Foreword
Understand the installation steps of the MBTS cabinet, boards, modules, and cables.
Describes the procedures for commissioning and verifying the MBTS after it is installed. The commissioning and verification procedures ensure that the MBTS operates as required
Page1
Learning Guide
Studied the MBTS hardware structure. Known MBTS data configuration and O&M concepts
Page2
Objectives
Understand the MBTS installation procedure. Describe the steps of MBTS commissioning. Master the commissioning of MBTS.
Page3
Contents
1. MBTS System Overview 2. MBTS Installation Procedures 3. MBTS Commissioning Procedures
Page4
MBTS Overview
The 3900 series multi-mode base stations feature a modular design. The BBU3900 and the RF module (MRFU/RRU3908) are connected through
The basic modules of the 3900 series multi-mode base stations are the baseband unit BBU3900, the outdoor remote radio unit RRU3908, and
Page5
The BBU3900 has a case structure. It can be installed in a 19-inch-wide and 2 U-high indoor space or outdoor protective cabinet, for example, indoor wall, staircase, storerooms, or outdoor cabinets in the existing network
Page6
Page7
Page8
UMTS mode
GSM+UMTS mode
Page9
See Remarks
Page10
The RRU3908 is an outdoor RF remote radio unit, which performs modulation, demodulation, data processing, and combining and dividing for baseband signals and RF signals.
Page11
MRFU appearance
Page12
Contents
1. MBTS System Overview 2. MBTS Installation Procedures 3. MBTS Commissioning Procedures
Page13
Page14
2) Check and adjust the base level & Test the insulation between the base and the expansion bolt
Page15
2) Marking the positions of the mounting holes & Securing the supports for installing the ESD floor
Page16
Installing a Single Cabinet Separately Installing Two Cabinets Side-by-Side Stacking Two Cabinets
Page17
Page18
2) Install the two connecting pieces on the positions & Tighten the screws
Page19
Page20
Page21
Installing the Input Power Cable for the Cabinet Installing the E1/T1/FE/GE Cables Installing the CPRI Cables Installing the RF Jumper
Page22
Page23
Page24
Page25
Figure 1 If... The cotransmission mode is used The separate transmission mode is used Then...
Figure 2
Link the DB26 male connector of the E1/T1 cable to the port labeled E1/T1 on the GTMU, and then tighten the screws, as shown in Figure 1. Link the DB26 male connectors of two E1/T1 cables to the ports labeled E1/T1 on the GTMU and on the WMPT respectively, as shown in Figure 2.
Page26
If...
Then...
The separate Connect one FE/GE cable to the port labeled FE0 on transmission mode the WMPT and another FE/GE cable to the port is used labeled FE0 on the GTMU.
Page27
Then... Connect the FE/GE cable to the port labeled FE0 on the WMPT. Connect the two ends of the interconnection cable between the FE optical ports to the ports labeled FE1 on the GTMU and on the WMPT respectively.
Page28
If...
Then...
Connect the FE/GE optical cable to the port labeled FE1 on the WMPT. Connect the two ends of the interconnection cable between the FE electrical ports to the ports labeled FE0 on the GTMU and on the WMPT respectively NOTE: The FE/GE optical cable should be wrapped a winding pipe,
Page29
Page31
Installing RF Cables
Single Cabinet
Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.
Stacked cabinet
Page32
Power-On Check
Page33
Contents
1. MBTS System Overview 2. MBTS Installation Procedures 3. MBTS Commissioning Procedures
Page34
Contents
3. MBTS Commissioning Procedures
3.1 MBTS Commissioning Scenarios 3.2 MBTS Commissioning Modes
Page35
Page36
Page37
Commissioning Resources
Before commissioning, you need to ensure that the required tools are available, obtain the information about the base station to be commissioned, and download the correct software for boards used in the base station
Tools: PC, Multimeter, Power Meter, Site Master, GSM MSs for testing, Ethernet cable, Serial port cable, Flat-head screwdriver, Light emitting diode (LED)
Page38
Hardware Requirements
The base station hardware is installed and the cables are connected.
The base station has passed the hardware installation check before it is powered on.
The base station is powered on, and the boards operate normally as indicated by the LEDs on the boards.
The base station controller is installed. The system commissioning is complete, and the system is operating properly.
Software Requirements
The data of the base station is configured on the base station controller. An adaptation layer version matching the base station to be commissioned is installed on the M2000 server
Page39
Page40
Remote Commissioning
Star BSC LMT
Check transmission and networking Check BTS version and configuration
Commission the BTS antenna system Check BTS alarm Commission BTS service
Checking the GBTS Environment Alarms End
Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page41
Page42
Check the status of the CPRI0 LED on the GTMU panel of the BBU and the status of the CPRI0 and CPRI1 LEDs in the RFU panel
If all the LEDs are in the on in green status, the communication between the CPRI0 port on the BBU and the RFU is normal
Page43
Page44
Page45
CPRI connections:
The ports SFP0 to SFP5 in the RXU Topology Structure area on the LMT correspond to CPRI0 to CPRI5 on the panel of the BBU.
