Sie sind auf Seite 1von 57

OptiX RTN 600 Equipment

Commissioning
www.huawei.com

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Learning Guide

Before studying this course, you are supposed to


complete the study on

Basics of digital microwave communications or related


knowledge

OptiX RTN 600 Product Introduction

OptiX RTN 600 Networking and Protection Mechanism

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 2

References

Digital Microwave Communications Basics

OptiX RTN 600 Radio Transmission System Configuration


Guide

OptiX RTN 600 Radio Transmission System Commissioning


Guide

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 3

Objectives

Upon completion of this course, you will be able


to:

Finish proper preparations before the commissioning

Performing NE commissioning of the OptiX RTN 600

Performing hop commissioning of the OptiX RTN 600

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 4

Contents
1.

Preparations for the OptiX RTN 600


Commissioning

2.

NE Commissioning of the OptiX RTN 600

3.

Hop Commissioning of the OptiX RTN 600

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 5

Contents
1.

Preparations for the OptiX RTN 600


Commissioning

1.1 Determining Commissioning Items

1.2 Preparing Related Documents

1.3 Preparing Related Tools

1.4 Checking Commissioning Conditions

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 6

Determining Commissioning Items


1. NE Commissioning Items
Commissioning Item

Optional/Requi

Remarks

red
Powering on the
equipment
Testing indicators
Accessing the Web
LCT
Configuring the data
Performing the
service loopback test

If the fan is available in the


Required

equipment, check whether the fan


is working or not after power on.

Required
Required
Required

Check whether all indicators work


normally or not.
If the instruments are available on

Optional

site, it is recommended that you


test this item.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 7

Determining Commissioning Items


(cont.)
1. NE Commissioning Items (cont.)
Commissioning Item

Optional/Requi

Remarks

red
Testing E1 cables
connections

Optional

Checking the receive


and transmit power
of the optical
interface

Optional

Testing the RF
transmit power

Required

Testing the
active/standby crossconnect board
switching

Required

It applies to the station where the


E1 service is accessed.
It applies to the station where the
SDH optical interface service is
accessed.
Use the Web LCT to query the RF
transmit power.
It only applies to the equipment
configured with the active and
standby cross-connect boards.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 8

Determining Commissioning Items


(cont.)
2. Hop Commissioning Items
Commissioning

Optional/

Item

Required

Aligning the
antenna
Testing the ECC
Testing the
orderwire phone
Testing all
services

Remarks
-

Required

Required

It is applicable when there is the


Optional

order wire phone available


between stations.
Test all service types turned up

Required

at the station like the E1, STM-1,


and WS.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 9

Determining Commissioning Items


(cont.)
2. Hop Commissioning Items (cont.)
Commissioning

Optional/Requir

Item

ed

Testing the clock


tracing
Testing the IF
switching modes
Testing the SNCP
switching
Testing the longterm BER

Required

Remarks
Check and ensure that the clock
source can be traced normally.
It is applicable when the 1+1

Required

HSB/FD/SD protection is
configured.

Required

It is applicable when the SNCP is


configured.
Generally perform the test for 24

Required

hours according to the actual


conditions

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 10

Preparing Related Documents

The documents that are required include the engineering


design documents and commissioning guide documents.

Engineering design documents like

OptiX RTN 600 Radio Transmission System Network Planning


Document

OptiX RTN 600 Radio Transmission System Engineering Design


Document

Commissioning guide documents like:

OptiX RTN 600 Radio Transmission System Commissioning Guide

OptiX RTN 600 Radio Transmission System Quick Installation and


Commissioning Guide

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 11

Preparing Tools

The tools that are required include the common tools, special tools and

instruments. The recommended list is as follows:

Type
Common
tool
Special
tool
Instrume
nt

Description
Adjustable wrench, percussion drill, sharp-nose
pliers, and electric knife
Anti-static glove, ESD-preventive wrist strap,
telescope, and intercom
Multi-meter, BER tester, and laptop computer
(installed with the Web LCT)

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 12

Checking Commissioning Conditions

The NE commissioning conditions to be checked include the


status of the equipment as well as that of the laptop
computer used in the commissioning. The NE commissioning
conditions are listed as follows:

The hardware installation of the equipment must be complete,


and it should pass the installation check.

