Sie sind auf Seite 1von 33

Project Management:

A Managerial Approach 4/e

By Jack R. Meredith and Samuel J. Mantel, Jr.

Published by John Wiley & Sons, Inc.

Presentation prepared by RTBM WebGroup


Project Management
A Managerial Approach

Chapter 13

Project Termination
The Varieties of Project
Termination

❚ A project can be said to be terminated


when work on the substance of the
project has ceased or slowed to the
point that further progress is no longer
possible
❚ There are four fundamentally different
ways to close out a project: extinction,
addition, integration, and starvation

Chapter 13-1
Termination by Extinction

❚ The project may end because it has been


successful and achieved its goals
❚ The project may also be stopped because it
is unsuccessful or has been superseded
❚ A special case of termination by extinction is
“termination by murder” which can range
from political assassination to accidental
projecticide

Chapter 13-2
Termination by Extinction

❚ Two important characteristics of


termination by murder are the
suddenness of project demise and the
lack of obvious signals that death is
imminent
❚ When a decision is made to terminate a
project by extinction, the most
noticeable event is that all activity on
the substance of the project ceases
Chapter 13-3
Termination by Addition
❚ If a project is a major success, it may be
terminated by institutionalizing it as a formal
part of the parent organization
❚ Project personnel, property, and equipment
are often simply transferred from the dying
project to the newly born division
❚ The transition from project to division
demands a superior level of political sensitivity
for successful accomplishment

Chapter 13-4
Termination by Integration
❚ This method of terminating projects is
the most common way of dealing with
successful projects, and the most
complex
❚ The property, equipment, material,
personnel, and functions of the project
are distributed among the existing
elements of the parent organization

Chapter 13-5
Termination by Integration
❚ In general, the problems of integration are
inversely related to the level of experience
that the parent or client has had with:
❙ the technology being integrated
❙ the successful integration of other projects,
regardless of technology

Chapter 13-6
Termination by Integration
❚ A few of the more important aspects of the transition
from project to integrated operation that must be
considered:
❙ Personnel - where will the team go?
❙ Manufacturing - is the training complete?
❙ Accounting/Finance - have the project’s account been
closed and audited?
❙ Engineering - are all drawings complete and on file?
❙ Information Systems/Software - has the new system
been thoroughly tested?
❙ Marketing - is the sales department aware of the change?

Chapter 13-7
Termination by Starvation
❚ This type of project termination is a “slow
starvation by budget decrement”
❚ There are many reasons why senior
management does not wish to terminate an
unsuccessful or obsolete project:
❙ Politically dangerous to admit that one has
championed a failure
❙ Terminating a project that has not accomplished
its goals is an admission of failure

Chapter 13-8
When to Terminate a Project
❚ Some questions to ask when considering
termination:
❙ Has the project been obviated by technical
advances?
❙ Is the output of the project still cost-effective?
❙ Is it time to integrate or add the project as a
part of regular operations?
❙ Are there better alternative uses for the
funds, time and personnel devoted to the
project?
❙ Has a change in the environment altered the
Chapter 13-9
need for the project’s output?
When to Terminate a Project
❚ Fundamental reasons why some projects fail
to produce satisfactory answers to
termination questions:
❙ A project organization is not required
❙ Insufficient support from senior management
❙ Naming the wrong person as project manager
❙ Poor planning
❚ These and a few other reasons, are the base
cause of most project failures
❚ The specific causes derive from these
fundamental issues

Chapter 13-10
The Termination Process
❚ The termination process has two
distinct parts
❚ First is the decision whether or not
to terminate
❚ Second, if the decision is to
terminate the project, the decision
must be carried out

