To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
S precedes T, which precedes U.
AOA
S 1 2 T 3 U 4
AON
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
S and T must be completed before U can be started.
AOA
1 S U T 2 3 4
AON
S U T
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
T and U cannot begin until S has been completed.
AOA
T 2 U 4 3 S
AON
T
S 1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
U and V cannot begin until both S and T have been completed.
AOA
1 S U 3 4 S
AON
U
T
2
V
5 T V
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
U cannot begin until both S and T have been completed; V cannot begin until T has been completed.
AOA
S 1 T 2 3 U 5 S
AON
U
Dummy V 4 6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
T and U cannot begin until S has been completed; V cannot begin until both T and U have been completed.
AOA
S
1 2 Dummy 3
AON
V
4 5 S T V
U U
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity A B C D E F
Description
G H I J K
Select administrative and medical staff. Select site and do site survey. Select equipment. Prepare final construction plans and layout. Bring utilities to the site. Interview applicants and fill positions in nursing, support staff, maintenance, and security. Purchase and take delivery of equipment. Construct the hospital. Develop an information system. Install the equipment. Train nurses and support staff.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network A Select administrative and medical staff. B Select site and do site survey. A C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview Start applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the hospital. I Develop and information system. J Install the equipment. K Train nurses and support staff.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network A Select administrative and medical staff. B Select site and do site survey. A C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview Start applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the B hospital. I Develop and information system. J Install the equipment. K Train nurses and support staff.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network A Select administrative and medical staff. B Select site and do site survey. A C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fill positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the B hospital. I Develop and information system. J Install the equipment. K Train nurses and support staff.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network A Select administrative and medical staff. B Select site and do site survey. A C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fill positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. I Develop and information system. J Install the equipment. K Train nurses and support staff.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network A Select administrative and medical staff. B Select site and do site survey. A C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fill positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. I Develop and information system. J Install the equipment. K Train nurses and support staff. E
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network A Select administrative and medical staff. B Select site and do site survey. A F C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fill positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. I Develop and information system. J Install the equipment. K Train nurses and support staff. E
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network A Select administrative and medical staff. B Select site and do site survey. A F C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fillG positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. I Develop and information system. J Install the equipment. K Train nurses and support staff. E
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network A Select administrative and medical staff. B Select site and do site survey. A F C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fillG positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. H I Develop and information system. J Install the equipment. K Train nurses and support staff. E
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network I A Select administrative and medical staff. B Select site and do site survey. A F C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fillG positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. H I Develop and information system. J Install the equipment. K Train nurses and support staff. E
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network I A Select administrative and medical staff. B Select site and do site survey. A F C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fillG positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. H J I Develop and information system. J Install the equipment. K Train nurses and support staff. E
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network I A Select administrative and medical staff. B Select site and do site survey. A F K C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fillG positions in nursing, Start applicants C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. H J I Develop and information system. J Install the equipment. K Train nurses and support staff. E
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AON Network I A Select administrative and medical staff. B Select site and do site survey. A F K C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview and fillG positions in nursing, Start applicants Finish C support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the D B hospital. H J I Develop and information system. J Install the equipment. K Train nurses and support staff. E
