EXCAVATION AND BASE PREPARATION

LNG TANK Erection Sequence

BASE SLAB REBAR AND CONCRETE EXCAVATION AND BASE PREPARATION

LNG TANK Erection Sequence

5M X 5M OPENING IN CONCRETE WALL

WALL CONSTRUCTION ROOF ERECTION 2- TOWER CRANES OUTSIDE 2-PLACER BOOM WITH CONC. PUMP & POURER

LNG TANK Erection Sequence

WALL CONSTRUCTION ROOF ERECTION BASE VAPOUR BARRIER INSTALLATION INSIDE CRANES TAKEN OUT

LNG TANK Erection Sequence

WALL CONSTRUCTION ROOF ERECTION BASE VAPOUR BARRIER INSTALLATION

LNG TANK Erection Sequence

WALL CONSTRUCTION ROOF ERECTION SUSPENDED DECK ERECTION

LNG TANK Erection Sequence

WALL CONSTRUCTION ROOF ERECTION SUSPENDED DECK ERECTION ON STAGING

LNG TANK Erection Sequence

WALL CONSTRUCTION COMPRESSION PLATE INSTALLATION ROOF ERECTION SUSPENDED DECK ERECTION

LNG TANK Erection Sequence

WALL CONSTRUCTION COMPRESSION PLATE INSTALLATION ROOF ERECTION SUSPENDED DECK ERECTION

LNG TANK Erection Sequence

WALL CONSTRUCTION COMPRESSION PLATE INSTALLATION ROOF ERECTION SUSPENDED DECK ERECTION

LNG TANK Erection Sequence

INSTALL AIRLIFT EQUIPMENT COMPLETE AIR LIFT PREPARATION KING POST REMOVED ACCESS OPENING CLOSED

LNG TANK Erection Sequence

COMMENCE AIR LIFT

LNG TANK Erection Sequence

AIR LIFT

LNG TANK Erection Sequence

AIR LIFT COMPLETED WELD ROOF TO COMPRESSION PLATE

LNG TANK Erection Sequence

INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM, CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS ERECT ROOF WALKWAYS LNG TANK POST TENSION TANK OUTER WALL

Erection Sequence

INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM, CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS ERECT ROOF WALKWAYS POST TENSION TANK OUTER WALL

LNG TANK Erection Sequence

INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM, CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS ERECT ROOF WALKWAYS POST TENSION TANK OUTER WALL

LNG TANK Erection Sequence

ERECT INNER TANK AND WALL VAPOUR BARRIER INSTALL ROOF FITTINGS AND TANK INTERNALS ERECT ROOF PLATFORMS POST TENSION TANK OUTER WALL

LNG TANK Erection Sequence

ERECT INNER TANK SHELL AND VAPOUR BARRIER COMPLETE BOTTOM INSULATION, SECONDARY BOTTOM AND INNER TANK BOTTOM INSTALL ROOF FITTINGS AND TANK INTERNALS ERECT ROOF PLATFORMS POST TENSION TANK OUTER WALL

LNG TANK Erection Sequence

ERECT INNER TANK AND VAPOUR BARRIER INSTALL ROOF FITTINGS AND TANK INTERNALS ERECT ROOF PLATFORMS POST TENSION TANK OUTER WALL

LNG TANK Erection Sequence

INSTALL FOAM GLASS TO WALLS AND 36% NICKEL INSTALL ROOF FITTINGS AND TANK INTERNALS POST TENSION TANK OUTER WALL

LNG TANK Erection Sequence

COMMENCE HYDROTEST INSTALL ELECTRICS INSTALL PIPEWORK INSTALL INSTRUMENTS

LNG TANK Erection Sequence

COMMENCE HYDROTEST INSTALL ELECTRICS INSTALL PIPEWORK INSTALL INSTRUMENTS

LNG TANK Erection Sequence

PERFORM HYDROTEST INSTALL ELECTRICS INSTALL PIPEWORK INSTALL INSTRUMENTS

LNG TANK Erection Sequence

PUMP OUT WATER AND CLEAN DOWN INNER TANK INSTAL ELECTRICS INSTAL PIPEWORK INSTALL INSTRUMENTS

LNG TANK Erection Sequence

INSULATE INNER TANK SHELL INSULATE SUSPENDED DECK

LNG TANK Erection Sequence

INSULATE INNER TANK SHELL INSULATE SUSPENDED DECK

LNG TANK Erection Sequence

FILL INTERSPACE WITH PERLITE

LNG TANK Erection Sequence

COMMISSION TANK

LNG TANK Erection Sequence