In case of any Issue: Contact directly the TI person on the field and the CMT person responsible for Site creation during that night.
Keep an eye on CGI (especially Cell ID) in GSM Current Channel Window in
TEMS. Cross Feeder Test should be down by checking the difference of Rxlev for each TRX under same Sector if difference is high Drive Tester shall coordinate with the TI person on field to resolve the problem.
Make short calls with the call duration of 10 seconds after the call setup on each
sector. (All TRXs should be checked in this by making 5 Calls on each TRX). Cross Feeder Test should be down by checking the difference of Rxlev for each TRX under same Sector if difference is high Drive Tester shall co-ordinate with the TI person on field to resolve the problem. After doing the 5 short calls on each TRX, EDGE/GPRS testing should be done at the same time.
Then the drive tester should move to the next sector and do the short calls and
then the EDGE/GPRS test, this procedure should be followed for all the sectors.
The EDGE/GPRS testing should include to check PDP Context Activitation, Cell
Reselection (GPRS-EDGE-GPRS) and RA update.
The 1st tier InterSite neighbours will be checked in the end. If the road is not
available a forced handover should be done. If the nearest site is far away and handover is not possible because of its weak Rxlevel then a comment should be put in the checklist
The drive for Intersite HO should be done both in Idle and dedicated mode. After Doing the Activity, Please carefully fill the Checklist (attached below)&
submit to the NSN RF Team.