First Floor Columns & Second Floor Slab

Prepared by

Elton Gallimore

Scope of Works
Area of construction: 86.4m x 46.8m grid= 4043.52 m2. To construct 39 First Floor reinforced steel concrete columns at 60 x 30 cm to a height of 2.10m.

To construct a Second Floor Slab to an area of 4043.52 m2 thickness of 250mm. Height from first floor slab 2.45m

Area of Construction (zones)


15.6m

7.2m

Area of construction (sections)

46.8m

86.4m

Section Breakdown

Safety Platform Assembly


Access to workable Areas will be via Temporary stairs Which be moved According to Construction schedule Week one Week two

Week

Week

Zone 1 Column formwork Sections 1-9 Column formwork arrangement with re bar 3 gangs (2 men per gang), 1 gang per column 1 column + rebar 30mins 12 columns = 2hrs.

Zone 2 Column formwork Sections 10-18 Column formwork arrangement with re bar 4 gangs (2 men per gang), 1 gang per column 1 column + rebar 30mins 9 columns = 1.5hrs.

200kg of 10mm steel rebar per m3 of concrete (Peri requirements)

Zone 3 Column formwork Sections 19-27 Column formwork arrangement with re bar 4 gangs (2 men per gang), 1 gang per column 1 column + rebar 30mins 9 columns = 1.5hrs.

Zone 4 Column formwork Sections 30-34 Column formwork arrangement with re bar 4 gangs (2 men per gang), 1 gang per column 1 column + rebar 30mins 9 columns = 1.5hrs.

200kg of 10mm steel rebar per m3 of concrete (Peri requirements)

Column formwork detail

Positioned to monolithic kickers from ground floor columns

Ground floor

First floor

Column formwork Sequence

Column formwork assembly zone 1


Retaining wall

Column formwork assembly zone 1

Column formwork assembly zone 1

Zone 1 Ready for pour / first floor slab construction still in progress

Zone 1 & 2 Concrete pour complete

Assembly of Peri LIWA lightweight panel


Zone 1 4 sections of wall formwork to be assembled 1 gang (2 men) per wall section 15 mins per m2 111.72 m2 approx. 1hr 45mins. Zone 3 3 sections of wall formwork to be assembled 1 gang (2 men) per wall section

15 mins per m2
35.28 m2 approx. 45 mins.

Zone 2

3 sections of wall formwork to be assembled


1 gang (2 men) per wall section 15 mins per m2 35.28 m2 approx. 45 mins.

Zone 4 sections of wall formwork to be assembled 1 gang (2 men) per wall section 111.72 m2 approx. 1hr 45mins.

LIWA lightweight panel concrete pour


Zone 1 4 sections of wall to be poured; 2 sections of 15.6 x 0.30m @ 2.45m height 2 sections of 7.2 x 0.30 @ 2.45m height Amount of concrete required 33.5 m3 Zone 4 Zone 2 3 sections of 7.2 x 0.30m @ 2.45 height Amount of concrete required 31.8 m3 4 sections of wall to be poured; 2 sections of 15.6 x 0.30 @ 2.45m height 2 sections of 7.2 x 0.30 @ 2.45m height Amount of concrete required 33.5 m3 Zone 3 3 sections of 7.2 x 0.30m @ 2.45 height

Amount of concrete required 31.8 m3

Skydeck slab formwork assembly

90 panels of Skydeck per section Panels @ 1.50 x 0.75

2.45m

810 panels for each zone


1.125m2 per section

First floor slab 150 kg of steel rebar for every m3 of concrete (Peri requirements)

Beams and slab rebar


Beams integrated into slab formwork

Beam layout for each zone

Section of slab rebar

Framing and shear wall assembly

Skydeck slab formwork assembly

Zone 1 Skydeck slab panels & beam formwork assembled, ready for concrete pour

Zone 2 slab concrete pour complete

Zones 3 & 4 column formwork assembly and pour, Zone 3 wall assembly and pour

Repositioning of plant machinery

Zone 4 shear wall assembly and pour/ Zone 3 Slab concrete pour complete

Zone 4 slab concrete pour complete

Handover