Beruflich Dokumente
Kultur Dokumente
POWER IS PLEASURE---ASK THOSE WHO ARE SEEKING IT POWER IS PAIN ---ASK THOSE WHO HAVE IT REAL POWER IS PAIN IMAGINARY POWER PLEASURE
SRLDC, BANGALORE
SRLDC, BANGALORE
ANOTHER ANALOGY
MVAR
MVA MW
SRLDC, BANGALORE
LINKS
SOURCES CAP CURVE INTRO ACTUAL LIMITS AVR SINKS SYNCHRONOUS MACHINES THEORETICAL LIMITS 3D CAP CURVE S.I.L MODES OF OPERATION CAP CURVE STABILTY LIMITS LAG LOAD SLD TL OV PROBLEM VOLTAGE LIMITS TAP CHANGING EXAMPLES ICT VA METERING VECTOR DIAGRAM HYDROGEN PRESSURE LEAD LOAD SLD TL UV PROBLEM REQUIREMENTS METHODS MILLER TAP CHANGING EXAMPLE GT SCROLL GRAPH VOLT JUN03
KDAMPARAI
HV CORRECTN
T.L.FACTS
LOAD ANGLE
MORE LINKS
SYNCHRONOUS GENERATORS AND CAPABILITY CURVES TRANSMISSION LINES
LOAD ANGLE
IEGC
SRLDC, BANGALORE
SYNCHRONOUS GENERATORS SYNCHRONOUS CONDENSORS SHUNT CAPACITORS STATIC THYRISTOR BASED DEVICES TRANSMISSION LINES
SRLDC, BANGALORE
LOADS
INDUCTION MOTORS(PUMPS,FANS ETC) INDUCTIVE LOADS (CHOKES ETC)
TRANSFORMERS TRANSMISSION LINES REACTORS STATIC THYRISTOR BASED DEVICES SHYNCHRONOUS MACHINES
SRLDC, BANGALORE
SYNCHRONOUS MACHINES
SRLDC, BANGALORE
UNDER-EXCITED OR LEADING PF
OVER-EXCITED OR LAGGING PF
SRLDC, BANGALORE
jIXd
I
V
jIXd
SRLDC, BANGALORE
CAPABILITY CURVE
Q=MVAR, REACTIVE POWER U2=P2+Q2 LEAD
MOTORING
GENERATING
P=MW, ACTIVE POWER
LAG
SRLDC, BANGALORE
SRLDC, BANGALORE
CAPABILITY CURVE:LIMITS
SRLDC, BANGALORE
SRLDC, BANGALORE
SRLDC, BANGALORE
LIMITATIONS
SRLDC, BANGALORE
CAPABILITY POLYHYDRON
SRLDC, BANGALORE
LAGGING LOAD
SRLDC, BANGALORE
CAPACITIVE LOAD
SRLDC, BANGALORE
AVR
SRLDC, BANGALORE
V-CURVES
SRLDC, BANGALORE
MOTORING
KADAMPARAI- ON 18/02/2003
500
400
51
300
50.5
200
100
50
49.5
-100
49
-200
PUMP MODE
-300
FREQUENCY(HZ)
MW
3 QUADRANT OPERATION
IDUKKI UNIT 1 RUNNING IN CONDENSER MODE ON 27-MAR-03
140 120 100
MW
80
MW/MVAR ->
MVAR
TIME IN HR ---->
SRLDC, BANGALORE
TRANSMISSION LINES
SRLDC, BANGALORE
SURGE IMPEDANCE LOADING:-The SIL is the loading level where the reactive VARs generated by the line capacitance equal the VARs required by the line inductance. QUICK FACT:
SRLDC, BANGALORE
OVERVOLTAGE PROBLEMS
Generator self-excitation Insulation breakdown Flashover Customer equipment damage Excessive heating of overexcited transformers
SRLDC, BANGALORE
UNDERVOLTAGE CAUSES
Heavy line loading Disturbances High customer demand Induction motor heating Dim lights - more lights Less heat - more heaters Voltage collapse
SRLDC, BANGALORE
SOME FACTS
A 10 percent voltage drop cuts light output by 30 percent. A 10 percent voltage drop cuts heat output by 20 percent. The user response, in many such cases, is to turn on more lights
SRLDC, BANGALORE
