Beruflich Dokumente
Kultur Dokumente
German engineers helped Japan build aircrafts in 30s. Takt is a German word for a musical meter. In TPS; Customer demand dictated the pace of operations on the shop floor. Takt Time: The concept of linking (external) customer demand to (internal) production resources. It is expressed in terms of the time available to make one unit to keep pace with customer demand.
Ardavan Asef-Vaziri
6/4/2009
Load Balancing?
An operator can not be overloaded. Apply time studies to lower the time or breakdown the task. Loading each operator close to 100 percent may lead to infinite queue if the workload is highly variable (negative). keep operators loaded close to 100% to motivate them to find creative ways to reduce their cycle time to takt time (positive). If the operators are underutilized, work expands to fill the time available (negative). takt time goes down when demand increases. Then some operator may become overloaded. Subdivide tasks more finely, to load each operator close takt time. However, that would uniformly underutilize each operator. A better alternative is to have the first two operators loaded with tasks that add up to the takt time, leaving the third underloaded.
Ardavan Asef-Vaziri 6/4/2009 4
The third operator could help if the others fall behind. S/he could be located at the end of the cell to perform material handling.
Ardavan Asef-Vaziri
6/4/2009
If each operator is paced to takt time, over production will be automatically limited. Limiting overproduction prevents frequent stops and starts that inhibit a smooth flow. It's best to buffer variation with capacity, not inventory. It is incorrect stating that a machine has a takt time of five minutes. Takt time is a measure of external demand; it has nothing to do with machine capacity. Takt is time per piece, not pieces per time. Enterprise should match its (internal) resources to meet the (external) customer demand. takt time applies better to a flow shop, may not be very relevant in job shop, but still useful to determine the number of operators.
Ardavan Asef-Vaziri 6/4/2009 6
Too Frequent Chaos Not flexible to change Missed opportunities, Inventory buildup Distinguish between noise and real trends. Takt time could be reevaluated if the demand exceeds the set production rate for 5 consecutive days (Run Test). At Dell Assembly takt time is 15 secs per computer. It is accomplished through (capacity) running multiple assembly lines
Ardavan Asef-Vaziri
6/4/2009
10
15
20
25
30
Day
RAPS
RAINS
RERUNS
4
10%
12
30%
6
15%
18
45%
Distribution Underwriting
Rating Policy writing Total Labor
Lean Thinking: 3- Takt Time
58
43 72 67 240
50
40 65 0 155
44
23 68 55 190
28
19 75 50 172
6/4/2009 9
Ardavan Asef-Vaziri
Average labor content = 0.10 (240) + 0.30 (155) + 0.15 (190) + 0.45(172) = 176.4 min
TT 10 10 10 10 10
M LR 4 3 7 4 18
6/4/2009 11
Ardavan Asef-Vaziri
Patients / Day
PNE 24
0.24
PHA 25
0.25
SIN 36
0.36
Fraction of total
Ardavan Asef-Vaziri
6/4/2009
12
Tasks 1, 3, and 4 are typically handled by RNs. Task 2 is handled by a physician. For simplicity, we assume that the arrival rates of patients are constant through both shifts.
Lean Thinking: 3-Takt Time Ardavan Asef-Vaziri 6/4/2009 13
Ardavan Asef-Vaziri
6/4/2009
14