Beruflich Dokumente
Kultur Dokumente
The event occurred on December 20, 2003 during the peak Christmas shopping season A fire occurred in a 12kV cable feeding a switch on the second floor of a 3 story indoor substation The substation receives power from 115kV underground cables and distributes 4 and 12kV within SF The fire caused a complete outage of the substation, effecting about 100,000 customers, some for as long as 32 hours
Timeline
15:51The network cable failed explosively. No customers lost power 15:51A circuit breaker protecting the N bus also operated 17:24The fire migrated to a bus duct above the switch and the burning bus caused the circuit breaker protecting another switch cabinet to operate, causing an outage to 3112 customers
Timeline
17:42A switchman was sent to Mission substation to investigate the incident 17:57All transmission circuit breakers were opened, causing an outage to approximately 100,000 customers
Investigation
CPUC assembled a team of engineers, analysts and attorneys to investigate the incident. During one of the interviews, the CPUC asked if there had been any previous incidents at Mission Substation involving fire. Yes, a previous incident occurred in 1996. The incident was very similar to the fire that occurred in 2003.
A vertically installed PILC cable caught on fire Smoke from that fire caused a short across the N bus Around 1:00am, a PG&E employee went to the substation to use a restroom and discovered the fire.
PG&E did not implement any of the key recommendations at Mission Substation by the time the incident occurred in 2003. CPUC published its report CPUC moved toward an Order Instituting Investigation (OII)
PG&E disputed our finding that the remedial measures would have made a difference. PG&E decided to settle the dispute via the Mission substation settlement agreement.
Settlement
PG&E, the City and County of San Francisco and the CPUC agreed that PG&E will pay $6.5 million, to various causes:
$500,000 to the States General Fund $3.0 million for reliability improvements to PG&E $750,000 for a fire safety program for SFFD $750,000 for CCSF to build needed infrastructure to improve public safety $1.0 million for a Hunters Point Substation Improvement Program $500,000 to support the Commissions undertaking to create a substation inspection program.
Meet with Five Investor Owned Utilities (PG&E, PP&L, SCE, SDG&E & SPP) Attended Training and Conferences concerning Substations and Equipment Attended CAISO audits of Utilitys Substation Programs
Two Choices
Prescriptive
Performance
Benefits Easy to Audit Easier to Understand Easily defined criteria Problems May require work to be done that is not needed Does not account for differences
Proposed General Order has both Prescriptive Parts and Performance Based Parts
Six Sections
General Provisions Definitions / Acronyms Construction Requirements Operation and Maintenance Program Reporting Requirements Maps and Drawings
13 pages
These rules are not intended as complete construction, inspection, or maintenance specifications, but embody only the minimum requirements which are most important from the standpoint of safety and reliability of service.
General Provisions Guarding Marking Safety Factor Requirements Secondary Oil Containment Switches
Operation and Maintenance Plan Utilities must file a copy of their Operation and Maintenance Plan yearly CPSD Audits Pre Inspection Report due 30 Calendar Days before Audit
Single Line Diagram Meter and Relay Drawing Physical Layout (e.g. Architectural drawings)
Map/Drawing Updates
180 Days
Start Inspections
Questions