PROJECT STATUS AND UPDATES AS OF 15 OCTOBER 2012

A. Civil Works and Building Component

Substantially completed Remaining works are the interfacing items with the Air Navigation System and Support Facilities (ANSSF) component such as the duct banks and the testing and commissioning of equipment installed in all buildings

98.66%

B. Air Navigation System and Support Facilities (ANSSF) Component


Procurement Process is Ongoing The invitation for bid was published on 13 July 2012 Submission and opening of bids were undertaken on 29 August 2012. With the additional 3 months contract duration required by EDCF, the project is expected to be completed in January 2014. Bid evaluation is ongoing.

C. Operation and Maintenance (O&M) of the Laguindingan Airport


Deloitte Touche Tohmatsu, the Transaction Advisor has submitted the O&M study in June 2012 and is still under review by DOTC

D. Planned Commercial/Soft Opening of the Laguindingan Airport


Per instructions from DOTC SMar and in coordination with CAAP, the airport is planned to open in January 2013 using Visual Flight Rule (VFR)

Taxiway

Apron

Runway

Pavement Markings

Pavement Markings Storm Drainage

Pavement Markings

Sodding

Perimeter Fence & Road

Passenger Terminal Bldg

Cargo Terminal Bldg

Operation & Control Tower Bldg Crash Fire & Rescue Bldg Administration Bldg Power House Bldg

Cold Water Receiving Station

Maintenance Bldg

Guard House

Car Parking Area

Car Parking Area

Sewage Treatment Plant

Landscaping

Landscaping

Landscaping

Landscaping

Landscaping

Landscaping

Ambulance

Grass Cutter

Tractor & Cart

Departure Area

Initial Security Check Automated Weighing Scale & Conveyors

Check-in Counters

Escalatorr

Elevator @ Departure Area

Wicket Counters

CCTV Camera

Final Security Check

Inspection Benches

Departure Lounge

Gang Chair

Gate 1

Gate 2

Gate 3

CIP Lounge

VIP Lounge

Boarding Bridge

Hallway @ Boarding/Arrival

Elevator @ Arrival

Baggage Handling Carousel

Baggage Handling Carousel Arrival Exit

CCTV Camera @ Arrival Area

Dome Type CCTV Camera @ Arrival Area

Information Counters

FIDS @ Arrival Arrea

VHF Bipole Antenna

Weather Instruments

ACTIVITIES
1. 2. Provision of Makers & Markings Coms(Tower) Equipment 2a. 2b. 2c. 3. Site Preparation Mobilization & Installation Testing

Office-InCharge
LADP-PMO CAAP LADP-PMO CAAP CAAP LADP PMO

2012 Sept Oct Nov Dec

2013 Jan

Remarks

Submission of Aerodrome Data

4.
5.

Evaluation & Publication


Wind Speed & Direction Sensor 5a. 5b. Delivery Installation

CAAP-ATS
CAAP

Until 09 January

5c. Testing

6. Wind Cone 7. Delivery of Fire Truck 8. Delivery of Runway Sweeper 9. Delivery of Furniture

CAAP LADP LADP LADP

ACTIVITIES
11. System Testing of Airport Equipment 12. Identification & Designation of Counters & Offices (Airlines)

Office-InCharge
LADP Contractor, Consultant & PMO CAAP

2012 Sept Oct Nov Dec

2013 Jan

Remarks

13.Training of CAAP Personnel


14.Transportation System 15.Stakeholders Coordination Meeting 16. Probing Flight/Dry Run 17. Inauguration

LADP Contractor, Consultant & PMO


LTFRB & CAAP