Beruflich Dokumente
Kultur Dokumente
Presented by:
Shweta Jangid Gaurav Jindal Puneet Joshi Bhupesh Kachhwaha Hemant T Kantiwal Dipesh Kapoor Mohd. Waseem Khan Gaurav Uday Khatri Darsh Kumar Khatwani
MRP
Material requirements planning (MRP): Computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials.
Dependent Demand
B(4)
C(2)
D(2)
E(1)
D(3)
F(2)
Dependent Demand
Objectives of MRP
Master Production Schedule (MPS) Bills of Materials (BOM) Inventory Status File
Inventory transactions
Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items
Determines exact unit numbers needed Determines the dates when orders for those materials should be released, based on lead times
Production sequence
Subassemblies Fractional options
Visual depiction of the requirements in a bill of materials, where all components are listed by levels.
Contains an extensive amount of information on every item that is produced, ordered, or inventoried in the system like
Identification number Quantity on hand Safety stock level Quantity disbursed Procurement lead time of every item
MRP Matrix
Gross Requirement Derived from planned order releases of the parent Actual / estimated demand, in case of final product Schedule Receipts Items on order Scheduled to arrive in the future time period Projected on hand Current inventory, or anticipated inventory at the end of period
MRP Matrix
Net requirements
Actual quantity to produce based on projected on hand and on-order quantity Quantity, when orders need to be received Consider lot sizing rule: When order need to be placed to receive on time Consider lead time
Lot-Sizing in MRP
Lot-size is the quantity ordered/produced at one time Large lots are preferred because:
Changeovers cost less and capacity greater Annual cost of purchase orders less Price breaks and transportation breaks can be utilized
Lower inventory carrying cost Reduced risk of obsolescence Shorter cycle time to produce customer order
EXAMPLE 1
Requirements include 95 units (80 firm orders and 15 forecast) of X on 10th day.
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
A(2)
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release
10 95 50 45 45
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
A(2)
B(1)
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release
10 95 50 45 45
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
A(2)
B(1)
C(3)
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release
10 95 50 45 45
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
A(2)
B(1)
C(3)
C(2)
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release
10 95 50 45 45
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
A(2)
B(1)
C(3)
C(2)
D(5)
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release
10 95 50 45 45
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
EXAMPLE 2
Pressboa rd (1)
Rivet s (2)
Level 1
Piv ot (1)
Sprin g (1)
Level 2
EXAMPLE 3
Bicycle(1) P/N 1000 Handle Bars (1) P/N 1001 Frame Assy (1) P/N 1002 Frame (1) P/N 1004
EXAMPLE 4
To produce an end item A component B/unit of end item is needed. It takes two weeks to produce a batch of component B.
Stock in hand 170 units 50 unites will be completed at the beginning of week 2
Average Weekly Demand 100 units Set-up Cost $90 Inventory Holding Cost 20%/unit/week
LOT-FOR-LOT Method
Week
1 Gross Requirement On-hand inventory Scheduled receipts Net requirements Planned production 50 100 170 150 20 2 50 20 50 3 70 0 50 50 0 4 100 0 100 100 150 0 200 5 0 0 6 150 0 150 150 100 7 200 0 200 200 0 8 100 0 100 100 80 0 20 9 0 0 10 80 0 80 80 160 11 20 0 20 20 0 12 160 0 160 160 0
LOT-FOR-LOT Method
Set-up cost
= 8 set-ups * $90 per set-up = $720
Holding cost
= 20 units in week 1 * 0.2 + 20 units in week 2 * 0.2 = $8
Average Weekly Demand (R) 100 units Set-up Cost (cp) $90 Inventory Holding Cost (ch) 20%/unit/week EOQ = 2Rcp ch = 20*100*90 0.2 300 units
Set-up cost
= 3 * $90 = $270
Holding cost
= 1150 * $0.2 = $230
EXAMPLE 5
(A) Transmission(1)
Forging Blank 40 2 Suppose we are to produce 40 trucks. What are the net requirements for each component?
Lead Low Item Time On Level Identif. WEEK Weeks hand Code
10
50
10 10 10 10 10 10 10
40 40 40 40 20 20 20 20 20 20 20 20
20
Gross Requirements Scheduled Receipts Projected on Hand 20 20 20 Net Requirement Planned Order Receipts Planned Order Releases
Lead Low Item Time On Level WEEK Weeks hand Code Identif.
