Beruflich Dokumente
Kultur Dokumente
Purpose To determine that the installation is in a satisfactory condition for continued service i.e. it meets the general objective of the LAW, this is verified by assuring the requirements of BS7671 are complied with. Legislation requires that certain installations are maintained in a safe condition and therefore must be periodically inspected and tested
Insurance companies
Mortgagors
Additionally
Periodic Inspection and Testing should be considered:Changes of ownership or tenancy
After alterations or additions
731-01-03
All heavy current equipment e.g. bus-bars, main switches etc should be tested.
Section B. A small office block in Stourbridge 1)a) What types of inspection and tests need to be carried out Initial Verification for the new work and Periodic Inspection and test for the existing installation b) State the documentation that should be completed and why An Electrical Installation Certificate for the new work (additional circuits have been installed) and a Periodic Inspection Report for the existing installation Both of these documents must be accompanied with a schedule of inspection and a schedule of test results
c) State the Statutory Regulations that need to be adhered to The Health and Safety at Work Act and the Electricity at Work Regulations d) List the test equipment required for this installation i) Low reading ohm meter (continuity tester) ii) Insulation resistance meter iii) Earth loop impedance tester iv) Prospective fault current tester
2)a) List five areas of inspection to be considered on the existing installation. Give one reason for each i) Wear and Tear, the installation is 20yrs old, the accessories,switches etc may show signs of deterioration ii) Excessive loading e.g. connection of conductors (effects of heat etc over 20 years)
iii) Damage, the installation equipment may be damaged to the extent it has become dangerous e.g. exposure of live parts
iv) Corrosion, the conduit is being used as a c.p.c, if this is corroded the shock protection may be affected v) Compliance with BS7671, there have been considerable changes in the standard over the installation life
b) Before commencing testing on the existing installation, what should be agreed with the client The extent and limitations that are to be imposed by the client c) List the correct sequence of tests required for the existing installation i) Continuity of protective conductors (including bonds) ii) Polarity iii) Earth fault loop impedance iv) Insulation resistance v) Operation of devices for isolation and switching If there are ring final circuits in the existing installation these should also be tested (as item (ii) )
Note:- There is no indication that the installation contains RCDs or Circuit Breakers, these tests therefore would not be required. Also alternative methods may be used provided the results are no less effective. d) List five of the inspection check list items for the new work i) Connection of conductors ii) Identification of conductors iii) Conductor current carrying capacity iv) Correct connection of accessories v) Erection methods
e) List the correct sequence of tests required for the new installation i) Continuity of protective conductors including bonds ii) Continuity of ring final circuits iii) Insulation resistance iv) Polarity v) Earth loop impedance vi) Prospective fault current
vii)Functional testing
3) Describe how to carry out the ring final circuit continuity test on the new installation
Test sequence Test open ends of the ring, phase to phase, neutral to neutral, cpc to cpc RECORD results
4) Describe how to carry out the insulation resistance test on the existing installation
Test preparation:- All current using equipment should be disconnected or turned off, the supply to the main distribution board should be isolated, all protective devices should be in position or on, all local switches on, any equipment which may be damaged by the test should be disconnected or by-passed. The test is then conducted between:i) All live conductors and
ii) All live conductors to Earth
5) Draw a fully labelled diagram of the complete earth fault path of the new lighting circuit.
b c
a) Supply phase, b) supply phase conductor, c) circuit phase conductor, d) exposed-conductive-part of the light, e) c.p.c of the lighting circuit, f) return path (PEN i.e the earthed neutral) of the supply cable
6) Because the existing wiring system does not contain separate c.p.cs describe the three stages of verification that need to be confirmed. i) Visual inspection along the length of all conduits to check their condition regarding corrosion etc ii) If the conduit appears in good condition measure its resistance with a low reading ohm meter
iii) If there is any doubt as to its suitability e.g. where its physical condition cannot be checked, a high current injection test is required (not exceeding 25A)
7)a) If the ring final circuit R1 + R2 is 0.72, calculate the approximate reading of Zs Zs = Ze + (R1 + R2) = 0.2 + 0.72 = 0.92 b) If the maximum tabulated Zs for this circuit is 1.2, calculate if the reading in (a) is acceptable There are no correction factors stated, use the rule of thumb 1.2 x 0.75 = 0.9 < 0.92 measured (circuit fails)
c) State what factors need to be considered before measured earth loop impedance values are compared against maximum tabulated Zs values i) Ambient temperature factors (when not measured at 200C) ii) Cable temperature factors (not at its operating temperature)