Figure 4.2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AOA Network A Select administrative and medical staff. 2 B Select site and do site survey. C Select equipment. D Prepare A final construction plans and layout. E Bring utilities to the site. F Interview Start applicants and fill positions in nursing, 1 staff, maintenance, and security. support G Purchase and take delivery of equipment. H Construct the hospital. I Develop and information system. J Install the equipment. K Train nurses and support staff.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AOA Network A Select administrative and medical staff. 2 B Select site and do site survey. C Select equipment. D Prepare A final construction plans and layout. E Bring utilities to the site. F Interview Start applicants and fill positions in nursing, 1 staff, maintenance, and security. support G Purchase and take delivery of equipment. H Construct B the hospital. I Develop and information system. J Install the equipment. 4 support staff. K Train nurses and
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AOA Network A Select administrative and medical staff. 2 B Select site and do site survey. C C Select equipment. D Prepare A final construction plans and layout. 3 the site. E Bring utilities to F Interview Start applicants and fill positions in nursing, 1 staff, maintenance, and security. support G Purchase and 5 take delivery of equipment. H Construct B the hospital. I Develop and information system. D J Install the equipment. 4 support staff. K Train nurses and
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AOA Network F A Select administrative and medical 8 staff. 2 B Select site and do site survey. I C C Select equipment. D Prepare A final construction plans and layout. 3 the site. 7 E Bring utilities to F Interview and fill positions in nursing, Start applicantsG 1 staff, maintenance, and security. support H G Purchase and 5 take delivery 6 of equipment. H Construct B the hospital. E I Develop and information system. D J Install the equipment. 4 support staff. K Train nurses and
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AOA Network F A Select administrative and medical 8 staff. 2 B Select site and do site survey. I C C Select equipment. D Prepare A final construction plans and layout. 3 the site. 7 J E Bring utilities to F Interview and fill positions in nursing, Start applicantsG 1 staff, maintenance, and security. support H G Purchase and 5 take delivery 6 of equipment. H Construct B the hospital. E I Develop and information system. D J Install the equipment. 4 support staff. K Train nurses and
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AOA Network F A Select administrative and medical 8 staff. 2 B Select site and do site survey. I Dummy C C Select equipment. D Prepare A final construction plans and layout. 3 the site. 7 J E Bring utilities to F Interview and fill positions in nursing, Start applicantsG 1 staff, maintenance, and security. support H G Purchase and 5 take delivery 6 of equipment. H Construct B the hospital. E I Develop and information system. D J Install the equipment. 4 support staff. K Train nurses and
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Description AOA Network F A Select administrative and medical 8 staff. 2 B Select site and do site survey. I Dummy C C Select equipment. K A D Prepare final construction plans and layout. 3 the site. 7 J E Bring utilities to F Interview and fill positionsFinish in nursing, Start applicantsG 1 staff, maintenance, and security. support 9 H G Purchase and 5 take delivery 6 of equipment. H Construct B the hospital. E I Develop and information system. D J Install the equipment. 4 support staff. K Train nurses and
Figure 4.3
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity I Completion Time Description 15 A Select administrative and medical staff. B Select site and do site survey. A F K C Select equipment. 12 10 6 D Prepare final construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
Figure 4.4
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity I Completion Time Description 15 A Select administrative and medical staff. B Select site and do site survey. A F K C Select equipment. 12 10 6 D Prepare final construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity I Completion Time Description 15 A Select administrative and medical staff. B Select site and do site survey. A F K C Select equipment. 12 10 6 D Prepare final construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity I Completion Time Description 15 A Select administrative and medical staff. B Select site and do site survey. A F K C Select equipment. 12 10 6 D Prepare final construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity I Completion Time Description 15 A Select administrative and medical staff. B Select site and do site survey. A F K C Select equipment. 12 10 6 D Prepare final construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity I Completion Time Description 15 A Select administrative and medical staff. B Select site and do site survey. A F K C Select equipment. 12 10 6 D Prepare final construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Path
Activity Description I Completion Time A-F-K 28 15 A Select administrative and medical staff. A-I-K 33 B Select site and do site survey. A-C-G-J-K 67 A F K C Select equipment. 12 10 6 B-D-H-J-K 69 D Prepare final B-E-J-K 43 construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Path
Activity Description I Completion Time A-F-K 28 15 A Select administrative and medical staff. A-I-K 33 B Select site and do site survey. A-C-G-J-K 67 A F K C Select equipment. 12 10 6 B-D-H-J-K 69 D Prepare final B-E-J-K 43 construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Path
Activity Description I Completion Time A-F-K 28 15 A Select administrative and medical staff. A-I-K 33 B Select site and do site survey. A-C-G-J-K 67 A F K C Select equipment. 12 10 6 B-D-H-J-K 69 D Prepare final B-E-J-K 43 construction plans and layout. E Bring utilities to the site. C G F Interview nursing, Start applicants and fill positions in Finish 10 35 support staff, maintenance, and security. G Purchase and take delivery of equipment. B D H J H Construct the hospital. 9 10 40 4 I Develop and information system. J Install the equipment. E K Train nurses and support staff.
