SLIDE 1/14
PROJECT TITLE
PROGRAM FOR CALCULATING REORDER POINT & SAFETY STOCK LEVELS
SLIDE 2/14
MAJOR VARIABLES
Committed Active
FERT Capacities
Material
Lead Times
SLIDE 3/14
SOME
QUESTIONS
WHY FOCUS OF REORDER POINTS AND SAFETY STOCK LEVELS? WHY DO WE NEED INVENTORY?
& THEIR
ANSWERS
TO BALANCE INFLOWS AND OUTFLOWS TO CATER FLUCTUATIONS IN DEMAND TO MINIMIZE HOLDING, FIXED COST AND OTHER TIED-UP FUNDS
WHY DO WE OPTIMIZE?
SLIDE 4/14
SLIDE 5/14
BALANCE INFLOWS WITH OUTFLOWS HIGH QUALITY PRODUCTS ON LOWEST POSSIBLE COSTS MINMIZE INVENTORY WITHOUT COMPROMISE RM AVAILABILITY OPTIMAL INVENTORY LEVELS TO REVEAL PROBLEMS
SLIDE 6/14
PROJECT DELIVERABLES
Optimal inventory levels A program to identify the quantities of raw materials INPUT: Forecasted values of order quantities OUTPUT: Production Budget for all Raw Materials Identify possible opportunity costs for planned projects.
SLIDE 7/14
SOP BIRDS-EYE-VIEW
SLIDE 8/14
PROCESSOR
SFG QUANTITY BOMs
INPUT
OUTPUT
Programs\Program 1\Processor.xlsx
SLIDE 9/14
PROCESSOR
STANDARD DEVIATION
NORMAL DISTRIBUTION RM = SAFETY STOCK+LEAD TIME DEMAND
INPUT
OUTPUT
Programs\Program 2.xls
SLIDE 12/14
THE SOP
SELECT A RAW MATERIAL
CALCULATE STOCK-OUT COST (M) IN PRODUCT OF GROSS PROFIT % AND RM USD/PAA QUANTITY USAGE PER PAA CALCULATE HOLDING COST (H) OF IDENTIFY COST OF RM PER UNIT AREA USING RM FOR DURATION OF LEAD TIME IN WAREHOUSE COST CENTRE VALUES USD/PAA IDENTIFY SERVICE LEVEL IDENTIFY PAST SALES OF RM USING PROGRAM-1 FORECAST QUANTITY AS PER LEAD TIME CALCULATE REORDER POINT & SAFETY STOCK LEVELS USING PROGRAM-2
SERVICE LEVEL, p
FIND ITS USAGE AS PER FORECAST FROM THE OUTPUT OF PROGRAM-1
SELECT A FORECASTING MODEL TO KNOW THE QUANTITY FOR THE DURATION OF LEAD TIME
USE THE EXCEL SHEET AS SHOWN: Programs\Program 2.xls
SLIDE 13/14
SAMPLE
SELECT A RAW MATERIAL
ZARN: LYCRA 44 Dtex/166L WHITE M = (72% x 0.00023) + 0.00023 = USD 0.004 Programs\STOCK OUT COST.xlsx H = USD 5e-8 Programs\CARRYING COST.xlsx p = 0.99 Programs\SERVICE LEVEL.xlsx
CALCULATE STOCK-OUT COST (M) IN USD/PAA CALCULATE HOLDING COST (H) OF RM FOR DURATION OF LEAD TIME IN USD/PAA IDENTIFY SERVICE LEVEL
AVERAGE CONSUMPTION = 18.4 KG/MONTH EXCEL ADD-IN USED FOR FORECASTING FOR THE LEAD TIME DURATION ROP = 60 KG, SAFETY STOCK = 18 KG Programs\Program 2.xls
SLIDE 14/14
CONCLUSION
LYCRA 44 Dtex/166L WHITE RAW MATERIAL ACTUAL SAFETY STOCK 0 CALCULATED 18
REORDER POINT
100
60
ALSO IN IDENTIFYING WHEN THE ORDER MUST BE PLACED, KEEPING IN MIND THE CONSUMPTION AND LEAD TIME