Beruflich Dokumente
Kultur Dokumente
Group-7 Atul Sharma Arnab Guha Mallik Rudra Radhakrishnan Ankur Dey Tarafder PGP/15/075 PGP/15/074 PGP/15/173 PGP/15/204
Project is a unique interrelated set of tasks with a beginning, an end and a well defined outcome
Assumption: everyone can identify the tasks and provide alternatives and maintain the same overall project vision throughout
A more comprehensive and better approach towards project management is uncertainty based management
Types of Uncertainty:
1. 2. 3. 4. Variation Foreseen Uncertainty Unforeseen Uncertainty Chaos
Types Of Uncertainty
Variation in activity durations, costs and exact performance level of the resources Foreseen risks refers to a distinct, understood and identifiable influences Require risk assessment with alternate plans Ex. results of field test in drug development
A developer can anticipate possible side effects The side effect is the foreseen uncertainty. The contingency plan may never be used, but it is there if the side effect occurs
Unforeseen uncertainty cant be identified during planning The team either is unaware of the events possibility or considers it unlikely Occurs in any project that pushes a technology envelope or enters a new market E.g.: Pfizers blockbuster drug Viagra
Projects subject to chaos do not start with stable assumptions/goals Basic structure of the plan is uncertain e.g. when technology is in upheaval or when research is the main goal. The project ends up with results that are completely different from the projects original intent. e.g. Ex. Sun s development of Java
A shifting schedule causes the critical path to move, forcing managers to monitor variations , not just critical activities
Ex. variation during a construction project in delivery dates
Planning
Execution
Planning
Execution
No uncertainty
(only task and relational complexity)
critical path
Activity network analysis (CPM, PERT, etc. )
Gantt Chart
The greater the uncertainty more the team may have to redefine the tasks or structure of the project plan in midcourse.
The mechanism that ensures agreement is the uncertainty profile. For example, although the dominant uncertainty an Internet start-up faces may be chaos, it also may face other types of uncertainty
To help identify the dominant uncertainty types, teams may use hunches or more formal approaches, such as statistical analyses, technology and market forecasts, or creativity management techniques Once a profile is created, it can be used to build a project infrastructure to execute a plan (in the case of variation or foreseeable uncertainty) or to learn from events and adjust (unforeseeable uncertainty or chaos)
The project managers role and the planning and monitoring activities change as the uncertainty profile evolves.
Flexibility and the ability to communicate changes is key.
Managing Relationships
Planning Execution
Variation
Build in slack/buff er at strategic locations in critical path and determine control limits for corrective action. Simulation of different scenarios.
Monitor performance against performance criteria. Maintain some flexibility with key stakeholders .
Critical Chain:
buffer management
The Mobile Systems Unit (MSU) of Acer learned the importance of that principle in its development and manufacture of PC notebooks They missed the market introduction window by only one month on a given model and it virtually eliminated the units profit potential for that model Significant schedule variations with multiple causes.
1. Vendors did not deliver sufficient volumes of a promised new component on time 2. Major customers such as IBM would change their requirements 3. Design problems with the motherboard would cause additional design loop 4. Negotiations among multiple parties might change internal specifications
This lead to shortcuts in testing, causing major rework at a more costly stage Acer attacked the multiple causes on multiple fronts.
1. They created buffers in the form of slack capacity by killing two delayed projects 2. It then concentrated on improving the way it documented operating procedures so that it could increase testing coverage and facilitate training of young engineers
Those steps reduced the number of correction loops during product development Improved the quality of the companys manufacturing ramp-up Over the next two years, MSU more than doubled its sales and gained significant market share.
Managing Relationships
Planning Execution
Foreseen risk
Decision tree
X1 X2 X3 X4
Chance node
Anticipate and trigger alternative paths to project goal through decision tree techniques
Contingency planning, decision analysis.
Continuousl y inform and motivate internal and external partners in order to cope with major switches in project execution
go 1 -p stop
Type of uncertainty
PM Style
Managing Tasks
Planning Execution
Managing Relationships
Planning Execution
Unforeseen risk
X1 X2 X3 X4
Build in the ability to add a set of new tasks to the decision tree
Continuou s-ly question the existing project model and scan the horizon for early signs of nonanticipated influences.
Build in ability to mobilise new partners in the network who can help solve new challenges
0
X5
Type of uncertainty
PM Style
Managing Tasks
Planning Execution
Managing Relationships
Planning Execution
Chaos
Consider parallel solutions with iteration and gradual selection of final approach.
Repeated verification of hypotheses on which project is built; detail plan only to next verification
Close linking with users and leaders in the field. Direct and constant feedback from markets and technology providers.
THANK YOU