Beruflich Dokumente
Kultur Dokumente
Study of factors affecting project cost, risk analysis and financial modeling of UMPP
Introduction
Why UMPP?
Economies of scale, supercritical technology Power a key driver of growth Demand supply mismatch Why the project? Understanding the decision variables, financial modeling and analysis To understand as to how costs can change with project
Risk
Land Requirement (Hectares) Land Costs (in Rs Cr) Use of Land Plant Area Ash disposal Employees Colony Road from colony to plant Corridor Ash Pipe Intake Water Pipeline Coal Mine Land Requirement for Project Resettlement and Rehabilitation Total Total 818.98 329.74 181.53 MGR Land 80 13.73 Water & Ash Pipeline Corridor 1 0.73 Total 6.34 2965.00
Coal Block land costs Land Afforestation of Forest Land R&R
Land
R&R
Total
34
114
191
170
361
4,316.05
Total
192.62
Total
142
4,508.67
35
75
19
271
Project
Capacity (MW)
Sasan UMPP (excluding apportioned Coal Block Development cost) APL Phase-III (Including Coal Supply Advance) NTPC Sipat Phase I
3960
6606
16,243
4.10
1320 1980
6602 6603
5,796 8,323
4.12 4.20
Tata UMPP
NTPC Barh Cuddalore Power
4000
1980 1320
8005
6603 6602
17,024
8,693 6,379
4.26
4.39 4.83
PFC long term State(Category 'A+')/ CPSUs/ AAA rated Companies State (Category 'A')/ Central/ Private(IR-1)
Private Sector
BORROWER
IR2/ E I & E II
IR-4
Generation
12
12.25
12.75
13
13.25
13.5
Coal
Parameters Base Case Station Heat Rate =2175 kcal/kWh Increae in Aux. Consumption by 0.5% Decrease in PLF by 5%
10.13% 10.38%
1.32 1.35
1.06 1.06
Risks
10.1 Fuel Availability and Fuel Price Risk 10.2 Demand Risk 10.3 Payment Risk 10.4 Land Acquisition & Environmental Clearances 10.5 Financial Risk 10.6 Foreign Exchange Risk 10.7 Political Risk 10.8 Regulatory/Policy Risk 10.9 Equipment Shortage 10.10 Manpower Shortage 10.11 Technology Risk 10.12 Interest Rate Risk 10.13 Performance Risk 10.14 CDM Risk
Severity High
High
Project
Sponsor
or
DISCOM Long
Term
contracts
with
proper
escalation
clauses,
Vertical Integration Escrow Mechanism for central and state utilities; Trust and Retention Account for others.
Medium
Medium Medium Medium Low
Project Sponsor
Project Sponsor EPC Contractor Project Sponsor Project Sponsor Project Sponsor Project Sponsor Project Sponsor Project Sponsor Project Sponsor Project Sponsor Upgrade technology generation plant or with new diversify Training Long Term PPAs Involve all the stakeholders and negotiate directly Fixed Rate loan, Refinancing Penalty Clause
Land Acquisition and Environment High Medium Medium Medium Medium Low
Low
Equipment Manufacturer
Financial Modeling
To study the effect of factors mentioned in the report, a financial model was made taking suitable assumptions where applicable. The model used Discounted Cash Flow method for arriving at the NPV and IRR figures. Indicators calculated NPV IRR Project Equity Equity NPV NPV (Rs) 6336.741 4213.449 Equity IRR IRR 12.47% 21% DSCR DSCR (min) 1.84
*NPV = Cr INR
EBIT
4500.00 4000.00 3500.00 3000.00 2500.00 2000.00 1500.00 1000.00 500.00 0.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 EBIT
7000.00 6000.00 5000.00 4000.00 3000.00 2000.00 1000.00 0.00 1 2 3 4 5 6 7 8 9 10 Debt Payments NOI
DSCR
NPV Risk analysis with Changing Coal price (1.8 to 3.6 Kg)
IRR Risk analysis with Changing PLF (95 mean and 5% Std deviation)
Entire range is from 19% to 23% Base case is 21%
Thank You