Beruflich Dokumente
Kultur Dokumente
Why Mechanization
High rise in Man power cost
Advantages of Mechanization
Speedy in construction
Safety Time saving
Cost saving
Controlled Planning Less lead time for procuement.
Quality of work
Productivity
-------------------------------------------------------Sl.no Activity Cost Manual Machinery ------------------------------------------------------01 Excavation & Rs 75 Rs 25 grading works 02 Concreting Rs 180 Rs 35
-Daily production of 50 to 75 cubic meters with 40 to 50 labour for a maximum depth of 1.5 meters - Cost of excavation- 50 labour @ Rs 70 per labour= Rs 3500/Cost per cubic meters = Rs 3500/50 c.meters = Rs 70 per cubic meter Add for administrative and other charges Rs 5 per cubic meter
Total cost = Rs 75 per cubic meter
Excavation/Grading works
EXCAVATION BY MACHINERY
1 Cost of equipment ( excavator) = Rs 35,00,000 2 Considering depreciation for 5 yrs = Rs 3500000/5= 7,00,000 per yr. 3 There fore cost of equipment per month Rs 700000/ 12 Rs 58,333 4 Cost of equipment per day = Rs 2000 5 Considering interest at 15% per annum = Rs 1500/Therefore cost of equipment per day = Rs 2000 + 1500 = Rs 3500/6 Considering maintenance at 30% = Rs 1050 7 Considering cost of operator / Helper = Rs 500 8 Considering cost of fuel = Rs 7500 9 Total cost per day = Rs 12,550/10 Cost per hour = Rs 1050 CONSIDERING VOLUME OF EXCAVATION AS 500 CM/DAY
COST OF EXCAVATION PER CUBIC METER= 12550/500 Rs 25 perCM
De Watering
By Man power- un productive and time consuming either by use of Pump at Ground level or suitably designed pumps meant for de watering application . Note: At certain locations De watering can be carried out only by the use of equipment such as in deep excavations for docks, harbours, pump houses etc.
By Equipment - very efficient and productive. Mostly carried out
Concreting
A) MANUAL CONCRETING Considering a normal pour with 7 sets of 2 nos 10/7 concrete mixer, 1 no weigh batcher and 1no. Building hoist, man power required are approximately 40 labour for mixing and placing for a concrete of 240 cubic meter per day ( Similar to a Batching plant of avg. pouring capacity of 30 cu.mtrs/hr) Considering a normal mix and ground floor works only. Cost of 2 mixer (each of capacity 2 cu.mtrs/hr) = Rs 2,00,000 Cost of 1 weigh batcher = Rs 50,000 Cost of 1 builder hoist = Rs 1,00,000 Total cost of 1 set = Rs 3,50,000 Total no. of sets required are = 7 nos. Cost of Machinery = 7 x 3,50,000 = Rs 24,50,000/-
Concreting ( contd.)
Considering depreciation of 5 yrs = Rs 4,90,000 Cost per year 24,50,000/5 = Rs 4,90,000 Cost per day = Rs 1342/( out put of 2 mixer 2 x 2 x 8=32 x 7 = 224 m3 / day) There for cost per cubic meter Rs 1342/224 = 5.9 say 6 M3/day--(a) Cost of labour for concrete per cubic meter - Rs 150 ..... (b) Man power for operation ( 28 operators at Rs 125 per operator) - Rs 125 x 28 = Rs 3500 Operation cost per cubic meter = 3500/224 = 15.6 say Rs 16...(c) Maintenance cost of eqpt @ 25% of eqpt cost for the period of 5 yrs. = Rs 8 per cubic meter..(d) There for Total cost of Manual concrete /Cu.meter = Rs 180/ CM
Concreting
B) CONCRETING USING MACHINERY - Considering 30 cu.mtrs/hr batching plant - Cost of Batchng plant = Rs 30,00,000 - Cost of 2 nos Transit Mixers = Rs 40,00,000 - Total = Rs 70,00,000 Considering economic life at 10 Yrs Depreciatin over period of 10 Yrs Rs 70,00,000/10= Rs 7,00,000 Cost of equipment per day = Rs 7,00,000/ 12 x 30 = Rs 2000/Considering a concrete pump, cost of pump = Rs 30,00,000 Considering other pump accessories (6 to 7 %) Rs 2,00,000 Total = Rs 32,00,000 Considering depreciation over a period of 7 yrs Cost of equipment per day Rs 32,00,000/ 7 x 12 x 30= Rs 1270/ day.
Concreting (contd.)
There for Total cost of Machinery= Rs 2000+ 1270= 3270/ day The batching plant of 30 M3/Hr will deliver an avg. quantity of 20 CM3/Hr concrete a) Operation cost ( Man power) 2 Operators, 2 Drivers, 2 Helpers 4 x Rs 150/day + 2 x 80 / 240 cu.meters = Rs 4 / M3 ..... (a) Volume of concrete for a 12 hours shift 12 hr x 20 M3 = 240 M3 Therefore cost of concrete per cubic meter= 3270 / 240 = Rs 14/ M3...(b) Adding interest @ 15% on investment = Rs 13 / M3....(c) Total ( a + b + c ) = Rs 31 per cubic meter. Man power charges for machinery concrete considering 10 labour @ Rs 80 perlabour = Rs 800/Therefore cost of labour / cubic meter = Rs 800 / 240 M3= Rs 4/M3 Therefore total cost of Concrete by Machinery= Rs 31 + 4= Rs 35/M3
Reference to Construction Equipment in Specs of Roads and Bridge works by Indian Road Congress.
( Ministry of Road Transport and High ways)
The following conditions regarding use of equipment in works shall be satisfied. 1) Contractor must give trail run of equipment for establishing their capability, to achieve the laid down specification and tolerances to the satisfaction of the Engineer before commencement of work. 2) All equipments provided shall be of proven efficiency and shall be operated and maintained at all times in a manner acceptable t o Engineer. 3) All Plant and Equipment shall be got approved from Engineer for ensuring their fitness and efficiency before commencment of work. 4) Any material or Equipment not meeting the approval of the Engineer shall be removed from the site. 5) No equipment will be removed from site without permission of the Engineer.
D) COMPACTION EQUIPENT Compaction of soil in road making is attained by applying energy to loose soil by one or more of the following methods. Kneading action Static weight Vibration Impact A variety of equipment is available including the following: Tamping rollers, smooth wheel rollers, Vibrating rollers, Manually operated compactors, vibrating compactors for deep sand. Besides the above a number of other Plant and Machinery are used such as Concrete Mixer/ Batching plant, Bituminous plant comprisign of Boiler, sprayer spreader and pavers, Hauling vehicles like tippers or dumpers, Metal crushing plant etc.