Beruflich Dokumente
Kultur Dokumente
4/15/2013
4/15/2013
ELECTRICITY NATIONALIZED
PostIndependence, Electricity( Supply) Act, 1948, aimed to increase access to electricity.
DOWNWARD SLIDE
Large demand-supply gap (2009-10) Energy shortage:10% Peak shortage:12.7% Low per capita consumption: 672 kwh per annum By early 90s, State Electricity Boards were bankrupt. Accumulated losses of the SEBs exceeded Rs.26,000 crores in 2000-01. Unpaid dues to central power generating companies alone exceeded Rs. 40,000 crores. Total return of SEBs in 2005-06 was (-) 26%. Financial collapse leading to operational collapse
4/15/2013
2007
(in Twh)
%age of total
GENERATION
2009
(in Twh)
%age of total
Germany 4/15/2013
636.5
3.2
596.8
3.0 8
4/15/2013
10
4/15/2013
11
4/15/2013
13
CHALLENGE OF CAPACITY ADDITION Plan Period Addition (in MW) 16,422 19,015 Percentage of Plan target 53.8 < 50
Tenth Plan
Eleventh Plan (target)
23,250
78,530 Thermal 58,597 Hydro 16,553 Nuclear 3,380
56.6
4/15/2013
14
If all inferred reserves materialize, coal & lignite can last for more than 140 years.
If domestic coal production continues to grow at 5 percent per year, total extractable reserves would run out in about 40 years. In-situ coal gasification can increase energy from domestic resources significantly.
4/15/2013
15
Proved gas and CBM together can last for some 50 years.
4/15/2013 16
4/15/2013
18
469
357 365 349
Other cost
Delhi
77
Gujarat
73
All India
66
19
62
COST-PLUS FALL-OUT
While differences in power cost of generating
stations can be due to differences in fuel type,
operational efficiencies
4/15/2013 20
Salal
Baira Siul Tanakpur Singrauli Chamera Rihand Anta Auraiya Unchahar-I Dadri 4/15/2013 Badarpur
BTPS
Hydro Hydro Hydro Thermal Hydro Hydro Thermal Thermal Thermal Thermal Thermal
358
0.59
0.63 1.04 1.09 1.32 1.47 1.61 1.62 1.88 2.27 2.37
21
Self generation Allocation from Independent power central generating producers; Bid/MOU (SEB owned stations ; CERC generators); route for projects; capacity cleared determines tariffs CERC/SERC vets the tariff by SERC
Medium term
Short term
COMPETITION IN GENERATION
The Central Government guidelines issued for tariff-based bidding process for procurement of electricity by DISCOMS for medium term (one to seven years) and for long-term (for more than seven years). Section 66 of the Act provides for development of electricity market for price determination/price discovery. A well functioning power market leading to free competition provides national-level access to all buyers and sellers for transparent price discovery, rewards more efficient generators and reduces power procurement cost.
4/15/2013 25
A NEW STRUCTURE
Wholesale power purchase model Reformed structure for power purchase
Single buyer model SEB/TRANSCO pools distribution utility requirements to procure power Primarily long duration contracts 15 -25 years or more Limited incentives to improve efficiency 4/15/2013 27
COMPETITIVE BIDDING
4/15/2013
28
COMPETITIVE BIDDING
4/15/2013
29
4/15/2013
30
SEB MODEL
4/15/2013
31
4/15/2013
32
4/15/2013
33
4/15/2013
34
4/15/2013
35
4/15/2013
36
4/15/2013
37
4/15/2013
38
4/15/2013
NORTHERN REGION
Largest in geographical area amongst the five regions covering 30.7% of the area and 28% of the countrys population. Largest number of constituents (9 states/UTs, 3 Central Generating Companies, one Central Transmission Utility and Bhakra Beas Management Board). Largest sized hydro unit (250 MW at Nathpa Jhakri) in the country. Establishment of the first super thermal power station (Singrauli STPS) and 400 kV transmission system in the country.
4/15/2013
40
NORTHERN REGION
Establishment of the first High Voltage Direct Current (HVDC) long distance transmission system in the country (2x750 MW, + 500 kV Rihand-Dadri HVDC bipole). First HVDC back-to-back interconnection with Western Region (2x250 MW back-to-back HVDC station at Vindhyachal). First 400 kV Static Var Compensators (SVCs) in the country (2x + 140 MVAR SVC at Kanpur). Largest capacity of combined cycle gas power stations amongst the five regions (2939.50 MW) located along the 700 Kms. long Hazira-Bijaipur-Jagdishpur (HBJ) natural gas pipeline of GAIL.
4/15/2013
41
NRLDC
NRLDC is the apex body to ensure integrated operation of the power system in the Northern Region. The main responsibilities of NRLDC are: Monitoring of system parameters and security. To ensure the integrated operation of the power system grid in the region. System studies, planning and contingency analysis. Analysis of tripping/disturbances and facilitating immediate remedial measures. Daily scheduling and operational planning.