The power supply of the equipment must be available.

The service signal cables connected to other equipment must be


routed well.

The laptop computer must be installed with the Web LCT, and
applications should work normally.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 13

Checking Commissioning Conditions


(cont.)

The hop commissioning items to be checked include the NE


commissioning status as well as the weather conditions.
The hop commissioning conditions are listed as follows:

The NE commissioning of the radio equipment at both ends of


the same radio link must be complete.

The weather should be suitable, and there should no rain or fog


between stations.

The on-site conditions and the personnel in charge of antenna


commissioning must meet the requirement on the operation at
a high altitude.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 14

Summary

This chapter describes the following contents:

NE commissioning items and hop commissioning items

Documents and tools prepared before the


commissioning

Commissioning conditions

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 15

Contents
1.

Preparations for the OptiX RTN 600 Commissioning

2.

NE Commissioning of the OptiX RTN 600

3.

Hop Commissioning of the OptiX RTN 600

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 16

Contents
2.

NE Commissioning of the OptiX RTN 600

2.1 Powering On the Equipment

2.2 Testing Indicators

2.3 Accessing the Web LCT

2.4 Configuring the Data

2.5 Performing the Service Loopback test

2.6 Testing the Connections of the E1 Cables

2.7 Testing the Transmit and Receive Optical Power

2.8 Testing the RF Transmit Power

2.9 Testing the Active/Standby Cross-Connect Board Switching

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 17

Powering On the Equipment

Prerequisites

The input power must be available.


The power switch of the input power (such as the power box
of the cabinet) must be turned off.

Tools and Instruments

The hardware installation of the equipment must be


complete, and it should pass the installation check.

Multi-meter

Procedure

Set the SYS-PWR switch on the PXC board to O.

Set the ODU-PWR switch on the IF board to O.

Turn on the input power switch of the cabinet.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 18

Powering On the Equipment (cont.)

testing the voltage and polarization of the input power at the


access point (such as the output terminal of the power box on the
cabinet) by multi-meter. The voltage should range from -38.4 V to
-72 V.
Set the SYS_PWR switch on the PXC board to I.
If the fan is available, first check it is working normally after power
on.
Wait for about 20 seconds, and then observe indicators of each
board installed in the IDU.

The PROG indicator on the SCC board should be first on. After it
blinks and is lit green for some time, it should be off.
For details on the board indicators, refer to the OptiX RTN 600
Radio Transmission System Product Description.

Set the ODU-PWR switch on the IF board to I.

Note: The SYS-PWR and ODU-PWR switches on PXC and IF boards have
the locking device. They need to be slightly pull out before switch
them.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 19

Testing Indicators

Prerequisites

Tools and Instruments

The equipment must be powered on for


more than five minutes.
None.

LAMP
TEST
button

Procedure

Press the LAMP TEST button on the


SCC board, and indicators of all boards
should be on.
Release the LAMP TEST button, and
indicators of all boards should recover
to the status before the LAMP TEST
button is pressed.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 20

Accessing the Web LCT

Prerequisites

The equipment must be powered on.

Tools and Instruments

NM interface

Laptop computer installed with the Web LCT

Network cable

Procedure

Start the laptop computer, and log in to the


operating system. Run the Web LCT
program.
Connect the network port on the laptop
computer to the ETH interface on the SCC
board through the network cable. The green
indicators of the ETH interface and network
port should be on.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 21

Accessing the Web LCT (Cont.)

Set the IP address information of the computer, and log in to the


NE. The IP address should comply with the following conditions:

IP address: The IP address should be in the 129.9.0.0 network section


and should be different from the default IP address of the NE
(129.9.191.240).

Subnet mask: 255.255.0.0.

Default gateway: Null.

Enter in the Address bar of the IE the address of the server to be


logged in. If the server is installed in the local computer, enter
http://127.0.0.1:8080/nglct/, and click the Turn to button.
In the login interface of the Web LCT, enter the user name and
corresponding password. Click Login. The default user name is
admin, and the default password is T2000. If the user name and
password are correct, the NE List page is displayed in the IE.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 22

Configuring the Data

Prerequisites

Tools and Instruments

The documents that are required by data configuration must be


available.