Remove shunt Reactors Insert shunt capacitors Energize open lines Raise LTC set points Raise voltage regulator set points Use generator reactive overload capability Curtail interruptible loads Shed firm load
SRLDC, BANGALORE
Remove shunt capacitors Insert shunt reactors Lower voltage set points Close open-ended lines or remove from service altogether Buck with generators Remove transmission lines from service
SRLDC, BANGALORE
POINTS TO REMEMBER
VAR control is the key to voltage control Use voltage control equipment early Avoid voltage collapse/High Voltage by smart operating
SRLDC, BANGALORE
kV
148 245
400
735/765
420
800
SRLDC, BANGALORE
LOAD ANGLE
ITS IMPLICATION IN POWER SYSTEM OPERATION
SRLDC, BANGALORE
LOAD ANGLE
SRLDC, BANGALORE
SRLDC, BANGALORE
VOLTAGE vs FREQUENCY
SRLDC, BANGALORE
The general synchronous machine equations show that voltage levels are directly proportional to the frequency and for godd voltage control extremes of system frequency are to be avoided
Excerpts from Chapter on Reactive Power and Voltage control. System operators Manual L
SRLDC, BANGALORE
E=4.44fN
Where E is the EMF Generated,f is the Frequency, the flux
SRLDC, BANGALORE
1. P=P0(F/F0) 2 2. Q=Q0(V/V0)
SRLDC, BANGALORE
SRLDC, BANGALORE
LOAD REPRESENTATION
TYPE OF LOAD PF
INCANDESENT LAMP
FLOURESCENT LAMP AIR CONDITIONER WINDOW TYPE
P/V (%)
P/F (%)
Q/V (%)
Q/F (%)
REFRIGERATOR
HOME APPLIANCE WITH MOTOR 150 HP INDUCTION MOTOR LARGE US TOWN ALUMINIUM PLANT AGRICULTURAL IN WINTER(US)
1.6 0 1 1 0.5 0.6 0.8 0.5 0.3 0.1 0.88 -0.1 0.89 1.7 1.9 0.91 2.4 0.4 SRLDC, BANGALORE 0.8
0.7
415
50.00
SRLDC, BANGALORE
415
50.00
413 49.50
411
FREQUENCY
48.50
SRLDC, BANGALORE
-150.00 51.00
-200.00 50.50
VOLT (KV)
50.00 -300.00
FREQUENCY -350.00
49.50
49.00 -400.00
SRLDC, BANGALORE
FREQ (HZ)
-250.00
51.00
-50 FREQUENCY
50.50
VOLT (KV)
-100
50.00
-150
49.50
-200 MVAR
49.00
48.50
SRLDC, BANGALORE
FREQ (HZ)
SRLDC, BANGALORE
ICT TAPS
ON LOAD TAP CHANGER 1.25% OR 5 KV PER TAP10% RANGE
NOMINAL TAP AT 9
TAP NO 1=440/220 400 KV SIDE 220 KV SIDE V TAP NO 17=360/220 V
SRLDC, BANGALORE
BASE CONDITION
SRLDC, BANGALORE
TAP IS MOVED FROM 9 TO 3 SAY MVAR FLOW AND RESULTANT VOLTAGES ARE DEPENDANT ON GRID AND STRENGTH OF BUS
SRLDC, BANGALORE
TAP CHANGING
REARRANGES MVAR FLOW TO BE DONE CONSIDERING VOLTAGES ON BOTH SIDES CO-ORDINATED ACROSS THE SYSTEM TAP CHANGING SCHEDULES
SRLDC, BANGALORE
GT TAP CHANGING
400 KV BASE CASE 21 KV
TAP 9
~
500 MW 30 MVAR
INFINITE BUS
~
500 MW
INFINITE BUS
5 MVAR
SRLDC, BANGALORE
SRLDC, BANGALORE
SWITCH ARRANGEMENT
SRLDC, BANGALORE
TAP STAGGER
SRLDC, BANGALORE
LOAD
LAGGING LEADING 1.SWITCH OFF CAPACITORS 2.GENERATORS ABSORBING VARS 3.SWITCH OFF LIGHTLY LOADED LINES 4.TAP STAGGERING
DURATION
SRLDC, BANGALORE
VOLTAGE CONTROL
WHAT THE IEGC SAYS..
