TRAINING COMPANY:ANNAI INFRA DEVELOPERS PRIVATE LIMITED under the branch construction of Rock & arch construction india (P),ltd. Head office: 102,sheik Dawood street,Erode 638001.Tamil nadu. Ph.no:+914242241433 E-mail ID: annaiinfra@gmail.com Branch office: Tirunelveli
Hydraulic structures like dams and weirs Road work Bridges Residential building Apartments Multistory buildings
Training work site: Tirunelvei (Dam and bridge site) Residential building site Office work Training period: 15.05.2012 to 03.07.2012
Site-I Dam:
Location: Tirunelveli Stage of working process: Finishing stage at dam site (cleaning, plastering and painting)
Plastering works:
Wall Plastering:(inspection room, office room and control room) CM 1:5 wall plastering 12mm thickness 1 part of cement and 5 part of sand Materials used in plastering: Cement(opc 33grade) Sand(below 4.75mm FA)- FA means Fine Aggregate Water
Site-I Dam:
Equipment used in plastering: Trowel Bond Surface trowel Level tube Plum bop Mix proportion: CM 1:5 One part of cement and 5 part of cement w/c(water cement radio) 0.475
Vasthu(rules of building):
Materials details:
Cement Ramco cement 43Grade Partially replacing material is Fly ash Sand - replacing of crushed stone dust Jally - 20mm jally in Rcc 40mm jally in Pcc Bricks - standard bricks Replacing of Fly ash bricks (size 0.19x.9x.9m) Steel - fe 415, Dia rod: 25,20,18,16,10,12,8mm
Equipment details:
Trowel Bond Vibrator Needle vibrator Surface vibrator Shuttering sheet Concrete mixer Mixer machine Transit mixer Pump concrete Lift concrete
Materials:
Bricks: 9 4.5 Cement: 9 4.5 Sand: 9 4.5 -
required bricks in 100ft 1400bricks required bricks in 100ft 750bricks 2 .5 bags 1.5 bags 70cube.ft 45cube.ft
Materials rate:
Cement Sand Fly ash brick Jally Fly ash Stone dust
English Bond:
This pattern also uses alternate stretchers andheaders, but the headers are centered on the stretchers and the joints between the stretchers in all the courses in line up vertically.
Site III : Pre-Stressed concrete Bridge: Location: Tirunelveli Stage of work on process:
Shuttering is fixed at
deck slab. Piers formwork or removed
Reinforcement details:
Reinforcement on parapet
Reinforcement on slab
Finishing work:
Technician Duties:
Superstructure Substructure Spans and Span Length Simple and Continuous Spans
Title and Index Sheet Boring Data Sheets Layout Sheet General Plan Detail Plan Sheets Bridge Summary and Estimate of Quantities Sheets Standard Drawings Contractor Plans or Drawings
Bridge Plans
The main structural components of pre-stressed concrete T-Beam and slab bridge decks are 1)Deck slab 2)Main or longitudinal beam 3)Cross girders or diaphragms 4)Cantilever portion 5)Foot paths, kerbs and hand rails 6)Parapets 7)Wearing course
The two most important constituents of prestressed concrete which will influence the quality of bridge deck are a)Concrete b)High tensile steel
The following information is essntial for making any controlled concrete mix, Grade of concrete: IS code IRC:18-2000 min M35 max M60 Cement requirements: IRC code:21-2000 min 400 kg/m3 max 540 kg/m3 Types of Aggregate: nominal size 20 to 40mm Workability of fresh concrete: water/cement ratio 0.3 to 0.4
These joints become necessary due to the following a)Differential shrinkage of concrete b)Creep or inelastic deformation of concrete c)Thermal expansion and contraction of the super structure and in some cases even the sub structure d)Elastic shortening of concrete due to prestress e)Displacements of the structure under load or any other action
Classification of Bridges
Material
Usage Span Structural Form
Steel Concrete Wood Hybrid Stone/Brick
Pedestrian Highway Railroad Short Medium Long
Structural Arrangement
Culvert Bridge
Slab Bridges
T-Beam Bridge Wood Beam Bridge Pre-cast Concrete Box Beam Bridge Pre-cast Concrete I-Beam Bridge Rolled Steel Beam Bridge