (i.e. including payment against Contractors claim for construction Power Supply, as already determined by the Engineers) shall become payable to the Contractor as final claim / dispute settlement. The Contractor was to be ensure completion of following mile stone: 1. Mile-Stone No. 25 (water re-system ready for commissioning by September 30, 2010). 2. Mile-Stone No. 24 (filling of reservoir by October 01, 2010 ). The Contractor could not achieve the desired targets. Remaining works are now scheduled to be completed by end March 2012.
Physical Progress KC-01 KE-04 (E&M) 100 99.75 100 99.7 Cost Per Unit = 2.28 US Cents.
Total Generation Since November, 2010 Unit # 1 = 92.711 GW-Hrs Unit # 2 = 108.464 GW-Hrs Auxiliary = 0.045 GW-Hrs Total Generation upto December 25, 2011
201.220 GW-Hrs