Value Stream Mapping & Value Stream Design

Workshop

Central Electronic Plants Continental Business System

Value Stream Mapping and Value Stream Design


Workshop Agenda
Time

Day 1

Day 2

08.30 09.00

Registration

Reflections on Day 1

09.00 09.30

Welcome Remarks
Administrative Details
Expectations of the participants

Workshop 2: Additional
Mapping

09.30 10.00

Group Discussion: Review of Lean

10.00 10.30

Discussion: Value Stream Mapping


an Approach

10.30 11.00
11.00 11.30
11.30 12.00

Morning Break
Workshop 1: Preparation of current
state map

12.00 13.00

Workshop: Development of
solutions
Lunch Break

13.00 13.30

Workshop: Development of
solutions

13.30 14.00
14.00 14.30

Discussion: Value Stream


Design

Workshop 2: Mapping the Current


State thru Gemba Walk

14.30 15.00

Workshop: Drawing of Future


State Map

15.00 15.30
15.30 16.00

Afternoon Break

16.00 16.30
16.30 17.00

Discussion / Feedback Session

Central
17:00Electronic
17:30 Plants Continental Business System
2

Continental AG

Discussion / Feedback Session

Note:
It may be necessary to have
a refresher training to better
understand CBS. If so, use
the CBS Bronze Level
Training.

VSM / VSD: Why


Training will highlight the
benefits of using the Tools
associated with CBS. The Value
Stream Design Method mainly
support the CBS Principles of
Flow, Pull and Simplicity

Processes
Principles
Methods

Tools

Central Electronic Plants Continental Business System


33

What is Lean?
Lean refers to the Toyota Production System (TPS) pioneered by
Taiichi Ohno
It is an "Approach to manage:
Customer relations
The supply chain
Product Development
Production Operations
Womack and Jones

Ohno says that The basis of TPS is the absolute


waste
Central Electronic Plants Continental Business System
4

elimination of

What is Lean Continued.....

Actions to Move the Organization closer to the ideal state


which is:
Provide customers with what they need
In the right quantity
When needed
Without waste

Central Electronic Plants Continental Business System


5

Definition of Value

The definition of "Value" should be viewed from the perspective


of the customer:
Will the customer pay for the activity being performed in
the process
The action should be done correctly the first time
The action must modify the product or service at some
level
Eradicating waste and maximizing value is central to the "Lean"
approach.
"Waste" is the opposite of value, it is anything for which the
customer will not pay
Central Electronic Plants Continental Business System
6

Definition of Value

Where do we find waste?


We find waste in the processes we use

How do we find the waste?


We analyze the processes in detail
What type of processes do we have?
Visible processes, manufacturing, document processing
Transactional processes, difficult to see what is happening

Central Electronic Plants Continental Business System


7

Definition of Value

The definition of Transactional Processes" as used here is:

Processes where work is performed but the actions, interactions


and details of the steps are not easily identified

Why is it important to see the detail?

In order to identify and eliminate the waste we must be able to


see every detail of the process

Central Electronic Plants Continental Business System


8

7 Wastes | Process Waste


Ohno identified 7 types of waste

7 Wastes
Defects
Overproduction
Inventory
Extra processing
Motion
Waiting
Transportation

Central Electronic Plants Continental Business System


9

Taiichi Ohno

Waste
How do you find waste?
Step 1:
Ensure you have a good 5S system in place
Sort
Set in order
Shine
Standardize
Sustain
Step 2:
Learn to look for waste in everything you do
Work on a Project
Central Electronic Plants Continental Business System
10

Waste

What do you do when you find waste?


Correct if you can
Use the CIM system
Work with your Project team to implement corrective
actions
Inform your Team Leader/Supervisor
Discuss at team meetings

Central Electronic Plants Continental Business System


11

Reference & Reading

Flow in the Office by Carlos Venegras


Learning to See by Mike Rother and John Shook
Creating Continuous Flow by Mike Rother and Rick Harris
Creating Level Pull by Art Smalley

Central Electronic Plants Continental Business System


12

Value Stream Mapping & Value Stream Design


Workshop

Central Electronic Plants Continental Business System

What is a Value Stream?


A Value Stream is the actions (both value-added and nonvalue-added)
currently required to bring a product through the main flows essential to
every product:
The production flow from raw material into the arms of the customer.
Value Stream Mapping (VSM) shows the current value stream of a
product from the receipt of raw materials until the shipment of finished
goods to the plants customer.
Value Stream Design (VSD) drafts a future state and the necessary
process improvements before these are implemented. VSD can also be
used in the planning phase of new production plants as well as in
designing a new production process.

Central Electronic Plants Continental Business System


14

Continental AG

Why do a Value Stream Map?


