Beruflich Dokumente
Kultur Dokumente
Chapter 16
When
a
plan specifying how many and when the firm plans to build each end item
Aggregate Plan (Product Groups)
Schedules production and purchases Principal input to MRP schedule Basis for determining resource requirements Provides basis for making delivery promises to customers
demand data
inventory status
Terminology
Parent
item: An item manufactured from one or more components. An item that goes into one or more parent items. of Materials (BOM): A diagram or record that shows all components going into an item and the usage quantities.
Component: Bill
Parts
Components Production
Planning
BOM
options
Fractional
Terminology
Usage
Part
End
Terminology
Intermediate
Item: An item with at least one parent and at least one component. Special case of intermediate item; it is assembled from more than one component. Item: An item with no components, coming from a supplier.
Subassembly:
Purchased
Time Fences
Frozen
Moderately Firm
Flexible
Time Fences
Frozen Capacity Firm Customer Orders Moderately Firm Flexible Forecast and available capacity
15 Weeks
26
MRP Requirements
Computer
inventory accuracy
Stable
lead times
MRP Benefits
Increased customer satisfaction due to meeting delivery schedules Faster response to market changes Improved labor & equipment utilization Better inventory planning & scheduling Reduced inventory levels without reduced customer service
Lead Times
MRP Programs
Inventory Data
Creates schedules identifying the specific parts and materials required to produce end items
Determines exact numbers needed Determines the dates when orders for those materials should be released, based on lead times
B(4)
D(2) E(1) D(3)
C(2)
F(2)
9 50
10 50
LT = 1 day
9 50
10 50
20 20 200
200
Spares
Day: A LT=1 B LT=2 C LT=1 D LT=3 E LT=4 F LT=1 Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement
9 50 200 100
10 50
400 200
200 200
Part D: Day 6
40 + 15 spares
C(2) F(2)
50 A 20 B (Spares) 15 D (Spares)
orders
Order
to
release notices
Changes
or suspensions of open
orders
due
Inventory
status data
Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10.
Requirements
On-hand Net
Planned Planned
order release
On Hand Required
2
3 1
X
A B
50
75 25
45 15 20 35 40 80
2
2
C
D
10
20
45 45
On Hand Required
2
3 1
X
A B
50
75 25
45 15
2
2
C
D
10
20
20 35/40 80
Item X A B C D
Week Required Released Required Released Required Released Required Released Required Released
10
45 45 15 15 20 35 40 80 20 40 80
35
Simulate
accounts payable, project planning, work force planning, etc. into MRP
Oracle