Materials requirements planning (MRP) is the logic for determining the number of parts, components, and materials needed to produce a product. MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced. Dependent demand drives MRP. MRP is a software system.
Dependent Demand
(components)
B(4)
D(2) E(1) D(3)
C(2)
F(2)
Objectives of MRP
Improve customer service Reduce inventory cost Enhancing operating efficiency
Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items.
Determines the dates when orders for those materials should be released, based on lead times.
10
Inventory transactions
Component or Subassemblies BOM create an artificial parent to the BOM used for inexpensive items like washers or pins to group.
Coding
Item is coded at lowest level at which it occurs D (Level 2 or Level 3) This number identifies the part at the lowest level of usage.
Pegging
Identify each parent item that created demand. Parent= Items above the current level Child = Items below the current level
Planned orders to be released at a future time. Order release notices to execute the planned orders. Changes in due dates of open orders due to rescheduling. Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule. Inventory status data.
Gross Requirements: needed during each period. Scheduled Receipts: Existing orders that arrive at beginning of period. On-hand or available balance:
Net requirements: What is need to meet requirements and safety stock. Planned order receipt: arrives at beginning of period. Planned order release: Addresses lead time.
MRP Examples
No Feedback Realistic?
Feedback
Yes
Execute: Capacity Plans Material Plans