Beruflich Dokumente
Kultur Dokumente
Capacity Planning
1
Capacity Planning
Capacity is the upper limit or ceiling on the load that an operating unit can handle. Capacity is the amount of work that can be done in a period of time It is usually stated in standard hours of work It must be determined at plant, department, and work center levels.
Various Capacities
Design capacity
Maximum obtainable output
Efficiency =
Effective capacity
Actual output
Utilization = Design capacity
This definition of efficiency is not used very much. Utilization is more important. 5
Actual Output 36 units / day Efficiency 90% EffectiveCapacity 40 units / day Actual Output 36 units / day Utilization 72% Design Capacity 50 units / day
6
Capacity planning
Definitions : Capacity planning is the process of determining the production capacity needed by an organization to meet changing demands for its products. In the context of capacity planning, "capacity" is the maximum amount of work that an organization is capable of completing in a given period of time
Capacity planning
In information technology, capacity planning is the science and art of estimating the space, computer hardware, software and connection infrastructure resources that will be needed over some future period of time. A typical capacity concern of many enterprises is whether resources will be in place to handle an increasing number of requests as the number of users or interactions increase. The aim of the capacity planner is to plan so well that new capacity is added just in time to meet the anticipated need but not so early that resources go unused for a long period. The successful capacity planner is one that makes the trade-offs between the present and the future that overall prove to be the most cost-efficient.
Capacity planning
Capacity planning has seen an increased emphasis due to the financial benefits of the efficient use of capacity plans within material requirements planning systems and other information systems. Insufficient capacity can quickly lead to deteriorating delivery performance, unnecessarily increase work-in-process, and frustrate sales personnel and those in manufacturing. However, excess capacity can be costly and unnecessary. The inability to properly manage capacity can be a barrier to the achievement of maximum firm performance. In addition, capacity is an important factor in the organization's choice of technology.
Capacity calculation
Capacity = (number of machines or workers) (number of shifts) (utilization) (efficiency).
Various Strategies
Lead strategy is adding capacity in anticipation of an increase in demand. Lead strategy is an aggressive strategy with the goal of luring customers away from the company's competitors. The possible disadvantage to this strategy is that it often results in excess inventory, which is costly and often wasteful. Lag strategy refers to adding capacity only after the organization is running at full capacity or beyond due to increase in demand . This is a more conservative strategy. It decreases the risk of waste, but it may result in the loss of possible customers. Match strategy is adding capacity in small amounts in response to changing demand in the market. This is a more moderate strategy.
Capacity Planning
1. Determine Service Level Requirements
The first step in the capacity planning process is to categorize the work done by systems and to quantify users expectations for how that work gets done.
**Workloads Explained**
From a capacity planning perspective, a computer system processes workloads (which supply the demand) and delivers service to users. A workload is a logical classification of work performed on a computer system. If you consider all the work performed on your systems as pie, a workload can be thought of as some piece of that pie. If you analyze performance based on workloads corresponding to business departments, then you can establish service level requirements for each of those departments.
Demand management
Price variation Marketing effort variation Incentive and discounts Buffer stock creation Lead time variation Rationing- reservation and appointment system
Capacity management
Working hours and shift management Scheduling work patterns Part time staff Outsourcing Process adjustment Adjusting equipment and processes Rescheduling maintenance Self service Franchising Subcontracting
Capacity cushion
Attempt to prevent a run out positive cushion - Additional capacity than the forecast demand Meet the average forecast Maximise utilisation - Negative cushion capacity build up cost is very high eg. Oil refineries, paper mills. It can harm long term market share.
