Beruflich Dokumente
Kultur Dokumente
Minggu 13
Project Proposal is an engineering decisionmaking process for a given situation or problem Example :
Additional Manufacturing Facility Alternatives :
Lease an existing building Construct a New Building Contract for the manufacturing to be done overseas
The Question is how to choose between alternatives either its a Mutually Exclusive Alternatives or a Single Project Proposals.
Eliminate from further consideration any alternative that fails to meet the minimum level of economic attractiveness.
CRITERIA FOR REJECTING UNNATTRACTIVE ALTERNATIVES
Reject alternative when Do NOT reject alternative when i > MARR PW benefits > PW cost
EUAC, EUAB
Benefit-cost ratio, B/C Net Present Worth, NPW
CRITERIA FOR CHOOSING THE BEST ALTERNATIVES FROM AMONG MUTUALLY EXCLUSIVE ALTERNATIVES
Analysis Method
Situation
Fixed input
Fixed output
Benefit-Cost Ratio
7
8 9
300
300 50
19.464
47.4 7
4
10 10
0
100 50
10%
12% 14%
30 %
25%
20%
Pick those with a higher rate of return. When the projects are arrayed by rate of return, as in figure, as follows, then Projects 3,1,4,5,6, and 2 is correct decision for the available budget of $650 Cut Off Rate Of Return
15%
10%
CutOff Rate of Return is the point where the money runs out to approving projects In other words, the minimum attractive rate of return to get a project accomplished is CutOff Rate of Return
Frequently, Capital Budgeting Problem is one where we will be unable to accept all desirable projects. Lorie and Savage showed that the proper technique is to use a multiplier, p, to decrease the attractiveness of an alternative in proportion to itsuse of the scarce supply of money.
NPW p (PW cost)
Multiplier p is adjusted until the total cost of the projects meeting the [NPW p (PW cost)] criterion equals the available money supply.
Project
Cost
UAB
Salvage Value
Computed NPW ($) 60.04 67.40 11.91 55.48 80.52 67.10 13.46
1 2 3 4 5 6 7
8
9
300
50
47.4
7
10
10
100
50
64.38
20.13
Project
Cost
1
2 3 4 5 6 7 8 9
100
200 50 100 100 100 300 300 50 1300
60.04
67.40 11.91 55.48 80.52 67.10 13.46 64.38 20.13
40.04
27.40 1.91 35.48 60.52 47.10 - 46.54 4.38 10.13
100
200 50 100 100 100
35.04
17.40 0.59 30.48 55.52 42.10 - 61.54
100
200
300 50 1000
- 10.62 7.63
300 50 650
For a value of p equal to 0.25, the best selection is computed to be Projects 1,2,4,5,6, and 9
Rank Independent projects according to their value of net present worth divided by the present worth of cost. The appropriate interest rate is MARR (as a reasonable estimate of the cutoff rate of return)
Project
Cost
UAB
Rate Of Return 20% 15% 25% 20% 20% 18% 10% 12% 14%
Comput ed NPW at 14.5% 22.01 3.87 6.81 21.10 28.14 17.91 -27.05 -31.69 -1.28
Cmoputed NPW/Cost 0.2201 0.0194 0.1362 0.2110 0.2814 0.1791 -0.0902 -0.1056 -0.0256
1 2 3 4 5 6 7 8 9
0.2814
1
4 6 3
0.2201
0.2110 0.1791 0.1362
2
9 7 8
0.0194
-0.0256 -0.0902 -0.1056
Its not a satisfactory ranking criterion and would have given a different ranking from the present wirth criterion