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
I 15
A 12
F 10
G 35
Start
10
Finish
D
10
H 40
J 4
E 24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
15
A 12
F 10
G 35
Start
10
Finish
D
10
H 40
J 4
E 24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
15
A 12 12
F 10
G 35
Start
10
Finish
D
10
H 40
J 4
E 24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
I 15
A 12 12
F 10
G 35
Start
10
Finish
B 9
D
10
H 40
J 4
E 24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
I 15
A 12 12
F 10
G 35
Start
10
Finish
B 9
D 19
10
H 40
J 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27 15
A 12 12
12
F 22 10
Start
12
C 22 10
G 35
Finish
B 9
D 19
10
H 40
J 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27 15
A 12 12
12
F 22 10
Start
12
C 22 10
G 35
Finish
B 9
D 19
10
19
H 59 40
J 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27 15
A 12 12
12
F 22 10
Start
12
C 22 10
22
G 57 35
Finish
B 9
D 19
10
19
H 59 40
J 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27 15
A 12 12
12
F 22 10
Start
12
C 22 10
22
G 57 35
Finish
B 9
D 19
10
19
H 59 40
59
J 63 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27 15
A 12 12
12
F 22 10
63 K 69
Start
Critical path
0
12
C 22 10
22
G 57 35
Finish
B 9
D 19
10
19
H 59 40
59
J 63 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27 15
A 12 12
12
F 22 10
63 K 69
Start
12
C 22 10
22
G 57 35
Finish
B 9
D 19
10
19
H 59 40
59
J 63 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27 15
A 12 12
12
F 22 10
63 K 69 63 69
Start
12
C 22 10
22
G 57 35
B 9
D 19
10
19
H 59 40
59
J 63 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27 15
A 12 12
12
F 22 10
63 K 69 63 69
Start
12
C 22 10
G 57 35
B 9
D 19
10
19
H 59 40
59
J 63 4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
A 12 12
12 22 53 10 63
63 K 69 63 69
Start
12
C 22 10
22
G 57 35
Finish
B 9
D 19
10
19
H 59 40
59 63 59 4 63
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
A 12 12
12 22 53 10 63
63 K 69 63 69
Start
12
C 22 10
22 57 24 35 59
Finish
B 9
D 19
10
19 59 19 40 59
59 63 59 4 63
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
A 12 12
12 22 53 10 63
63 K 69 63 69
Start
12 22 14 10 24
22 57 24 35 59
Finish
B 9
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
12 22 53 10 63
Start
Critical path
0 0
12 22 14 10 24
22 57 24 35 59
Finish
B 9 9 9
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
0 12 2 12 14
12 22 53 10 63
63 K 69 63 69
Start
12 22 14 10 24
22 57 24 35 59
Finish
0 0
B 9 9 9
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
0 12 2 12 14
12 22 53 10 63
63 K 69 63 69
12 22 14 10 24
22 57 24 35 59
Finish
0 0
B 9 9 9
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
0 12 2 12 14
12 22 53 10 63
63 K 69 63 69
12 22 14 10 24
22 57 24 35 59
Finish
0 0
B 9 9 9
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
0 12 2 12 14
12 22 53 10 63
63 K 69 63 69
12 22 14 10 24
22 57 24 35 59
Finish
0 0
B 9 9 9
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
LS 2 0 14 9 35 53 24 19 48 59 63
Slack 2 0 2 0 26 A 12 0 41 2 12 14 2 0 36 0 0
B 9 9 9
12 27 48 15 63
12 22 53 10 63
63 K 69 63 69
12 22 14 10 24
22 57 24 35 59
Finish
0 0
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Node Duration ES A B C D E F G H I J K 12 9 10 10 24 10 35 40 15 4 6 0 0 12 9 9 12 22 19 12 59 63
LS 2 0 14 9 35 53 24 19 48 59 63
Slack 2 0 2 0 26 41 2 0 36 0 0
B 9 9 9
12 27 48 15 63
12 22 53 10 63
63 K 69 63 69
12 22 14 10 24
22 57 24 35 59
Finish
0 0
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
Critical Path
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12 27 48 15 63
0 12 2 12 14
12 22 53 10 63
63 K 69 63 69
Start
12 22 14 10 24
22 57 24 35 59
Finish
0 0
B 9 9 9
9 19 9 10 19
19 59 19 40 59
59 63 59 4 63
