1. STARTING TEST
1. Starting test to be carried out as per Class Rules for starting system of the main engine.
a. b. For reversible engine, the staring system shall capable for 12 times start, for non-reversible engine for 6 times.
2. 3.
For electric starter: the starting system is to be confirmed to start as engine manufacturer guidance. Items of Measurement: Total number of starting Functional test confirmation
Items of Measurement: Vessels speed Main Engine parameters; Rpm, Throttle position, and other necessary items Weather, sea state condition, relative velocity, direction of wind, and depth of sea.
ii.
Items to be measured:
(1) Measurement on Stop Astern Test: i. Vessels speed each 10 second interval by Speed Log on the wheel house. ii. Vessels heading angle each 10 second interval by Gyro compass. iii. ME rpm each 10 second interval correspondingly. iv. Wind direction and velocity, weather state, and sea depth at the beginning of the test. v. Time elapsed from signal fullastern to the complete stop, i.e. from the Main engine to be stopped engine begins to rotate astern up to the vessel is completely stopped.
(2) Measurement on Stop Ahead Test: i. Vessels speed each 10 second interval by Speed Log on the wheel house. ii. Vessels heading angle each 10 second interval by Gyro compass. iii. ME rpm each 10 second interval correspondingly. iv. Wind direction and velocity, weather state, and sea depth at the beginning of the test. v. Time elapsed from signal full-ahead to the complete stop, i.e. from the Main engine to be stopped engine begins to rotate ahead up to the vessel is completely stopped.
6. TURNING TEST
Purpose:
To examine the vessels turning maneuverability, maximum advance, and maximum tactical diameter of turning.
Procedure:
Turning test shall be measured at 100% Main engine Load (fullthrottle) then the steering rudder to be moved maximum (as per design) to the starboard and portside, and the position to be kept until the vessel reach the turning of 360O from the original course.
Items to measure:
i. ii. iii. iv. v. Vessels speed each 10 second interval by speed log Vessels heading angle each 10 second interval by gyro compass Shaft rpm each 10 second interval accordingly Wind direction and velocity, weather state, and sea depth at the beginning of the test. Tactical diameter and advanced diameter.
Procedure:
Having the vessel initially in full-ahead-speed on 100% MCR, the Zigzag test is to be carried out, as follows: i. Direct the vessel to the heading 20O starboard. ii. When the heading of the vessel has been reaching 20O to the starboard from the initial course, portside the helm 20O iii. When the heading of the vessel has been reaching 20O to the portside from the initial course, starboard the helm 20O iv. Repeatedly, carry out the step no ii. v. When the vessels heading return to initial course, the test is finished.
KIND OF TESTS:
1. Loading Test: The windlass shall be functionally tested by hoisting up 55 mm (2 fathoms) of chains from the state in which 82.5 (3 fathoms) of anchor chains are submerged and freely suspended at commencing of lifting. 2. Chain Drum Brake Test: The chain drum brake shall be tested with the anchor dropping at every approximately fathoms of chains to confirm safe paying out and holding of the anchor chains by means of braking the chain drum.
Items of Measurement:
a. Weather, wind velocity and direction, and water depth. b. Hoisting speed (required time for hoisting 1 fathoms).
Items of measurement:
Required time to start and to connect Main Switch Board of the standby generator after loss of the electrical power supply. Functional tests on electronic equipments that shall be still in power during black-out conditions.
To examine the Main Engine endurance performance in continuous operation of Service Continuous Rating, and To measure performance of the Main Engine in terms of Power, RPM, Fuel Consumption, and durability.
Endurance trial shall be carried out for at least six (6) hours continuous operation at NCR (85% MCR). During the endurance trial, Fuel Consumption of Main Engine shall be measured for operational reference.
Procedure:
Conditions of Measurement:
The noise is to be measured under following conditions: a. Main propulsion machinery shall be run at Normal Continuous Rating. b. Other auxiliary machineries, navigation instruments, etc, shall be operated throughout the measurement period as required for normal seagoing condition during sea trial.
Items of Measurement:
All fire fighting equipment shall be functionally tested, including: Fire main hydrants on decks and accommodation deck Some portable fire extinguishers. Fire alarms and fire detectors in all rooms Emergency fire pumps.