HEIJUNKA

AUTOMOTIVE SYSTEMS INGEENIERING

TOYOTAS HOUSE

HEIJUNKA DEFINITON
HEI: Plane JUN: Level KA: Performance Leveling customer demand through the volume of production in a uniform period of time

GENERAL OBJETIVE
Load balance production lines, having an order of manufacture of the products.

SPECIFIC OBJETIVES

Remove Mudas by

standardization of work. Reduce inventories.

HEIJUNKA CHARACTERISTICS
It can be used in conjunction with other tools of Lean

Manufacturing. Brings stability in the manufacturing process Product Leveling Production Leveling

HEIJUNKA BOX
Also called leveling box, is a physical tool used to level the volume and variety of production for a certain period of time (pitch) using kanban cards.

Important Concepts
Takt time It refers to the rate of production of the company based on customer demand.

Pitch: Refers to the number of pieces per unit time based on takt time

Example
Products Daily Requirement Quantity Per Pack # of kanbans A01 300 15 20 B02 240 15 16 C03 180 15 12 D04 60 15 4 TOTAL 780 60 52

Production time:

8hrs x 60 min = 480 min 2 breakfast 15 min= -30 min Rest 10 min= -10 min --------------440 min

440 min x 60 x2 = 52,800 seconds


8

Takt time= 52.800 seconds / 780 units = 67.6 seconds Pitch= 67.6 sec. x 15 units = 1,014 seconds or 16.9 min.

So: The leveling of the production is to be achieved as follows:


Product Quantity

A01
B02 C03 D04

20
16 12 4
9

Representation of a Heinjunka box

10

HEIJUNKA BOX CHARACTERISTICS


One row for each product
A column for each pitch A single kanban card in each box

Levels of lines in order


Check the pitch

1 1

1 2

CONCLUTIONS
Calcular takt time.

Crear la caja heijunka

Calcular el pitch de cada producto.

Establecer el ritmo de produccin

13

REFERENCIAS
Manual de Lean Manufacturing gua bsica 2da. Edicin. Autores: Alberto Villaseor Contreras, Edber Galindo Cota, editorial LIMUSA. Pginas consultadas 93 101
LEAN MANUFACTURING pginas consultadas 137-139

Creating your lean future state, how to move from seeing to doing chapter 5 load leveling, or heijunka. Autores: Tom Louyster, Don Tapping, pginas consultadas: 105 - 115