Beruflich Dokumente
Kultur Dokumente
E, EE/P&C,TNEB)
2600MVA 110KV 8 110/33KV 10MVA Z% = 10.8 7 33KV 5 15.7KM J0.625 /km 33KV 4 33/11KV 5MVA Z% = 6.5 3 11KV 2 1 A B 6 C D
Yy0
Dy1
2.5MVA
2.5MVA
For the 5MVA transformer (4), MVA Fault level of Bus D Fault level of Bus C
1 + 1 . 2600 92.59 1 = 49.48 MVA 1 + 1 + 1 . 2600 92.59 111 1 = 49.48 MVA 1 + 1 + 1 + 1 . 2600 92.59 111 77
D 2
2600MVA (Source)
2600 MVA
92.59MVA
C 3 B 4 A 77MVA 111MVA
89.28 MVA
49.48 MVA
30.12 MVA
SELECTION FOR CT RATIO :The CT ratio is selected using the higher of the following two currents. the nominal current the maximum short circuit current for which no saturation is occurred (0.05 x Isc)
Relay 1 &2 : Inom 1 = Inom 2 = Pnom 1 3 x V1 = 2.5 x106 . 3 x 11 x 103 = 131.22 A (referred to 11KV)
Relay No
1 & 2 3 4
Pnom MVA
2.5 5 5
Isc A
1581.21 1581.21 866.37
CT Ratio
5
6
5
5
1564.42
1564.42
78.22
78.22
87.48
87.48
100/5
100/5
7
8
10
10
1564.42
13646.41
78.22
174.96 200/5
700/5
682.32 52.49
Distribution lines: Since the distribution lines are the end of the system any one of the following criteria may be adopted. i) 50% of the maximum fault current at the point of connection of the CT supplying relay. ii) Between six and ten times of the maximum load current.
Transformer units: The instantaneous units of over current relays on the primary side of the transformer should be set between 125 and 150% of the short circuit current at the bus bar on the secondary side, referred to the primary side. If the instantaneous units of the transformer secondary and feeder relays are subjected to same short circuit level then the transformer secondary instantaneous over current unit needs to be overridden to avoid loss of coordination.
Set the relay at 27A secondary amps equivalent to 810A primary amps.
Relay 3 The instantaneous unit is overridden to avoid the possibility of loss of co-ordination.
Relay 4
The setting is based on 125% of the short circuit current that exists at the busbar on the low voltage side of the transformer, referred to the high voltage side. Iinst = 1.25 x1581.21 x (11/33) = 658.84 A primary amps =658.84 x(5/100) = 32.94A secondary amps
ie
Relay 5 The setting is calculated on the basis of 125% of the current for the maximum fault level that exists at the next downstream substation. Iinst = 1.25 x 866.37 =1082.96 A primary amps ie = 1082.96 x (5/100) = 54.15A secondary amps Set 55 amps equivalent to 1100 primary amps. Relay 6 Iinst ie
Relay7 The instantaneous unit is overridden to avoid the possibility of loss of co-ordination. Relay 8 The setting is calculated on the basis of 125% of the current for the maximum fault level that exists at the next downstream substation referred to the high voltage side Iinst = 1.25 x 1564.42 x (33/110) = 586.66 A primary amps ie = 586.66 x (5/700) = 4.19A secondary amps Set at 6 secondary amps (the minimum setting) equivalent to 840 primary amps.
PICK-UP SETTING:
The pick-up setting or plug setting is determined by the following expression. Pickup setting = OLF x Inom CTR
The overload factor(OLF) recommended for various circuits are given below.
For phase fault relays: For motor 1.05 For lines, generator, and transformers 1.25 to 1.5 For distribution feeders under emergency condition 2 For earth fault relays: For lines, generator, and transformers For transmission lines For distribution feeders
Calculation of pick-up settings: PU = OLF x Inom CTR Relay 1 &2 PU 1,2 =1.5 x 131.22 x (5/150) =6.56; set at 7 Relay 3 PU 3 =1.5 x 262.44 x (5/300) =6.56; set at 7 Relay 4 PU 4 =1.5 x 87.48 x (5/100) =6.56; set at 7 Relay 5 PU 5 =1.5 x 87.48 x (5/100) =6.56; set at 7 Relay 6 PU 6 =1.5 x 87.48 x (5/100) =6.56; set at 7 Relay 7 PU 7 =1.5 x 174.96 x (5/200) =6.56; set at 7 Relay 8 PU 8 =1.5 x152.49 x (5/700) =0.56; set at 1
determine the required operating time t1 of the relay farthest away from the source by choosing the lower time multiplier setting and considering the fault level for which the instantaneous unit of this relay picks up. This may be higher if it is necessary to co-ordinate with devices installed downstream. eg. Fuses or reclosers and condition like cold load pick-up.
determine the required operating time of the relay associated with the next upstream breaker t2a = t1 + tmargin. Use the same fault level that used to determine t1 of the relay associated with the previous breaker for this calculation also.
For the same fault current as in 1 above and knowing t2a and pick-up value for relay 2, calculate time multiplier setting of the relay 2. Determine the operating time t2b of relay 2, but now using the fault level just before the operation of its instantaneous unit. Continue with the sequence, starting from the second stage.
