Prepared by
Elton Gallimore
Scope of Works
Area of construction: 86.4m x 46.8m grid= 4043.52 m2. To construct 39 First Floor reinforced steel concrete columns at 60 x 30 cm to a height of 2.10m.
To construct a Second Floor Slab to an area of 4043.52 m2 thickness of 250mm. Height from first floor slab 2.45m
7.2m
46.8m
86.4m
Section Breakdown
Week
Week
Zone 1 Column formwork Sections 1-9 Column formwork arrangement with re bar 3 gangs (2 men per gang), 1 gang per column 1 column + rebar 30mins 12 columns = 2hrs.
Zone 2 Column formwork Sections 10-18 Column formwork arrangement with re bar 4 gangs (2 men per gang), 1 gang per column 1 column + rebar 30mins 9 columns = 1.5hrs.
Zone 3 Column formwork Sections 19-27 Column formwork arrangement with re bar 4 gangs (2 men per gang), 1 gang per column 1 column + rebar 30mins 9 columns = 1.5hrs.
Zone 4 Column formwork Sections 30-34 Column formwork arrangement with re bar 4 gangs (2 men per gang), 1 gang per column 1 column + rebar 30mins 9 columns = 1.5hrs.
Ground floor
First floor
Zone 1 Ready for pour / first floor slab construction still in progress
15 mins per m2
35.28 m2 approx. 45 mins.
Zone 2
Zone 4 sections of wall formwork to be assembled 1 gang (2 men) per wall section 111.72 m2 approx. 1hr 45mins.
2.45m
First floor slab 150 kg of steel rebar for every m3 of concrete (Peri requirements)
Zone 1 Skydeck slab panels & beam formwork assembled, ready for concrete pour
Zones 3 & 4 column formwork assembly and pour, Zone 3 wall assembly and pour
Zone 4 shear wall assembly and pour/ Zone 3 Slab concrete pour complete
Handover