Web LCT

Procedure

Before configuring the NE data, create the NE, log in and modify the
ID settings of the NE according to the requirements in the Network
Planning Document.
The OptiX RTN 600 can be configured in two modes, General Mode
and Wizard Mode. Users can choose the proper configuration mode
depending on the specific configuration scenarios. For details, refer
to the OptiX RTN 600 Radio Transmission System Configuration
Guide.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 23

Testing Transmit and Receive Optical


Power

Prerequisites

The service data must be configured.


The 15-minute performance monitoring of the NE must be
started.
The fiber connections must be normal.

Tools and Instruments

Web LCT

Fixed optical attenuator or variable optical attenuator

Procedure

Disable the automatic laser shutdown (ALS) function of the


laser, and ensure that transmission of the laser is enabled.
Query the 15-minute performance by using the Web LCT to
obtain the values of the transmit and receive optical power.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 24

Testing the Transmit and Receive


Optical Power (cont.)

Based on the queried values along with the specifications of


optical modules, judge whether they are within the normal
value range. The receive optical power should be 3 dB more
than the minimum sensitivity and 5 dB less than the minimum
overload provided in the specifications.
If the values are beyond the normal range, adjust the optical
power by increasing or decreasing the number of attenuators
to ensure that the receive and transmit optical power is within
the normal value range.
Perform the loopback test for the services upon the completion
of the optical power test. Ensure that no bit errors occur in five
minutes.

Note: The attenuator should be connected to the receive


end other than the transmit end.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 25

Performing the Service Loopback


Test

Prerequisites

The Web LCT must be logged in to successfully and its


connection to the NE must be normal.

The board must work normally.

Tools and Instruments

Web LCT

BER tester or SDH analyzer

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 26

Performing the Service Loopback Test


(cont.)

Procedure

Connect the board to be tested to the test instrument.


Issue the loopback command and observe the instrument for
five minutes. The services should be normal.
Repeat the above two steps to test each board.
The service loopback for the IF board can only be
implemented by testing the services of other service boards.
Adopt different loopback mode depending on the actually
used instrument.
If the SDH analyzer is used to test the optical interface board,
first use the optical power meter to test the optical power
before the test and use the attenuator to ensure that the
optical power is within the normal range. This can protect the
instrument and the board.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 27

Testing E1 Cable Connections

Prerequisites

The E1 port must be transferred through the DDF.

The service data must be configured.

Tools and Instruments

Web LCT

BER tester

Procedure

Connect the BER tester to the first E1 port of the OptiX RTN 600 at
the DDF.
Set the corresponding E1 port to outloop by using the Web LCT.
Observe the BER tester. The AIS alarm displayed on the BER tester
should be cleared.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 28

Testing E1 Cable Connections (cont.)

Release the outloop of the E1 port by using


the Web LCT.
Observe the BER tester. It should report the
AIS alarm.
Repeat the above five steps to test other E1
ports.

Tip
Connect all E1 ports in a serial manner and
set all of them to outloop by using the Web
LCT. In this way, you can check whether all E1
ports are normal at the same time. If any fault
occurs, you also need to locate it segmentally.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 29

Testing the RF Transmit Power

Prerequisites

Web LCT

Procedure

The ATPC function must be disabled.

Tools and Instruments

The service data must be configured and the performance


monitoring of the NE must be started.

In the NE Explorer, select the ODU that requires querying the RF


transmit power and query RF Transmit Power in the performance
events.
Browse the performance events in the window. The difference
between the queried value of the RF transmit power and the preset
value should be less than 0.1 dB.

If the tested value is abnormal, contact Huawei for solutions.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 30

Testing Active/Standby Cross-connect


Board Switching

Prerequisites

The service data must be configured.

The 15-minute performance monitoring of the NE must be


started.

The equipment must be configured with the active and


standby cross-connect boards.

Tools and Instruments

Web LCT

BER tester

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 31

Testing Active/Standby Crossconnect Board Switching (Cont.)