4/15/2013 42
NRLDC
Facilitating bilateral and inter-regional exchanges. Computation of energy dispatch and drawl values using SEMs. Augmentation of telemetry, computing and communication facilities
4/15/2013
43
of over 10,00,000 sq. km of area with nine States/Union Territories namely Punjab, Haryana, Rajasthan, Delhi, Uttar Pradesh, Himachal Pradesh, Uttaranchal, Jammu Kashmir and Union territory of Chandigarh, Generating Stations at Central and State Sector Independent Power producing stations, State DISCOMS, STU etc.
4/15/2013
44
33,785 MW as on 31.03.2006 with 16,295 MW in State Sector and 17,490 MW in Central Sector including BBMB.
iii) The States are inter-connected with each other through 400kV/220 kV network. Northern Region is connected to Western and Eastern regions through a few radial 220 kV/132 kV HVAC and HVDC Back to Back links to facilitate exchange of power from surplus to deficit region / State as well as wheeling of power.
4/15/2013 45
demand of 25,362 MW on 19.08.2005 with an average energy consumption of 462.96 MU during the year 2005-06.
4/15/2013
46
4/15/2013
47
4/15/2013
48
4/15/2013
49
4/15/2013
50
4/15/2013
51
4/15/2013
52
4/15/2013
53
4/15/2013
54
4/15/2013
55
4/15/2013
56
UNIT
MW MW MW MW
TOTAL CAPACITY
32791.75 1620
15122.75 4391.4
MW
53925.9
57
UNIT
MW MW MW MW
TOTAL CAPACITY
7909.95
TOTAL
4/15/2013
MW
64494.24
58
UNIT
MW
TOTAL CAPACITY
NUCLEAR
HYDRO RENEWABLE ENERGY SOURCES
MW
MW MW
TOTAL
4/15/2013
MW
UNIT
MW MW MW MW
TOTAL CAPACITY
22005.08 0 3882.12
398.71 26285.91
60
TOTAL
4/15/2013
MW
UNIT
MW MW MW
TOTAL CAPACITY
MW
MW
UNIT
MW MW MW MW
TOTAL CAPACITY
70.2 0 0
6.1 76.3
62
TOTAL
4/15/2013
MW
131703.4
4780.0
38990.4
24503.46
TOTAL
4/15/2013
MW
199977.2
63
UNIT
MW MW MW MW MW MW
TOTAL CAPACITY
112022.4
18481.05
1199.93
4780 38990.4 24503.46
MW
199977.2
64
4/15/2013
65
4/15/2013
66
STATE Uttar Pradesh Chhattisgarh Andhra Pradesh West Bengal Madhya Pradesh Uttar Pradesh Bihar Uttar Pradesh Orissa Uttar Pradesh Orissa Andhra Pradesh Uttar Pradesh Delhi Chhattisgarh Maharashtra
COMMISSIONED CAPACITY(MW) 2,000 2,600 2,600 2,100 3,260 2,000 2,340 1,820 3,000 1,050 460 2,000 440 705 2,320 500 29,195
Total
67
3,955
4/15/2013
68
Coal 1. Indira Gandhi STPP- JV with IPGCL & HPGCL (500) Haryana 500
2.
3. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Hydro 1. 2. 3.
Sipat I (660)
Simhadri II Unit - IV( 500) Vallur I -JV with TNEB ( 500) Vallur Stage-I Phase-II -JV with TNEB ( 1 x 500) Bongaigaon(3 x 250) Mauda Rihand III(2X500) Vindhyachal-IV (2X500) Muzaffarpur Expansion (2x195) JV with BSEB Nabinagar TPP-JV with Railways (4 x 250) Barh II (2 X 660) Barh I (3 X 660)
Chhattisgarh
Andhra Pradesh Tamilnadu Tamilnadu Assam Maharashta Uttar Pradesh Madhya Pradesh Bihar Bihar Bihar Bihar
660
500 500 500 750 500 1000 1000 390 1000 1320 1980
Koldam HEPP ( 4 x 200) Tapovan Vishnugad HEPP (4 x 130) Singrauli CW Discharge(Small Hydre)
800 520 8
Total
11,428
PERFORMANCE STATISTICS
YEAR
PLF(%)
2011-12
2010-11
85.00
88.29
2009-10
2008-09 2007-08 2006-07 2005-06
218.84
206.94 200.86 188.67 170.88
90.81
91.14 92.24 89.43 87.52
91.76
92.47 92.12 90.09 89.91
Actual Energy Generation (AG, measured ex-bus) would be different from scheduled and the deviations positive or negative settled at a price linked to system sufficiency, in that time slice.
Time slice of 15 minutes each in use Average Frequency of operation in the time slice used as an index of system sufficiency Settlement through a UI pool account
COMPONENTS OF ABT
1. CAPACITY CHARGE
2. 3. 4. 5.
APM
PMT
1. 2. 3. 4.
GAIL2-(SPOT)
RELIANCE APM+PMT+RIL RLNG+NEW SPOT
Remarks:-
5.955
2.748 2.485 4.015
26.070
12.018 10.837 17.575
1.The APM/PMT price was hiked by GOI to $4.2/MMBTU in June 2010 2.Dut to above the ECR of APM/PMT became almost double. 3.RIL gas was started from 01st Nov'09. 4.Additional RIL Gas Was started from Feb'10 & equivalent amount of APM/PMT is diverted from NCR to WR as per NTPC Management decision.
4/15/2013
79