Policy Thrusts
PEP 2012-2030
Future
Climate Proof the Energy Sector
Sector
Geothermal
Hydropower
Biomass Biofuels
341.3
276.7
DC on E10 in 2011 Mandatory E10 to all Gasoline by 2012 PNS for B5 by 2014 DC on B5 by 2015 Mandatory B5 to all Diesel by 2015
3,161.0
1,891.8
5,394.1
276.7
PNS for B20 and E85 by 2020 DC on B10 and E20 by 2020
Fossil Fuel Oil (MMB) Gas (BCF) Condensate (MMB) Coal (MMMT*)
*@10,000 BTU/lb
A. Increase installed capacity B. Upgrade and expand transmission and distribution network C. Interconnect the island grids D. Expand energy market from Luzon-Visayas to Mindanao and include RE.
23 4 27
5 16 21
54 82 136
Achieve 90% Household Electrification by 2017 Achieve 100% Sitio Electrification by 2015
Area / Regional Depots Service / Refilling Stations LPG Refilling Stations Distribution Pipelines
The Bright Now! Campaign aims to educate and empower Filipinos to be smart energy users Expand coverage of energy labeling program and move towards standardization Government to lead 10.0 percent savings on fuel and electricity Consistent with the ASEAN and APEC Targets
Energy Standards and Labeling Program will be expanded to cover: Television sets Washing machines Refrigerators (up to 12 cubic feet) New models of passenger cars and light duty vehicles
2030
Number of Vehicles 61 19,052 630 10% 2% 1,000 20,200 50,170 10% 5% 5,000 100 20,500 80,730 10% 5% 6,900 1,000 21,700 106,000 20% 10% 9,200 6,000 23,200 150,000 20% 20% 15,000 16,000 23,000 230,000 20% 20%
Year
2011
2015
7,645
9,056 10,348 11,428
6,477
7,672 8,768 9,683
5%
10% 20% 20%
382
906 2,070 2,286
324
767 1,754 1,937
2020
2025 2030
Note:
30% of Public Utility Vehicles on Alternative Fuels by 2030 (Bioethanol) Gasoline Demand Year (In Million Liters) 4,181 5,350 7,955 10,322 12,589 (In KTOE) 3,274 4,189 6,229 8,083 9,858
Supply Requirement/Fuel Displacement (In Million Liters) 418 535 1,591 2,064 2,518 (In KTOE) 327 419 1,246 1,617 1,972
Target Year
2014-2016
Pipeline Projects
27.4 k.m. Pipeline System for Cagayan de Oro and PHIVIDEC Area 2x2 k.m. Distribution Pipeline in Iligan City
Target Year
2014-2016 2014-2016
Storage Facility
Satellite Supply Terminal (2 Storage Tanks each with 120 cu.m.) in South Iligan Satellite Supply Terminal (1 Storage Tanks with 120 cu.m.) in North Iligan
Target Year
2014-2016 2014-2016
Refilling Station
Liquefied Compressed Natural Gas (LCNG) Refueling Stations in Iligan City, CDO and PHIVIDEC Areas
Note: Said Targets are still subject for review based on current socio-economic conditions.
Target Year
2016-2017
19
Target Year
TBD
Pipeline Projects
53 k.m. Pipeline in General Santos
Target Year
2016-2018
Refilling Stations
Liquefied Compressed Natural Gas (LCNG) Refueling Stations in General Santos and Davao
Note: Said Targets are still subject for review based on current socio-economic conditions.
Target Year
2016-2018
20
Implement the National Climate Change Action Plan (NCCAP) in the energy sector
Mitigation action mainly through energy efficiency, renewable energy and alternative fuels and technology programs Conduct vulnerability assessment of the energy sector
Critical Periods
2014 initial relief period due to committed and indicative capacities 2018 next critical period with committed capacity only 2020 - if with committed and indicative capacities
Additional capacity requirement will be more than calculated due to presence of suppressed demand
2000
1500 1000
2017
2019
2021
2012
2013
2014
2015
2016
2018
2020
2022
2023
2024
2025
2026
2027
2028
2029
Notes a. Demand curve represents total of peak demand and required Regulating Reserve (RM) i.e. 4% regulating reserve and contingency and dispatchable reserve requirement (RM). b. 4.76% peak demand growth rate resulted from aggregated demand as submitted by the utilities to DOE. c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for electric power with national economic growth applied to 6.6 percent GDP growth rate (GR) for 2012. 23 d. Power demand in the island remains restrained. Grew by 1.84 % in 2012.
2030
Participants
Generators (Grid, Embedded, Firm, Non-Firm) Customers With Self Gen Capability (DUs) Demand-Side (VLC)
Pricing
Bid-based with Bid Cap
Scheduling
Day-Ahead Nomination Real-time imbalance correction
Financial Settlement
Uniform Pricing (Market Clearing Price)
Establishment Timeline
Consultation Market Rules Promulgation
Regulatory Approvals
Rates Cost Recovery
IMEM
- Price Determination Methodology and Cost Recovery Filing
6 Months
5 Months
Market Development
Training and System Trial Infra & System Development
Stakeholder Engagement
J F M A M J J A S O N D J F M A
2013
2014
15 months starting from the Issuance of DC *As presented during the public consultations
DEPARTMENT OF ENERGY