5 35 16
6 32 15
Direct labor per unit ( in standard hours) A 0.95 hours B 1.5 hours
33 * 0.95 + 17* 1.5 = 56.85 60% of 56.85 = 34.11 30% of 56.85 = 17.06 10% of 56.85 = 5.67
Capacity bills
Takes into account any shifts in product mix Required data: Bill of material Routing data Direct labor-hour or machine-hour data for each operation
Capacity bills
Part requirement
A B
D C D
E- 2 F F- 2
Capacity bills
End produ cts A B
Compo nents
Lot Sizes
Std. run Total time hrs. hrs. per Per unit unit 0.025 1.25 0.05 1.30
40 20
1 of 1 1 of 1
100 100
1.0 1.0
C D E F
40 60 100 100
1 of 2 2 of 2 1 of 1 1 of 1 1 of 1
Bill of Capacity
Capacity bills
A Work centre 100 Total time/unit 0.05 B Total time/unit 1.30
200
300 Total time/unit
0.70
0.20 0.95
0.55
0.0 1.85
Calculation Example: Set time/ Lot size = 1/40 = 0.025 Std. set up hrs. per unit = 0.025 + 0.025 = 0.50 For 1 C and 1 D = 0.60 + 0.1 = 0.70 For one D, two Es and four Fs = 0.1 + 2*0.1 +4 * 0.0625 =0.55
Capacity bills
------------------------PERIOD ---------------- Total Hours Work center %
6 36.95 40.75 7.40 85.10 172.74 215.93 43.19 431.85 40% 50% 10% 100%
Calculation Example: For Work Center- 100 : 33*0.05 + 17 *1.3 = 23.75 For Work Center- 200 : 33*0.7 + 17*0.55 = 32.45
Resource profiles
Takes into account the specific timing of the projected workloads at individual work centers Production set up and lead time data are taken into account MPS is useful.
Resource profiles
Time required during preceding periods for one end product assembled in period 5: .Time period .... 3 4 5 End product A Work center 100 0 0 0.05 Work center 200 0.6 0.1 0 Work center 300 0 0.2 0 End product B Work center 100 Work center 200
0 0.25
0 0.3
1.3 0
Resource profiles
Time phased capacity requirements generated from MPS for 40 As and 13 Bs in time period 5: .Time period .... 3 4 5 40 As Work center 100 0 0 2 Work center 200 24 4 0 Work center 300 0 8 0
13 Bs Work center 100 Work center 200 Work center 300 Total from period 5 MPS Work center 100 Work center 200 Work center 300
0 3.25 0
0 3.9 0
16.9 0 0
0 27.5 0
0 7.9 8
18.9 0 0
10
25
1 30 50 45 0
2 40 5 50
Period 3 4 40 40 15 50 25 50
5 40 35 0
6 0 35 0
1 20 25 5 15
2 20 0 20
Period 3 4 20 20 0 20 0 20
5 20 0 20
6 20 0
43
Input/Output control
Planned work input and planned output at a work center will be compared to the actual work input and output Deviations are caused by: Lower-than-expected productivity Breakdowns Absences Random variations Poor product quality Insufficient output from a preceding work center Improper releasing of planned orders Monitors backlogs as the cushion between input and output
Capacity Bills Cons Doesnt consider lead times, inventory information, or gross-to-netting
Less accurate Resource Profiles Doesnt consider inventory information or gross-to- netting
Easy to use Minimal computational requirements Considers lead times Less accurate Consider product mix Capacity Requirements Planning Considers: gross-to-netting, Requires MRP system, Time-phased Inventory information, records, Extensive computational lead times requirements More accurate Considers product mix
45
Question Bowl
The objective of Strategic Capacity Planning is to provide an approach for determining the overall capacity level of which of the following?
a. b. c. d. e.
Facilities Equipment Labor force size All of the above None of the above
Answer: (d )
Question Bowl
To improve the Capacity Utilization Rate we can do which of the following?
a. b. c. d. e.
Reduce capacity used Increase capacity used Increase best operating level All of the above None of the above
Answer: ( b )
Question Bowl When we talk about Capacity Flexibility which of the following types of flexibility are included? a. b. c. d. e. Plants Processes Workers All of the above None of the above Answer: (d )
Question Bowl When adding capacity to existing operations which of the following are considerations that should be included in the planning effort? a. b. c. d. e. Maintaining system balance Frequency of additions External sources All of the above None of the above
Answer: (d )
Question Bowl
Which of the following is a term used to describe the difference between projected capacity requirements and the actual capacity requirements? a. b. c. d. e. Capacity cushion Capacity utilization Capacity utilization rate All of the above None of the above
Answer: (a)
Question Bowl
In determining capacity requirements we must do which of the following? a. Address the demands for individual product lines b. Address the demands for individual plants c. Allocate production throughout the plant network d. All of the above e. None of the above
Answer: (d)
Question Bowl In a Decision Tree problem used to evaluate capacity alternatives we need which of the following as prerequisite information?
a. b. c. d. e.
Expect values of payoffs Payoff values A tree All of the above None of the above
Answer: (b)
.
END OF CHAPTER 6