Procedure

Confirm the current working status of active and standby PXC


boards and no abnormal alarms by using the Web LCT.
Perform active/standby PXC board switching by Web LCT.
Query the working status of the active and standby PXC boards
to check whether the switching is performed normally.
Query the current and history alarms to check whether any
alarm is generated during the switching process.
After the test, restore the PXC board in slot 1 to the active
board. Query the alarms and ensure that the cross-connect
board works normally.
If you use the BER tester to monitor the services, few bit errors
may occur during the switching process. The services,
however, can recover immediately after the switching is
complete.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 32

Questions

What is the procedure to access Web LCT?

How should the E1 port be set and connected for testing the
connections of E1 cables? How to adopt the testing it quickly?

Why shall we disable the ATPC function when test RF transmit power?

What are the two modes in data configuration? What are the
differences between them?

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 33

Summary

This chapter describes the prerequisites, tools and

instruments, and procedure for the NE commissioning items:

Powering on the equipment

Testing indicators

Accessing the Web LCT

Configuring the data

Testing the transmit and receive optical power

Performing the service loopback test

Testing the connections of E1 cables

Testing the RF transmit power

Testing the active/standby cross-connect board switching

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 34

Contents
1.

Preparations for the OptiX RTN 600 Commissioning

2.

NE Commissioning of the OptiX RTN 600

3.

Hop Commissioning of the OptiX RTN 600

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 35

Table of Contents
3.

Hop Commissioning of the OptiX RTN 600

3.1 Aligning the Antenna

3.2 Testing the ECC

3.3 Testing the E1 Service

3.4 Testing the WS Service

3.5 Testing the order wire

3.6 Testing the Clock Tracing

3.7 Testing the IF 1+1 Switching

3.8 Testing the SNCP Switching

3.9 Testing the 24-Hour BER

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 36

Aligning the Antenna

Prerequisites

During the commissioning, the weather should be suitable and there


should be no rain/fog between stations.
The on-site conditions and personnel in charge of the antenna
commissioning must meet the requirements of operation at a high
altitude.

Tools and Instruments

The NE commissioning of the radio equipment at both ends of the


same radio link must be complete.

Wrench, multi-meter and intercom.

Note: If there are 2 antennas at each site, it needs to align the


main antennas and diversity antennas at both ends respectively.
First align the main antennas and then the diversity antennas.
Both antennas at local site should be aligned with the main
antenna at opposite end.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 37

Aligning the Antenna (cont.)

Procedure
1.

According to the designed received signal level (RSL) along with the
relationship curve between the VBNC and RSL described in the user
documents (shipped with the equipment) of the ODU, read the
designed value of the VBNC.

2.

Align the antennas at both ends approximately by using the specific


tool (telescope) or instrument (COMPASS or GPS). If the antennas at
both ends are not aligned approximately, the V BNC cannot be adjusted
to the designed value.

3.

Fix the antenna at the opposite end, and adjust the azimuth
(elevation) of the antenna at the local end in a wide range. Use the
multi-meter to observe the VBNC value of the ODU at the local end. At
least three peak signals should be detected and the voltage of the
peak signal in the middle should be maximum. When the V BNC
reaches the maximum value, tighten the antenna. When the
antenna is being tightened, keep that the V BNC is always the
maximum.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 38

Aligning the Antenna (cont.)


4.
5.

6.

7.

8.

9.

As step 3, adjust the elevation (azimuth) of the antenna. And tighten it.
Tighten the antennas at the local end. Repeat steps 3 and 4 to adjust
the antennas at the opposite end and tighten them.
Repeat steps 3 to 5 for two to four times. When the RSL of the
antennas at the local end and the remote end reach the maximum
value, tighten the antennas at both ends.
Test VBNC of ODUs at both ends by multi-meter. Read the actual receive
power level (RSL) by referring to the relationship curve between the
VBNC and RSL for the ODUs at both ends. The difference between actual
RSL value and its designed value should be ranged from -3 dB to +3
dB.
If the VBNC does not meet the above requirements, check whether the
antennas at both ends are approximately aligned by referring to the
step2. Also you can refer to the OptiX RTN 600 Radio Transmission
System Maintenance Guide for solutions.
After antennas aligning is complete, tighten all screws of the antennas.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 39

Testing the ECC

Prerequisites

Antenna alignment must be complete.