Chapter 13-11
The Decision Process
❚ Decision-aiding models for the termination
decision fall into two generic categories:
❙ 1. Models that base the decision on the
degree to which the project qualifies
against a set of factors generally held to be
associated with successful projects
❙ 2. Models that base the decision on the
degree to which the project meets the goals and
objectives set for it
❚ Just as the decision criteria, constraints, weights,
and environmental data are unique to each
organization, so are the specifics of using any
decision model Chapter 13-12
The Implementation Process
❚ The actual termination can be planned
and orderly, or a simple hatchet job
❚ Special termination managers are
sometimes useful in completing the long
and involved process of shutting down a
project
❚ The primary duties of the manager in
charge of termination can be
encompassed in nine general tasks
Chapter 13-13
The Implementation Process
❚ Duties of the termination manager:
❙ Ensure completion of the work, including tasks
performed by subcontractors
❙ Notify the client of project completion and
ensure that delivery is accomplished
❙ Ensure that documentation is complete
including a terminal evaluation of the project
deliverables and preparation of the project’s
Final Report
❙ Clear for final billings and oversee preparation
of the final invoices sent to the client
Chapter 13-14
The Implementation Process
❚ Duties of the termination manager (cont.):
❙ Redistribute personnel, materials equipment, and any
other resources to the appropriate places
❙ Clear project with legal counsel or consultant
❙ Determine what records to keep
❙ Ascertain any product support requirements, decide how
each support will be delivered, and assign responsibility
❙ Oversee the closing of the project’s books

Chapter 13-15
The Implementation Process
❚ Most project managers delay the personnel
reassignment/release issue as long as
possible for three main reasons:
❙ 1. A strong reluctance to face the interpersonal
conflicts that might arise when new
assignments and layoffs are announced
❙ 2. Worry that people will lose interest and stop
work on the project as soon as it becomes
known that termination is being considered
❙ 3. Concern that team members will try to avoid
death by stretching out the work as far as
possible Chapter 13-16
The Final Report -
A Project History
❚ The final report is the history of the
project
❚ It is a chronicle of the life and times of the
project, a compendium of what went right
and what went wrong
❚ The required information is contained in
the master plan, all project audits, and
evaluations
❚ The precise organization of the report is
not of great concern; the contentChapter
is 13-17
The Final Report

❚ Several Subjects should be addressed in


the final report:
❙ Project performance
❙ Administrative performance
❙ Organizational structure
❙ Project and administrative teams
❙ Techniques of project management

Chapter 13-18
The Final Report
❚ For each element covered in the final
report, recommendations for changing
current practice should be made and
defended
❚ Equally important are comments and
recommendations about those aspects of
the project that worked unusually well
❚ The fundamental purpose of the final
report is to improve future projects
Chapter 13-19
Summary
❚ A project can be terminated in one of four
ways: by extinction, addition, integration, or
starvation
❚ Making a decision to terminate a project
before its completion is difficult, but a
number of factors can be of help in reaching
a decision
❚ Studies have shown that the factors
associated with project success are different
for different industries and the various types
of projects Chapter 13-20
Summary

❚ Most projects fail for one or more of


the following reasons:
❙ Inappropriate use of the project form of
organization
❙ Insufficient top management support
❙ Naming the wrong project manager
❙ Poor planning

Chapter 13-21
Summary
❚ Success-related factors, or any factors
management wishes, can be used in
termination decision models
❚ Special termination managers are
often used, and needed, for closing
out projects
❚ This task, consisting of eight major
duties, is a project in itself
Chapter 13-22
Summary
❚ The project Final Report incorporates the
process knowledge gained from the project
❚ In addition to preservation of project
records, the Final Report embodies the
experience from which we learn
❚ The Final Report should include: project
performance comments, administrative
performance comments, organizational
structure comments, personnel
suggestions
Chapter 13-23
Project Termination

Questions?

Chapter 13-24
Project Termination

Picture Files
Project Termination

Figure 13-1
Project Termination

Figure 13-2
Project Termination

Table Files
Project Termination
Project Termination
Copyright © 2000 John Wiley & Sons, Inc. All rights
reserved. Reproduction or translation of this work beyond
that permitted in Section 117 of the 1976 United States
Copyright Act without the express written permission of
the copyright owner is unlawful. Request for further
information should be addressed to the Permissions
Department, John Wiley & Sons, Inc. The purchaser may
make back-up copies for his/her own use only and not for
distribution or resale. The Publisher assumes no
responsibility for errors, omissions, or damages, caused by
the use of these programs or from the use of the
information contained herein.

Das könnte Ihnen auch gefallen