24
Gross Requirements
Scheduled Receipts Projected on Hand 24 24 24 Net Requirement Planned Order Receipts Planned Order Releases
40
24 24 24 16 16 16 40 18 18 22 22
18
Gross Requirements
Scheduled Receipts
Projected on Hand 18 18 18 Net Requirement Planned Order Receipts
22
Lead
40
200
Projected on Hand 40 40 40 40 Net Requirement Planned Order Receipts Planned Order Releases 160
160 160
EOQ example
Setup cost, S = $100 Unit price, C = $50 Holding costs, HR = .24 per annum HP = .02 per period Annual demand, D = 200 Q = (2DS / CHR)1/2 = 58
Period Net rqmts. Planned orders 1 35 58 2 10 3 4 40 58 5 6 20 7 5 8 10 58 9 30 10
MRP Example:-
MRP Example:-
Level 0
Product structure for Awesome(A) A C(3) Std. 12Speaker kit w/ amp-booster F(2) Std. 12 Speaker booster assembly
D(2) 12 Speaker Amp-booster
E(2)
E(2)
D(2) Packing box and installation kit of wire, bolts and screws
G(1)
12 Speaker
2 weeks
2 weeks to produce
1 week E 1 week
C
Item A B C D E F G
Inventory on hand 10 15 20 10 10 5 0
Week
Gross Requirement Scheduled Receips Projected on Hand 10 Net Requirement Planned Order Receipts Planned Order Releases
2 3 4 5 6
8
50
10 10 10 10 10 10 10 10 40 40 A 40
15
Gross Requirement Scheduled Receips Projected on Hand 15 Net Requirement Planned Order Receipts Planned Order Releases
80 15 15 15 15 15 15 15 65 65 65
Week
1 2
3 4
Gross Requirement Scheduled Receips Projected on Hand 20 20 20 Net Requirement Planned Order Receipts Planned Order Releases
6 7 8 A 120
20 20 100 100
20 20
20
100
10
Gross Requirement Scheduled Receips Projected on Hand 10 10 10 Net Requirement Planned Order Receipts Planned Order Releases
Item Identificatio n
F
Week
Gross Requirement Scheduled Receips Projected on Hand 5 Net Requirement Planned Order Receipts Planned Order Releases
1
5
2
5
3 4
5 5
5
5
6
C 200 5 195 195
195
10
F 390 B 130 Gross Requirement Scheduled Receips Projected on Hand 10 10 10 10 Net Requirement 380 130 Planned Order Receipts 380 130 Planned Order Releases 380 130 F 195 Gross Requirement Scheduled Receips Projected on Hand 0 Net Requirement 195 Planned Order Receipts 195 Planned Order Releases 195
This is what we want to develop, the final materials requirements plan. Lets see how we got to this
50
Day: Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement
9 50 200 100
10 50
400 200
200 200
A
Part D: Day 6
C(2) F(2)
40 + 15 spares
First, the number of units of A are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of A on the 9th day to receive them in the 10th day.
Day: A Required Order Placem ent 1 2 3 4 5 6 7 8 9 50 10 50
LT = 1 day
Next, we need to start scheduling the components that make up A. In the case of component B we need 4 Bs for each A. Since we need 50 As, that means 200 Bs. And again, we back the schedule up for the necessary 2 days of lead time.
Day: A B R e q u ire d O rd e r P la c e m e n t R e q u ire d O rd e r P la c e m e n t 20 200 20 50 200 1 2 3 4 5 6 7 8 9 10 50
Next, we need to start scheduling the components that make up A. In the case of component B we need 4 Bs for each A. Since we need 50 As, that means 200 Bs. And again, we back the schedule up for the necessary 2 days of lead time.
Day: A B R e q u ire d O rd e r P la c e m e n t R e q u ire d O rd e r P la c e m e n t 20 200 20 50 200 1 2 3 4 5 6 7 8 9 10 50
Spares
4x50=200
Finally, repeating the process for all components, we have the final materials requirements plan:
Day: A LT=1 B LT=2 C LT=1 D LT=3 E LT=4 F LT=1 Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement 1 2 3 4 5 6 7 8 9 50 200 100 55 55 20 200 200 200 400 300 20 200 400 100 300
54
10 50
20 20 200
A
2x50=100
Part D: Day 6
40 + 15 spares
C(2)
LT = 1
F(2)
THANKS