The NE must have access to the Web LCT.

Tools and Instruments

Precautions

Web LCT

Test the ECC at one end of the radio link.

Procedure

In the NE List page, click Add NE.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 40

Testing the ECC (cont.)

In the Add NE page, set the following attributes of the opposite


NE:

ID: ID of the opposite NE

Name: name of the opposite NE

Extended ID: extended ID of the opposite NE

Gateway Type: IP gateway

Gateway IP Address: IP address of the local NE

User Name: root (default)

Password: password (default for the user root)

Click OK. In this case, a row of data for the newly added NE is
added in the NE List page.
Observe Login Status of the newly added NE. Login Status
should be displayed as Logged In.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 41

Testing the E1 Service

Prerequisites

Antenna alignment must be complete.

Tools and Instruments

The E1 service must be available between stations and the service


configuration at each station must be correctly delivered.

BER tester and Web LCT

Procedure

At local site, connect the BER tester to the first E1 port.


At remote site, loopback the first E1 port by cable. If cable loopback
is unfeasible, set the software inloop for the first E1 port by Web LCT.
Test the BER for 5 to 10 minutes by BER tester. No bit error should
occur.

Release all loopbacks.

Repeat the above four steps to test other E1 ports one by one.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 42

Testing the WS Service

Prerequisites

The WS service must be configured.

Antenna alignment must be complete.

Tools and Instruments

BER tester

Procedure

At local site, connect the BER tester to the WS port.

At remote site, perform the hardware inloop for the WS port.

Test the BER for 5 to 10 minutes by BER tester. No bit errors should
occur.
Release the loopback.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 43

Testing the order wire

Prerequisites

The data of the order wire must be configured.

Antenna alignment must be complete.

Tools and Instruments

The order wire phone must be correctly installed at the


station.

None.

Procedure

Check the status of the order wire at the local equipment side.
The status of the order wire should meet the following
requirements:

The ringing switch must be set to ON.


The dialing mode switch must be set to T, that is, the dual-tone
dialing mode is selected.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 44

Testing the Order wire (cont.)

Dial the order wire of the opposite equipment as follows:

Pick up the order wire, and press the TALK key on the front panel of the
phone. The red indicator on the upper right side of the front panel is on,
accompanied by the dial tone.

Dial the order wire number of the opposite equipment. Normally, the voice
quality is good and the voice is clear.

Answer the order wire.

The maintenance personnel at the opposite equipment side dials the order
wire of the local equipment. Normally, the order wire rings and at the same
time the red indicator on the upper right side of the front panel is on.

Pick up the phone, and press the TALK key to talk. The red indicator on the
upper right side of the phone is on. Normally, the voice quality is good and
the voice is clear.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 45

Testing the Clock Tracing

Prerequisites

Tools and Instruments

The clock tracing priority list must be configured.


Web LCT

Procedure

Query the current clock priority table by using the Web LCT.
According to the clock priority table, query whether the current
clock tracing source is traced normally.
If the active and standby PXC boards are configured, perform the
active/standby switching. This operation can check whether the
current clock source can be traced normally after the switching.
After the test is complete, restore the PXC boards in slot1 as
active board.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 46

Testing the IF 1+1 Switching

Prerequisites

The equipment must be configured with the IF 1+1 protection.

Antenna alignment must be complete.

Tools and Instruments

BER tester and Web LCT

Note: The following procedure considers the E1 service


between stations as an example. If no E1 service is
configured between stations, perform the test through the
configured WS service (only applicable in the SDH radio).

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 47

Testing the IF 1+1 Switching (cont.)

Procedure

At local site, connect the BER tester to one E1 port.