Critical Path
9 E 33 35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Project Crashing
Crashing
reducing project time by expending additional resources
Crash time
an amount of time an activity is reduced
Crash cost
cost of reducing activity time
Goal
reduce project duration at minimum cost
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
2 8 1
12
4
12
7 4
3 4 6 4
5 4
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
$5,000 $4,000
$3,000
$2,000 $1,000
Crash time
Normal activity
Normal cost
Normal time
| 2
| 4
| 6
| 8
| 10
| 12
| 14
Weeks
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
ACTIVITY
1 2 3 4 5 6 7
12 8 4 12 4 4 4
7 5 3 9 1 1 3
5 3 1 3 3 3 1
$75,000
$110,700
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
$500
2 8 1
12
$7000 4
12
FROM
$400
3 4 $3000
5 4 $200
$7000 4
12
$700
TO
Project Duration: 31 weeks Additional Cost: $2000
1
7
7 4
6 4 $200
$400
3 4
5 4 $200
$3000
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Time-Cost Relationship
Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Time-Cost Tradeoff
Minimum cost = optimal project time Total project cost Indirect cost Cost ($)
Time
Probability
Time a m Mean
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probability
3s
3s
Time b
m Mean
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Start
Finish
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Start
Finish
7 + 4(8) + 15 te = = 9 weeks 6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Start
Finish
7 + 4(8) + 15 te = = 9 weeks 6
s2 =
15 - 7 6
) = 1.78
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Time Estimates (wk) Optimistic Activity (a) A B C D E F G H I J K 11 7 5 8 14 6 25 35 10 1 5 Likely (m) 12 8 10 9 25 9 36 40 13 2 6 Pessimistic (b) 13 15 15 16 30 18 41 45 28 15 7
Activity Statistics Expected Variance Time (te ) (s 2 ) 12 9 10 10 24 10 35 40 15 4 6 0.11 1.78 2.78 1.78 7.11 4.00 7.11 2.78 9.00 5.44 0.11
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
s2
= (variances of activities)
T TE z= s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
s2
= (variances of activities)
T TE z= s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
s2
= (variances of activities)
T TE z= s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
s2
= (variances of activities)
T TE z= s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
s2
= (variances of activities)
T TE z= s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
TE = 69 days
s2
activities)
T-T
Figure 4.12
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
s2
= (variances of activities)
T TE z= s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Start
Time
Finish
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Construct a PERT Network from the following set of activities, their precedences requirements and 3 time-estimates of completion time. Compute the slack for each activity and determine the critical path.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity
Precedences
Optimistic
Pessimistic
Most Likely
None
B
C D E F G H I
None
A B C C C, D F, G E
8
7 6 9 10 11 6 4
8
11 6 11 18 11 14 6
8
9 6 10 14 11 10 5
J
K
I
H
3
1
5
1
4
1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Costs in dollars
Job Description
Normal
Crash
Normal
Crash
None
80
100
40
94
Rewind armature
12
100
184
Replace bearings
70
102
B, C and D
50
50
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
The fixed cost per day is $ 20 per day. As a policy the firm does not allow an activity to be crashed by more than a day for fear of poor quality. (Except in case of C which can be crashed by a maximum of 4 days) i. Draw the activity on arc network. ii. Find the optimum project duration.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.