Sie sind auf Seite 1von 24

The Flixborough, UK, Cyclohexane Disaster, 1 June 74

A Vapor Cloud Explosion (VCE) Case Study Presented to ES-317y at UWO in 1999. Dick Hawrelak

Flammability Hazards
Bursting shock wave - TNT equiv. Fireball - thermal hazards BLEVE - flying fragments Flash Fire - thermal hazards Vapor cloud explosions - TNT equiv.

Two Classes Of Hydrocarbon Vapor Cloud Explosions, VCEs


Detonation Class VCE - High level explosion. Deflagration Class VCE - Low Level explosion.

Detonation Class VCE


Flammable vapor is ignited in a congested plant area with vertical confinement. High flame acceleration leads to detonation. The sharp impulse force can be equivalent to a TNT explosion. Damage will be radial from the explosion epicenter. Overpressure range, PSO, 10 to 5 psig.

Deflagration Class VCE


Flammable vapor is ignited in uncongested area with open space. Low flame speed leads to deflagration. Impulse force longer duration and not as damaging as a detonation. Damage may be directional from the explosion epicenter. Overpressure range, PSO, 5 to 0.5 psig.

Flixborough Reactors

Flixborough Flowsheet

The Incident
A 20 inch diameter temporary by-pass pipe Jack-knifed and failed under thermal expansion stress. 40 of 120 tonnes of cyclohexane escaped into the congested reactor support structure. Within two minutes, the vapor cloud ignited and a Detonation Class VCE took place (35 tons TNT equiv).

Thermal Expansion Jack-Knife

VCE Results Flammable Hazard V1.2


10.00 Clancey Gugan P S O i n 1.00 p s i g Flix Pts. Edge Of Cloud

0.10 100

1,000 Distance From Vessel, Feet

10,000

Flammable Hazard V.12


Type of Damage Flixborough Type Damage Distillation Tower Overturned Piperack Bent - Piping Breaks Limit Of Major Plant Eqt Damage Steel Panel Building Demolished API Tank 50% Full Uplifts Non Reinf Conc Blocks Shattered Lower Limit Serious Struct Damage Man Knocked Over - No Ear Damage Corrugated Steel Panels Buckle Glass Damage Shattered Limit Minor Structural Damage Limit of Glass Failure Overpressure PSO, psig 10.01 7.25 6.09 5.00 3.48 3.00 2.51 2.20 2.00 1.00 0.50 0.41 0.15 Radial Dist., Ft. 376 468 527 603 772 854 965 1,053 1,125 1,804 2,892 3,334 6,721

Basis: Know Your Insurer's Expectations, Fire Protection Design, Hydrocarbons Processing, August 1977, p-103, by Robert W. Nelson. Updated from Lihou's Table 4 - 8 Sep 96

Overpressure, psig Equipment Control Rm, Stl Rf Control Rm, Conc Rf Cooling Tower Tank: API Cone Roof Instrument Cubicle Furnace Heater Reactor: Chemical Filter Regenerator Tank: Float'g Roof Reactor: Cracking
0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5 10 12 14 16 18 20 22

a a b

c e

d p d f

n n o k u t t i f j k j i,p u i t t d p t v t o

d a g a h i

l,m

Plot Plan Showing VCE Impact

The Consequences
28 plant people were killed. 53 people were wounded and required medical treatment. 1,800 houses were damaged in the rural area beyond the plant fence line. Property damage was $425MM in US funds.

Events Leading To The Incident.


Two months before the incident, R-5 was found to be leaking. A 6 ft. long crack had developed. A water hose stream was directed to the crack to cool and quench the small cyclohexane leak.

Events Contd
The cooling water contained nitrates which encourage stress corrosion of certain carbon steels. Thus, by trying to relieve the situation, the quenching was actually acting as a promoter of corrosion. Ultimately, the reactor had to be removed from service.

Events Contd
There was no experienced works manager, WM, available on site at the time of the removal of R-5. The previous WM, a good maintenance engineer with 25 yrs of experience, had quit because an anticipated promotion was given to an outside person.

Events Contd
As there was no experienced mechanical engineer on site, those remaining decided to fast track or scratch pad a solution for the intended by-pass. They sketched a full-scale by-pass line in chalk on the maintenance floor. No stress analyses calculations were performed on the by-pass connection.

Events Contd
The by-pass line was quickly installed and the plant put into start-up mode. Shortly after start-up, the by-pass line failed causing 40,000 lbs of cylcohexane to leak into the confined spaces of the reactor support structure. Within two minutes, the vapor cloud exploded.

Lessons Learned
The main root cause of this incident was the use of cooling water with nitrates to quench cyclohexane leaks on the reactors. Another root cause was installing a by-pass line, or any line for that mater, without stress analysis. This is a recipe for disaster. A third root cause was management must recognize when they are vulnerable to critical manpower changes.

Lessons learned Contd


More control is required to conduct good engineering practices once the plant is up and running. Poor location and poor construction of the control room. Plant was too congested at the design stage. Must minimize hazardous inventories.

Lessons Learned Contd


Process hazard review required at regular intervals. Plant must adhere to pressure vessel regulations. Require emergency planning with the community.

Deterministic Pre-planning Flammable Hazard V1.2


Defines vapour cloud characteristics between UEL and LEL. BLEVE shock wave, thermal and fragmentation analysis. Flash Fire thermal analysis. VCE analysis. Space separation (ISBL, OSBL and green belt).

Possible Exam Questions


How does a Detonation Class VCE differ from a Deflagration Class VCE? Describe the characteristics of the two type of explosions. What were the three root causes of this incident?

Das könnte Ihnen auch gefallen