Slots of RXUs:
On the LMT, RFUs are configured in subrack 4. The slot numbers of RFUs start from slot 0, on the basis of the configuration sequence of RF units. During the RFU installation, the slots of RFUs are determined based on the actual requirements. The subracks where the RRUs are configured are virtual subracks. The subrack number ranges from 60 to 254. During the RRU installation, the slots of RRUs are determined based on the actual requirements.
Page46
Page47
Page48
Page49
Page50
Page51
Page52
Page53
Power on one test MS, and check that the Ms automatically searches for the GSM network
Lock the test MS on a specific frequency. Change the status of one or two TCHs on the frequency from Locked to Unlocked. Then, conduct the call tests on this TCH.
Ensure that all calls are successful, the conversion is normal, and voice quality
is clear.
Test short message service (SMS) as follows: Use two testing MSs to send SMS messages to each other, and ensure that all the SMS messages are successfully sent and received.
Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page54
Enable the MS to support the GPRS or EGPRS services. Then, test PS services through multiservice testing. PS service test involves sending multimedia message, browsing WebPages, and downloading files.
Check whether the MS can successfully send multimedia messages, browse WebPages, and download files.
Page55
Page56
Page57
SMT
Page58
Page59
Page60
Login
Page61
In the left pane of the Site Maintenance Terminal System window, select Board. In the right pane of the window, double-click Board Management
Page62
Right-click MRFU0, and then click Board Information. The query is successful. The Board Information dialog box is displayed
Page63
Right-click GTMU, and choose Board Information from the shortcut menu. The Board Information dialog box is
displayed
Page64
Page65
Page66
Page67
Activating Software
Input the version number Input the board number to be activated Select the program type
Page68
Obtaining the Site Management Rights Configuring the Boards of the BTS on the SMT
Page69
Page70
Page71
Page72
Page73
Page74
Page75
Page76
double-click Site
Configuration in the Function
displayed
Page77
Add a cell
Subobject. In the
Object Attributes area, specify Object No. and Object Name. In the Object Operation area, Cell0 is added
Page78
Click Cell0, and select the TRX to be configured in the Boardtype drop-down list box. Set the board type to
MRFU
Page79
Attributes area,
specify Object No., Object Name, Board No., and Pass No.. Carrier0 is added in the Object Operation area. The carrier is bound to pass 0 of the TRX whose board number is 0
Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page80
Page81
Click Site0. The Set button is available. Click Set, Configuring cell succeeded is available
Page82
Close the dialog box. The configured cell is displayed in the navigation pane
Page83
Choose Site0 > Site Opstart > OK. Site Opstart successfully. is displayed, and click Close
Page84
Choose Cell0 > Cell Opstart > OK. Cell Opstart successfully. is displayed, and click Close
Page85
Choose BT0 > BT Opstart > OK. BT Opstart successfully. is displayed, and click Close
Page86
Choose RC0 > RC Attributes Management. Specify frequency in ARFCN, and click Set. Getting RC attributes succeeded is
displayed. Click
Close
Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page87
Choose RC0 > RC Opstart > OK. RC Opstart successfully is displayed. Click Close
Page88
SFP Port Inconsistency Alarm is cleared. The status of the GTMU is Active normal
Page89
The running status and alarm information of the GBTS needs to be check locally. If alarms are found, clear them in time.
If the LEDs on the boards or modules are not in the normal state, check the alarm information on the SMT and rectify the faults according to the suggestions displayed.
Page90
ALM
ACT LIU0 to LIU3
Red
Green Green
OFF
ON LEDs LIU0 to LIU3 represent the four E1 links. If the links are connected normally, LIU LEDs are OFF.
CPRI0 to CPRI5
Green
When CPRI0 to CPRI5 ports are not in use, the LEDs are OFF. When the BBU is normally connected to the RFU, the corresponding LED is ON.
Blinking (ON for 1s and OFF for 1s) ON
UBFA UPEU
STATE RUN
Green Green
Page91
Page92
Page93
Page94
2. Arranging for the Files in the USB Storage Device Required for the
Base Station Commissioning
Page95
Related Information
Collect the information related to the base station
Page96
Create a .txt, and name it as Precfg.ini. Then, add the following contents to this file:
[PRECONFIG] ALL=GTMU|MRFU
2. Save the pre-configuration file in ASCII mode. 3. Copy the file Precfg.ini to BTS3900 GSM directory in the
Page97
4. Save the GBTS software package and configuration script under the specified path in the USB device
Page98
configuration file. When the LED on the USB disk blinks, the
GBTS starts to load the target software and parse the
Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.
configuration file.
Page99
Page100
Summary
Introduce hardware overview of MBTS Describe the installation procedures of MBTS hardware Describe the commissioning procedures of MBTS under different scenarios.