Time discrimination margin : A discrimination margin between two successive time characteristic of the order of 0.2 to 0.4s should be typically used. The operating time of the relay can be obtained from the operating characteristic on log-log paper or from the mathematical formula given below. t = k +L (I/Is) - 1 Where I = fault current, Is = pick-up setting. K = time multiplier setting, L a constant t = relay operating time in sec
By knowing the PSM and operating time the equation can be solved for TMS Curve description standard Moderately inverse IEEE 0.02 0.0515 Very inverse IEEE 2 19.16 Extremely inverse IEEE 2 28.2 inverse CO8 2 5.95 Short time inverse CO2 0.02 0.0239 Standard inverse IEC 0.02 0.14 Very inverse IEC 1 13.5 Extremely inverse IEC 2 80 Long time inverse IEC 1 120
By knowing the PSM and operating time the equation can be solved for TMS
For relays associated with breakers 1 & 2 choose the smaller multiplier setting and calculate the operating time.
Relays 1 & 2
Choose time multiplier setting k = 0.05 PSM = Iinst.sec x (1/PU1,2) = 27 x (1/7) = 3.857 times t1 = 0.05 x 13.5 3.857 - 1 = 0.236 sec or say 0.24 sec
Relay 3 The relay backs up relay 1 and 2 Use a grading margin of 0.4sec There fore the required operating time is t3a = 0.24+0.4 = 0.64 PSM is based on 810 primary amps associated the instantaneous setting of relays 1 & 2 So PSM3a = 810 x(1/CTR3) x (1/PU3) = 810 x (5/300) x(1/7) = 1.928 times
k = (PSM 1) x t3a 13.5 = (1.928 1) x 0.64 13.5
Since in this case the instantaneous unit is overridden the short circuit current is used and multiplied by the factor 0.86 in order to cover the delta-star transformer arrangement.
So PSM3b = 0.86 x Isc x (1/CTR) x (1/PU3) = 0.86 x 1581.21 x (5/300) x (1/7) = 3.238 times With time multiplier setting 0.05 and PSM3b of 3.238 the operating time of the relay t3b = 0.05 x 13.5 3.238 - 1 = 0.3sec
Relay 4 The relay 4 backs up relay 3 Use a grading margin of 0.4sec Hence the required operating time is t4a = 0.3+0.4 =0.7 PSM4a is based on 1581.21 primary amps of the CT associated with relay 3
It is now necessary to calculate the operating time of relay 4 just before the operation of the instantaneous unit. PSM4b = Iinst.prim4 x (1/CTR4) x (1/PU4) = 660 x (5/100) x (1/7) = 4.714 times
With time multiplier setting 0.14 and PSM4b 4.714 t4b = 0.14 x 13.5 = 0.51sec 4.714 - 1
Relay 5
The relay 5 backs up relay 4 Use a grading margin of 0.4sec Hence the required operating time is t5a=0.51+0.4=0.91 PSM5a is based on 660 primary amps of the CT associated with relay 4 So PSM5a = 660 x (5/100) x (1/7) = 4.714 times With PSM5a = 4.714 and backup time of 0.91 k = (4.714 1) x 0.91 = 0.25 13.5
It is now necessary to calculate the operating time of relay 5 just before the operation of the instantaneous unit. = Iinst.prim5 x (1/CTR5) x (1/PU5) = 1100 x (5/100) x (1/7) = 7.857 times
PSM5b
With time multiplier setting 0.25 and PSM5b 7.857 t5b = 0.25 x 13.5 = 0.492sec 7.857 - 1
Relay 6
Time multiplier setting = 0.3 (assume slightly higher setting than relay 5 for clarity of problem
Relay 7
Relay 7 backs up relay 5 & 6 and should be coordinated with the slower of these two relays. Relay 5 has an instantaneous setting of 1100primary amps and relay 6 has an instantaneous setting of 1000 primary amps. Therefore the operating of both the relays should be calculated for 1000 primary amps current.
Relay 5; PSM5 = 1000 x (5/100) x 1/7) = 7.14 times With PSM = 7.14 and time dial setting 0.25 t5 = 0.25 x 13.5 = 0.55sec 7.14 - 1
Relay 6; PSM6 = 1000 x (5/100) x 1/7) = 7.14 times With PSM = 7.14 and time dial setting 0.3 t6 = 0.3 x 13.5 = 0.66sec 7.14 - 1
Therefore, in order to be slower than relay 6, the back up time of relay 7 should be
t7a = 0.66+0.4 = 1.06 sec
PSM7a is based on the 1000 primary amps of the CT associated with relay 6 So, PSM7a = Iinst.prim7 x (1/CTR7) x (1/PU7) = 1000 x (5/200) x (1/7) = 3.57 times = 3.57 and backup time of 1.06 sec = (3.57 1) x 10.6 = 0.2 13.5
With PSM7a k
As the instantaneous unit is overridden, the multiplier PSM7b is calculated using the current for a short circuit on busbar C = Isc x (1/CTR7) x (1/PU7) = 1564.42 x (5/200) x (1/7) = 5.5 times
So, PSM7b
With time multiplier setting 0.2 and PSM7b 5.5 T7b = 0.2 x 13.5 = 0.6sec 5.5 - 1
Relay 8
The relay 8 backs up relay 7 Use a grading margin of 0.4sec Hence the required operating time is t8a = 0.6+0.4 = 1.0 sec PSM8a is based on 1564.42, the short circuit current of busbar C referred to 110 KV bus, since the instantaneous unit of relay 7 is overridden. So PSM8a = 1564.42 x (33/110) x (5/700) x (1/1) = 3.35 times With PSM8a = 3.35 and backup time t8a = 1 k = (3.35 1) x 1 = 0.17 13.5
Tms
Inst pri sec 0.05 810 27 0.05 overridden 0.14 600 33 0.25 1100 55 0.3 1000 50 0.2 overridden 0.17 840 6