At remote site, loopback an E1 port by cable. Or set the software
inloop on an E1 port by web LCT when cable loopback is unfeasible.
Test the BER by BER tester. Confirm E1 service is normal.
View the working status of the protection group by using the Web
LCT. The Active Board of Device and Active Board of Channel
should be the active IF board.
Set the transmission status of the main ODU to mute by using the
Web LCT or power off the main ODU. This can trigger the IF 1+1
switching.
View the working status of the protection group after the
switching by using the Web LCT. The Active Board of Device
and Active Board of Channel should be the standby IF board.
The HSB_INDI or HSM_INDI alarm should be reported.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 48

Testing the IF 1+1 Switching (cont.)

View the BER by Web LCT.

In the 1+1 HSB protection or 1+1 SD protection, service should recover


after a transient interruption.
In the 1+1 FD protection, service just has some bit errors without
interruption.

After switching is complete, test the BER for 5 to 10 minutes. No bit


errors should occur.
Set the transmission status of the main ODU to unmute by using the
Web LCT or powering on the main ODU.
If the protection mode is set to Revertive mode, test the BER again by
using the BER tester. When the restore time arrives, the result should
indicate that the service has recovered after a transient interruption.
WTR Time is set to 600s by default. Test the BER according to the
requirements of the actual configuration.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 49

Testing the SNCP Switching

Prerequisites

The equipment must be configured with the SNCP protection.

Antenna alignment must be complete.

Tools and Instruments

BER tester and Web LCT

Procedure

At local site, connect the BER tester to one E1 port.


At remote site, loopback the corresponding E1 port by cable.
Or set inloop on the E1 port by web LCT when cable loopback
is unfeasible.
Test the BER by BER tester. Confirm E1 service is normal.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 50

Testing the SNCP Switching (cont.)

Check SNCP status of E1 service by Web LCT. And status should be


normal.
Trigger the SNCP switching by disconnecting the fiber connectors or
powering off the ODU in the working channel of the E1 SNCP service.

View the abnormal events of the NE by Web LCT. The abnormal events
of SDH SNCP Switching are displayed in Abnormal Event List.

View the BER test result. The result should indicate that the service has
recovered after a transient interruption.

Reconnect the fiber connector or power on the ODU.


In the Revertive mode, when the restore time arrives, the BER tester
result should indicate that the service has restored back. WTR Time is
set to 600s by default.

Test the BER depending on the requirements of the actual configuration.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 51

Testing the 24-Hour BER

Prerequisites

Tools and Instruments

Antenna alignment must be complete.


BER tester and Web LCT

Precautions

If the 24-hour BER cannot be tested for each hop on the link
because of the restrictions of the actual situation, choose the
E1 service of the first node and terminal node of each link to
perform this test. This operation ensures that the test path
covers all the radio links.
The following test procedure considers the E1 service between
stations as an example. If no E1 service is configured between
stations, perform the test through the configured WS service
(only applicable in the SDH radio).

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 52

Testing the 24-Hour BER (cont.)

Procedure

At local site, extract several typical E1


services, and perform the hardware
inloop for the E1 ports. If the hardware
inloop is unfeasible, perform the
software inloop for the E1 ports by
using the Web LCT.
At remote site, connect the E1 services
in a serial manner at the DDF, and
access them to the BER tester.
Test the 24-hour BER by using the BER
tester.
Record the test result. The result
should indicate that no bit errors occur.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 53

Testing the 24-Hour BER (cont.)

Postrequisites

If bit errors occur in the first 24-hour BER test, remove the
fault. Perform another 24-hour BER test until the test is
passed.

If bit errors occur in the test for a serial connection, locate


the fault by using the dichotomizing search or other methods
until each channel passes the 24-hour BER test
independently.

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 54

Questions

What is the procedure to aligning antennas?

How long should it take to test the E1 service and WS service respectively by using the BER tester?

What alarms occur after the IF 1+1 switching is complete?

How can we ensure that SNCP switching is successful?

How should we handle bit errors occurring in the 24-hour BER test?

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 55

Summary

The commissioning items in hop commissioning:

Aligning the antenna

Testing the ECC

Testing the E1 service

Testing the WS service

Testing the order wire

Testing the clock tracing

Testing the IF 1+1 switching

Testing the SNCP switching

Testing the 24-hour BER

Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

Page 56

Thank You
www.huawei.com