Sie sind auf Seite 1von 22

GEOLOGIST

ABDUL WAHAB ORAKZAI UNIVERSITY OF AZAD JAMMU AND KASHMIR MUZAFFARABAD SESSION 2008-2012

WELCOME TO INDUS TRIBUTARIES HIGH-HEAD COMPLEX PROJECTS

INDUS TRIBUTARIES HIGH HEAD HYDROPOWER COMPLEX PROJECTS BESHAM


1.

KHAN KHWAR HYDROPOWER PROJECT

2.
3.

DUBER KHWAR HYDROPOWER PROJECT


ALLAI KHWAR HYDROPOWER PROJECT

EMPLOYER

WATER AND POWER DEVELOPMENT AUTHOURITY

(WAPDA)

CONSULTANTS

HIGH-HEAD CONSULTANTS (HHC)

HIGH-HEAD CONSULTANTS (HHC) A JOINT VENTURE OF


1. NATIONAL DEVELOPMENT CONSULTANTS.
2. LAHMEYER INTERNATIONAL GmbH, GERMANY. 3. BAK CONSULTING ENGINEERS.

4. PAKISTAN ENGINEERING SERVICES.


5. ENGINEERING GENERAL CONSULTANTS. 6. INFRA-D CONSULTANTS.

7. BARQAAB CONSTLTING SERVICES.


8. DEVELOPMENT MANAGEMENT CONSULTANT. 9. REVIEW CONSULTANTS.

KHAN KHWAR
HYDROPOWER PROJECT

KHAN KHWAR HYDROPOWER PROJECT


CONTRACTORS
1. 2. CIVIL CONTRACTOR E&M CONTRACTOR SINOHYDRO DONG FANG

INTRODUCTION
The Khan Khwar HPP is located on the river Khan Khwar, a right bank tributary of the River Indus in the Shangla District (KPK). The intake structure is located on the right bank of Khan Khwar. The diverted water crosses the ridge between Khan Khwar valley and Indus valley via an underground water way conduit of some 5.14km length. The Powerhouse is located at the right bank of Indus River. The maximum power output of this plant will be 72 MW, corresponding to a turbine design discharge of 35 m3/s at a max. gross-head of 257 m. The Khan Khwar HPP will produce an annual energy of some 306 GWh, out of which approximately 105 GWh/a will be available during a 04 hour/day period of peaking operation.

PROJECT IMPLEMENTATION DATA


PC-1 Cost Approved...Rs. 8301.479 Million 1) KC-01 (LOT C&HS) i. Contract Price ......Rs.1816.259 mil. (original) Rs. 3542.047 mil. (revised) ii. Date of Issuance of Construction Order (Contract).June 16, 2003 iii. Date of Issuance of Construction Order (Actual)..Jan 12, 2005 iv. Schedule Date of Completion/Period ........Oct 11, 2008 (46 months) after Approval of EOT of 362 days. v. Date of Completion as per MOU # 2...Feb 15, 2011 vi. As Per Contractors Revised Work Schedule .Mid February, 2012

2) KE-04 (E&M) i. Contract price ..Rs 732.445 mil. (original) Rs. 848.880 mil. (revised) ii. Schedule Completion Date/Period .Oct 11, 2008 (46 Months) after Approval of EOT of 362 days

MAIN FEATURES Weir Site


1. Reservoir
Total Storage Capacity Live Storage Capacity Length
1.05 Million m3 0.40 Million m3 1.60 km Concrete Gravity 29 m 116 m 829 masl

2. Weir Structure
Type Height Above River Bed Crest Length Crest Elevation

3. Stilling Basin
Length Width

60 m 54 m

4. Headrace Tunnel
Type Length Size Discharge Capacity Circular 4535 m 3.85 m (int. dia) 35 m3/sec. External 50.7 x 33.6 x 39.0m 50.7 x 19.6 x 16m 586.00 masl

5. Powerhouse
Type Size Machine Hall Machine Hall Floor Ele.

6. Pressure Shaft
Length of Shaft Shaft Size (dia) 183m 3.25 m

7. Pressure Tunnel a. Concrete Lined Section


Length Size (Int. dia.)

125 m 3.25 m

b. Steel Line Section


Length Size (Int. dia) 290m 3.00 m
41 m 17 m 825 masl 818 masl 257 m 247 m

8. Tailrace Tunnel
Covered Tunnel Length Open Channel Length

9. Head
Max. Operation Level Min. Operation Level Max. Gross Head Min. Gross Head

MAIN FEATURES
Electro Mechanical 1. Hydro Mechanical Equipment 2 No a Francis Turbines
Speed Discharge 500 rpm 16.5 m3 / s (each) 01 No 428 rpm 02 m3/s 2 No. Generators 500 rpm 34 MW (each)

b Vertical Pelton Turbine


Speed Discharge

2. Electrical Equipment a Main Units


Speed Output

b Auxiliary Unit
Speed Output 428 rpm 04 MW

3. Energy Output

72 MW

4. Mean Annual Energy

306 GWH

CONSTRUCTION ACTIVITIES AT Weir Site


Weir Structure , Power Intake, Headrace Tunnel, Powerhouse, Switchyard, Pressure System and Surge System are 100 % completed.

Remaining Work:
Under MOU # 2 approved by the authority Pak Rs. 1,100.0 Million (i.e. including payment against Contractors claim for construction Power Supply, as already determined by the Engineers) shall become payable to the Contractor as final claim / dispute settlement. The Contractor was to be ensure completion of following mile stone: 1. Mile-Stone No. 25 (water re-system ready for commissioning by September 30, 2010). 2. Mile-Stone No. 24 (filling of reservoir by October 01, 2010 ). The Contractor could not achieve the desired targets. Remaining works are now scheduled to be completed by end March 2012.

OVERALL FINANCIAL AND PHYSICAL PROGRESS


Contract no. Planned Progress (%age) Actual Progress (%age)

Physical Progress KC-01 KE-04 (E&M) 100 99.75 100 99.7 Cost Per Unit = 2.28 US Cents.

Total Generation Since November, 2010 Unit # 1 = 92.711 GW-Hrs Unit # 2 = 108.464 GW-Hrs Auxiliary = 0.045 GW-Hrs Total Generation upto December 25, 2011

201.220 GW-Hrs

THANK YOU

Das könnte Ihnen auch gefallen