SRLDC, BANGALORE
4.9 Reactive Power Compensation (a) Reactive Power compensation and/or other facilities, should be provided by SEBs/STUs or distributing agencies as far as possible in the low voltage systems close to the load points thereby avoiding the need for exchange of Reactive Power to/from ISTS and to maintain ISTS voltage within the specified range.
SRLDC, BANGALORE
6.9 (J)All generating units shall normally have their automatic voltage regulators (AVRs) in operation, with appropriate settings. In particular, if a generating unit of over fifty (50) MW (10 MW in case of North-Eastern region) size is required to be operated without its AVR in service, the RLDC shall be immediately intimated about the reason and duration, and its permission obtained. Power System Stabilisers (PSS) in AVRs of generating units (wherever provided), shall be properly tuned as per a plan prepared for the purpose by the CTU from time to time. CTU will be allowed to carry out tuning/checking of PSS wherever considered necessary. SRLDC, BANGALORE
(q) All regional constituents shall make all possible efforts to ensure that the grid voltage always remains within the following operating range. NOMINAL MAXIMUM MINIMUM
400 220 132 420 245 145 360 200 120
SRLDC, BANGALORE
6.4 Demand Control 6.4.1 Introduction: This section is concerned with the provisions to be made by SLDC's to permit the reduction of demand in the event of insufficient generating capacity, and transfers from external interconnections being not available to meet demand, or in the event of breakdown or operating problems (such as frequency, voltage levels or thermal overloads) on any part of the grid.
SRLDC, BANGALORE
d)The RLDC is authorised during the restoration process following a black out, to operate with reduced security standards for voltage and frequency as necessary in order to achieve the fastest possible recovery of the grid.
SRLDC, BANGALORE
1.
2.
3.
7.6 Reactive Power and Voltage Control: The Beneficiaries are expected to provide local VAR compensation/generation such that they do not draw VARs from the EHV grid. However, considering the present limitations, this is not being insisted upon. Instead, VAR drawals by Beneficiaries (except on their lines emanating from ISGS) are to be priced as follows:The Beneficiary pays for VAR drawal when voltage at the metering point is below 97%. The Beneficiary gets paid for VAR return when voltage is below 97%. The Beneficiary gets paid for VAR drawal when voltage is above 103%. The Beneficiary pays for VAR return when voltage is above 103%. The charge/payment for VARs, shall be at a nominal paise/kVARh rate as may be approved by CERC from time to time, and will be between the beneficiary and the Pool Account (for VAR interchanges with ISTS), and between two beneficiaries (for VAR interchanges on ties between their systems). Notwithstanding the above, RLDC may direct a beneficiary to curtail its VAR drawal/injection in case the security of grid or safety of any SRLDC, BANGALORE equipment is endangered.
7.6.4In general, the Beneficiaries shall endeavour to minimise the VAR drawal at an interchange point when the voltage at that point is below 95% of rated, and shall not return VARs when the voltage is above 105%. ICT taps at the respective drawals points may be changed to control the VAR interchange as per a beneficiary's request to the RLDC, but only at reasonable intervals. 5. Switching in/out of all 400 KV bus and line Reactors throughout the grid shall be carried out as per instructions of RLDC. Tap changing on all 400/220 KV ICTs shall also be done as per RLDC's instructions only. 6. The ISGS shall generate/absorb reactive power as per instructions of RLDC, within capability limits of the respective generating units, that is without sacrificing on the active generation required at that time. No payments shall be made to the generating companies for such VAR generation/absorption.
SRLDC, BANGALORE
VA Metering
VA METERING
ACCURACY CLASS DIFFICULTY IN CALIBRATION AND CHECKING DIFFICULTY IN MEASURING BAD POWER FACTOR
SRLDC, BANGALORE