Beruflich Dokumente
Kultur Dokumente
MS EM-03
LECTURE 09
Resource Person
Topics Covered
Program
Project
Sample
TE=(a + b + 4m)/6
Var=V= 1/36 (b - a)
2
(already discussed)
The variance is a measure of uncertainty of the duration. The larger variance, the larger is the uncertainty.
Probability
Pr = (D T) /
D= deadline / desired completion time T= project completion time = normal distribution (from table)
Problem 09
(Use Pert Technique on P-04)
Activity Preceding Activity A B C D A E B F B G C H D, E I F, G Duration (weeks) 10 07 12 18 14 13 16 12 06
B
C D E F
7
12 18 14 13
5
10 16 13 10
9
20 32 21 16
G
H I
16
12 6
15
11 5
23
19 7
B
C D E F
7
12 18 14 13
5
10 16 13 10
9
20 32 21 16
7
13 20 15 13
G
H I
16
12 6
15
11 5
23
19 7
17
13 6
B
C D E F
7
12 18 14 13
5
10 16 13 10
9
20 32 21 16
7
13 20 15 13
.44
2.78 7.11 1.78 1
G
H I
16
12 6
15
11 5
23
19 7
17
13 6
1.78
1.78 .11
= 11+20+13 = 44
Variance V= Va + Vd + Vh = 1.78+7.11+1.78= 10.67
Probability
Pr = (D T) / D= deadline / desired completion time=40 T= project completion time=44 Pr = (40 44) / 3.266 = (-1.23) = 0.11
The chance of meeting the deadline is 11 percent only.
D= 48.2
E S U L
In order to have 90 percent guarantee against a delay, the deadline should be 49 days.
Comments on Pert
Program evaluation and review technique (PERT) allows activity duration with uncertainty. It assumes that there is no underlying connection leading to simultaneous duration variation of two or more activities. If activity X is delayed, this does not lead to a similar delay of activity Y. This is, of course, a questionable assumption. Quite often there are activities that are connected.
For example, a delay of an activity may be caused by a shortage of labor. In this case it is reasonable to believe that this is the case for other activities performed in the same region.
Project Crashing
Activity time can be reduced by utilizing additional resources i-e additional labor, more equipment and so on.
Project Crashing
Although shortening or crashing activity times can be expensive; doing so might be worthwhile. This is also referred as cost-time trade-offs.
Crash time: amount of time an activity is reduced Crash cost: cost of reducing activity time
Project Crashing
Rules:
Crash the activities on the critical path. As a result of crashing, a parallel non-critical path may become new critical path.
Start crashing with least cost of crashing per unit time, crash the most costly activity if required, last of all.
Project Crashing
2
3
1
4
6
4
2
3
3 Reduce it to 06 days
Project Crashing
Act- Normal Normal Crash Crash Cost ivity Time Cost Time Cost Time (days) ($) (days) ($) crash cost per unit time 1-2 3 40 1 80 (80-40)/(3-1) =20 1-3 2 50 1 120 1-4 2-4 3-4 6 4 3 100 80 60 4 2 1 140 130 (130-80)/(4-2) =25 140
Project Crashing
Activity 1-2 and Activity 2-4; both are on critical path. The project completion time can be reduced to six days by crashing either 1-2 or 2-4 by one day. It costs $20 per day to crash activity 1-2 and $25 per day to crash activity 2-4. Therefore it is less costly to crash activity 1-2 by one day in order to achieve an over all project completion time of six days.
Problem 10
The data of activities, activity precedence, activity normal and crash times and costs for a pipe line renewal is given in the table on next slides. a) Develop a network for the project.
b) Determine the project completion time with normal time of activities. c) Crash the project to reduce the project completion time with least incremental cost.
Note: Time is given in days and cost in rupees.
Remaining Problem 10
Activity Prece- Normal Normal Crash Crash dence time cost time cost A 3 1 B 4 4 C A 2 900 1 1000 D C 1 300 1 300 E D 5 2500 3 3000 F D 9 900 5 1200 G E 5 3500 2 5000 H B, D 1 300 1 300 I B, D 2 900 1 1200 Go on next slide for remaining data of Problem 10
Remaining Problem 10
Activity Prece- Normal Normal dence time cost j H, I 4 1200 K G, J 6 4200 L K 2 800 M F, H, I 2 500 N L, M 2 500 O N 2 400 P L, M 4 1200 Q N, P 2 400 R O, Q 2 400 Crash time 2 3 1 1 1 1 2 1 1 Crash cost 2000 5400 1000 800 800 600 1600 600 500