CSC PROJECT
Material Issuance
Current Status// Issues 369 Agreement verified. But 250 cases not yet signed from RCOM side. Material Issued to 231 VLEs, but 36 Sets are lying with DMs, Would be distributed as and when full payment comes.
Decision to be taken by Circle Head and NHQ Pooja Gulati/ Commercial for material Sajjan Agrawal realisation.
CSC PROJECT
As per new process formulated, under Phase II scheme, material will be issued to the VLE's only when they pay in Full i.e Payment Reconciliation Rs.84,000/-. There are 75 cases where materials already given but we have not recd full pymt. Payment for Office Rent is not happening Vendor Payment from Shared Services. Stock unavailability at WH Level and Stock replenishment coordination request for disctribution comes at last minute.
Sajjan Agrawal
Follow up being done at Sajjan Agrawal NHQ and Circle level. As per business requirement Sajjan Agrawal
confidential
WIMA X BUSINESS
Agreement verification
Agreement for 6 CP, already signed and code Sales to be provided the created. Agreement and Code creation agreement copy pending for 1 CP ( Maharaja). Nil Pendency Commission processed for 15th Sept- 15 Oct'08 data, as recd from NHQ.
Fresh code created within Pooja Gulati 48 Hrs. SLA of 72 Hrs from Recpt of Sajjan Agrawal Data
WIRELINE PCO
Commission Payouts
Once validation/Invoices Till Sep'08, commission data recd and sent to recd from Business Team, Santosh Misra for validation. Commission Sajjan Agrawal Commission will be details for Oct is awaited from NHQ. processed in 24 Hrs. 1 Case for damaged RCV recd and details pending with Sales Team. Nil Pendency To be followed up NHQ Sajjan Agrawal once recd. SLA of 24 Hrs from Recpt of Pooja Gulati Data Sajjan Agrawal
confidential
Support from respective authorities required Daily for circulation of complete tracker.
Vendor Management
Current Status// Issues Based on New TRAI guideline DD needs to be handed over to Customer is 60 days from order. As on date NIL pendency. Nil Pendency, except Zodiac's last courier bill due to clarity on the deduction of undelivered bill. Proper control should be in place in order to reduce Expenses without effecting business.
Way forward To process in 24 hrs of receipt. All invoices processed for payment in 7 days SLA.
Charge Deviation
CDs are being approved in Selectica SCR being approved considering the CAPEX VS Revenue justification. SCR/ Very Short Cycle SCR Approval
SCR
All measures are being reviewed for proper controling. NIL Pendency. Application for new User ID To approve the same in 24 asked from NHQ Selectica Team. Hrs. Details needs to be asked Monitoring of Actual Vs. Budgeted CAPEX and from NHQ for proper Revenue realisation not in place. control of Cost and revenue. SCRs are being approved/rejected in 24 Hrs of 72 Hrs SLA receipt of data from NHQ.
Sudipta Bose
Sudipta Bose
LCO
LCO installation commission till OCT08 Installation and Collection commission processed. Nothing is pending. Commission being processing Collection commission for Apr- July processed. processed in 48 Hrs.
Sudipta Bose
NIL Pendency
THANKS
POOJA GULATI SAJJAN AGRAWAL SUDIPTA BOSE