INDEX
Raw
Materials Products & Capacity Process Details Source Of Pollution (Air ,Water, Hazardous &Solid Waste Etc.), Treatment Facilities Water Balance Chart Material Balance Chart Compliance Of Conditions
Made by Viplove Singh & Rajiv Sharma
BOARD OF DIRECTORS
Mr. Pradip Kumar Daga : Chairman Mr. Vikram Prakash Agarwal : Director Mr. Yashwant Daga : Director Mr. P K Drolia : Director Mr. J N Pathak : Director Mr. S B Sharda : President
Made by Viplove Singh & Rajiv Sharma
COMPANY PROFILE
Established
1991 Corporate Office : Kolkota Present capacity including count range are given below: Spindles Capacity: Existing -25000 & additional Expansion-13200 and it will be 38200 Production Capacity: Existing- 28000 Kg/day & additional Expansion- 14000 Kg/day and it will be 42000 Kg/day Product range : Synthetic blended Grey & Dyed(Black) Yarns & OPT White Yarn Count range : 8s to 40s
Made by Viplove Singh & Rajiv Sharma
The existing power requirement of the Guna unit from CPP unit with a capacity of 3 MW Biomass based Power Project Reference no. UNFCCC 00000095CDMP
33KV ,1 MW (Max Demand) from M.K.V.V.Co.Ltd. 2Nos 1250 KVA & 1 No. 1325 KVA DG Set as a backup arrangement.
Statement of Area
Existing Capacity 25000 Spindles & Investment 74.14 Crore New Expansion 13200 Spindles & Investment 64.59 Crore
SPINNING PROCESS
The process of converting fibres from ginned lint into a yarn involves a number of processes that aim to clean, remove short fibres, align fibres and ultimately spin the yarn and prepare it for delivery Depending on the setup and machinery present in a spinning mill and the desired quality of the yarn needed to be produced will determine which processes are undertaken
Carding
After Carding
Speed Frame
QUALITY CONTROL
Packing
Sources of pollution
Air Pollution
Terma
cyclone system in the Boiler & same is working satisfactory . We have improved the arrangement to avoid the dust formed near the Ash collecting hopper ,as we have water spray system on the ash belt & also providing the water Sprinkling System & the operators have been instructed to have regular watch for cleaning materials, sprinkling & good house keeping practices
Made by Viplove Singh & Rajiv Sharma
Water Pollution
We
commissioned & taken the trial of the S.T.P system in the premises. Our industry is not generating any process effluent.
Decanto r
Areation tank
dosing of chlorine Collection Tank
Air Blower
Lummela Tank
Flowculatio n tank
Medi aFilt er
Effluent
slug pump
FLOW CHART
Effluent
Cont..
After 8 days water into decantor tank via flowculation tank
1. In Flowculation tank, Dosing of Alum 20kg/200liter -(10 ppm) solution, 2.In Areation Tank,Dosing of Polyelectrolyte 200g/200liter-(1ppm) solution) it will rum 24 hour
During this time slug pump will be operated and its outlets biomass to areation tank. Limit of biomass in areation tank will be 25 to 30 % upto 30 %,biomass will go in slugbed Tank (one by one)
Made by Viplove Singh & Rajiv Sharma
Cont..
Via Lummela Tank through level control as overflow
To start the HP pump and give the outlet to media filter(need backwash after every 8 hr)
Polyelectroly te
Dosing of Alum
dosing of chlorine
-Nil
Wastes
Used Oil During the previous financial year 8-10 Kg During the current financial year 08-09 Kg
From process
3.Industry shall take adequate precautionary Taken care measures before and during operation, maintenance and cleaning of pollution control equipment to avoid any accidental hazard. 4.Extensive tree plantation shall be carried out in Plantation is already open area available within the factory premises in existing in open area consultation with the expert agency and good Made by Viplove Singh & Rajiv Sharma housekeeping practices shall be adopted.
5.Industry shall install separate meter in accordance Already installed & to Rule-3 of Water Cess Rules, !978 for the Sr.No. & Report measurement of water consumption in all the four submitted in MPPCB categories as mentioned in Schedule-II of Water (Prevention & Control of Pollution) Cess Act, 1977. 6.Industry shall submit environmental statement for the Submitted previous year ending 31st March on or before 30th September every year to the Board.
7.Industry Shall make proper arrangement for the Complied disposal of solid waste, also valid authorization under Hazardous Waste (Management, Handling & Tran boundary Movement) Rules, 2008 shall be obtained from the Board. 8.Industry shall comply with all the relevant acts/rules, I Agree direction, guidelines, notifications issued by MoEF/CPCB/MMPCB from time to time as required and if applicable. 9.Industry shall submit a fresh application for next I Agree renewal of consent fee u/s 25/26 of Air (prevention & Control of Pollution) Act, 1974,180 days before the expiry Made by Viplove Singh & Rajiv Sharma of the date of this consent renewal letter.
Air Consent (Compliance Of Conditions ) 1.The industry shall improve their existing Already maintained as
pollution control facilities and maintain the per MPPCB norms same properly so that the emission could be maintained within the prescribed standards. 2.Industry shall take adequate precautionary Taken care measures before and during operation, maintenance and cleaning of pollution control equipment to avoid any accidental hazard.
3.Extensive tree plantation shall be carried out in Plantation is already open area available within the factory premises in existing in open area consultation with the expert agency and good housekeeping practices shall be adopted.
4.Industry shall submit environmental statement Submitted for the previous year ending 31st March on or before 30th September every year to the Board.
5.Industry shall make proper arrangement Complied for the disposal of solid waste, also valid authorization under Hazardous Waste (Management, Handling & Tran boundary Movement) Rules, 2008 shall be obtained from the Board. 6.Industry shall comply with all the relevant I Agree acts/rules, direction, guidelines, notifications issued by MoEF/CPCB/MMPCB from time to time as required and if applicable. 7.Industry shall submit a fresh application for I Agree next renewal of consent u/s 21 of Air (prevention & Control of Pollution) Act, 1981,180 days before the expiry of the date of this consent renewal letter.
Thank You
Deepak Spinners Ltd