THREE SCHEDULES
SCHEDULE I : DIMENSIONS ESSENTIAL FOR SAFE WORKING .ANY DEVIATIONS NEED PRIOR SANCTION OF CRS SCHEDULE II: RECOMMENDED DIMENSIONS FOR GOOD PRACTICES ANY DEVIATIONS DO NOT NEED SANCTION OF CRS SCHEDULE III:IT GIVES DIMENSIONS THAT ARE INFRINGEMENT TO STANDARD DIMENSIONS
S.No.
Description
1.
Minimum distance center to 4265 center of track 14 Recommended distance center to center of track 4725 156
a.
BG mm (ft.Inch)
MG mm (ft.inch)
4265 14 4420 146
Minimum distance c/c 4265 of track 14 Recommended 4725 distance c/c of track 156
1a
S.No. 2.
3. 4.
Minimum clearance of check rails for a curve Minimum clearance of check rail at level crossing
5.
6.
57
38
57
35
Check rail clearance Min 51mm. max. 57mm Minimum depth of check block 38mm(35mm) for MG
S.No. Description
BG mm (ft.Inch)
MG mm (ft.inch) 44
18.
18a.
Points & Crossings Max. clearance of check rail 48 opposite nose of crossing or of wing rail at nose of Xing Min. clearance of check rail 44 opposite nose of crossing and at heel of switch rail
41
S.No. Description
19. 20. Diamond crossing not be flatter than
BG mm MG mm (ft.Inch) (ft.inch)
1 in 8-1/2 89
Maximum clearance between 115 toe of open switch and stock rail
100
S.No. Description
21.
BG mm (ft.Inch)
MG mm (ft.inch)
1 in 400
Maximum gradient in 1 in 400 station yards Recommended gradient in station yards. 1 in 1200
21a
1 in 1200
OVER-DIMENSIONAL CONSIGNMENTS
Schedule of Dimensions provides for certain standard moving dimensions which govern the construction of rolling stock
Dimensions of which when loaded on wagons, exceed the standard moving dimensions Movement under certain restrictions : Speed, during day or night, depending on minimum clearance available to fixed structures on the route.
ODCs Classification
Class A :
6 and above
Movement
Civil
Military
Class B :
Movement: Civil:
40 kmph (BG) Day only. Night movement also permitted with Train escort
Military:
C Class
Class C :
clearances: < 3 With restriction of stop dead and proceed dead slow at structures having most restricted clearance. Train is to be piloted by official of the Mech. Department.
CRS SANCTION
Approval of CRS is necessary for execution of any work on open Line which will affect running of trains
Realigning curves. Lubrication of joints. Painting of Girders Renewal of points & crossing involving no modification in lay out. Rail & sleeper renewal
Additions or Alterations to running lines. Electric traction installations Provision of New stations Provision of foot over bridge across the tracks. New Bridges or extensions of existing ones New level crossing in running lines Carriage of O.D.C. having gross clearance less than 6. Any work involving infringement to S.O.D.
New lines
No new Railway Line can be opened for public carriage of passengers without obtaining CRS sanction. No sanction is necessary for opening of new lines to goods traffic.
All the works required for running of train has been completed and commissioned Staff required for operating new line posted Track thoroughly packed and boxed throughout Permanent maintenance gangs are distributed along definite sections.
Application
14 days before expected commencement of work For new lines, 1 month before opening of the section.
Inspection by CRS
A week before opening date. Will recommend one of the following Railways be opened unconditionally Railways be opened subject to certain stated restrictions Opening of the railways to be postponed until certain stated conditions have been fulfilled.