Helps to visualize more than just the single process level in production to see the flow
Helps to see the waste as well as the sources of waste in the value stream
Provides a common language for talking about manufacturing processes
Makes decisions about the flow apparent
Ties together lean concepts and techniques, which helps avoid cherry picking
Show the linkage between the information flow and the materials flow
Forms the basis of an implementation plan

Value Stream Design

Value Stream Mapping


Information flow
Supplier

Steering

Information flow

Information flow
Customer

Supplier

Steering

Information flow
Mat. -flow

Pre Assembly

Customer
Information flow

Mat. -Flow

Test/
Control

Information flow

Assembly

10 Days

Mat. -flow

Pre Assembly

Mat. -flow

FIFO

Test/
Control

Assembly

1 Day

Wherever there is a product for a customer, there is also a value stream. The challenge is to recognize and see it. (Mike Rother)

Central Electronic Plants Continental Business System


15

Continental AG

Process Framework: Execution of VSM/VSD


Employees within the Value Adding Process
(All Functions, Responsibility, Qualification)
Mapping Phase
Nomination
of a Value
Stream
Leader

Selection of a
Product
Family

Design Phase

Value
Stream
Mapping

Value
Stream
Design

Current
Material and
Information
flow in the
Production

Material and
Information flow
is focused on
Value Stream
Principles

Implementation Phase

Implementation
(Value Stream
Plan)
Roadmap

CBS Principles,
Methods, Tools

Required Customer Information:


BOM structure, Product Split, Ordering Behavior

Central Electronic Plants Continental Business System


16

Continental AG

Review

Value Stream Mapping Symbols

Central Electronic Plants Continental Business System


17

Continental AG

Value Stream Mapping Symbols

Central Electronic Plants Continental Business System


18

Continental AG

The 10,000 Meters View


What do you see at 10,000 Meters?
The general topography, not the detail
How the area is generally laid out
A high level map of the process
Focuses on the big picture
Limit the map to 4 7 steps; less than 4 steps shows very little information

RAW Warehouse

Production 1

Central Electronic Plants Continental Business System


19

Continental AG

Production 2

FG Warehouse

The 100 Meters View


RAW Warehouse

Production 1

Production 2

FG Warehouse

What do you see at 100 Meters?


The more detailed view, but not so much that the detail becomes overwhelming
Helps to understand how the product moves from one process to another
Mapping...
The process as it is currently, warts and all; not how we would like them to be (i.e.,
sanitized version)
Becomes much easier if the team goes and walks the process, trying to find out how
things actually operate.
Solder Paste
Printing

Depaneling

SMD
Placement

Manual
Insertion

Wave
Soldering

Reflow
Soldering

Visual
Inspection

Central Electronic Plants Continental Business System


20

Continental AG

Flash
Programming

Automated
Inspection

Function
Testing

Case
Mounting

Verification

Final
Testing

Packing

Value Stream Mapping

1. Mapping Phase

II
Selection
of
Product
Family

3. Implementation
Phase

2. Design Phase

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Value-stream mapping means walking and drawing the processing


steps (material and information) for one product family from door to
door in the plant as it is today

Central Electronic Plants Continental Business System


21

Continental AG

Value Stream Mapping


Process Steps
I

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

Design of
future
state

Customers care ONLY about their specific products!


It is necessary to focus on one product family.
Drawing all product flows on one map is too complicated.

Central Electronic Plants Continental Business System


22

Continental AG

VI

V
Action
Plan

Review

Value Stream
Definition of product family
Definition point of view

Definition of product family

Starting point

2.Level: location

...

...

process 3

1. Level: SCM-network

process 2

process 1

process steps

3. Level: segment

4. Level: machine cells

5. Level: machine

products

product 1
product 2
product 3
product 4
product 5
...
...

... starts with level 1 or 2 and goes down systematically

Central Electronic Plants Continental Business System


23

Continental AG

Productfamily

Value Stream Mapping


Process Steps
I

II

III
Selection
of
Value
Stream
Leader

Selection
of
Product
Family

Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Focus:
how

Material and information flow for a product (all processes and


each is scheduled).

Target:
optimum

Individual processing areas should operate in a way that is


from the perspective of the value stream.

Central Electronic Plants Continental Business System


24

IV

Continental AG

Review

Selection of Value Stream Leader


Role Expectations:
Leads the creation of the current state and future state value stream maps
and the implementation plan for getting from the present to the future.
Able to make change happen across functional and departmental
boundaries.
Monitors all aspects and reports progress of implementation
Qualification:
Hands-on person
Credible
A good facilitator
Knowledgeable in at least some areas of the process

Central Electronic Plants Continental Business System


25

Continental AG

VALUE STREAM MAPPING


11 Steps to Create a Future State Map
Mapping the
Current State &
Future State

1
Identify the Customer
Requirement (Takt Time)

6
Check all Cycle Times to
Customer Takt

Prepare to
create the
Future State

2
Identify the Processes /
Gather Process
Parameters and WIP

5
Create the Timeline

3
Draw the Material Flow

4
Draw the Information
Flow

Continental AG

8
Check application of
Supermarket

9
Reduce Scheduling to
One Process Only
(Pacemaker)

10
Identify Other Areas for
Further Improvements

Central Electronic Plants Continental Business System


26

7
Check where to
implement Continuous
Flow

11
Creating the
Future State
Map

A few mapping tips


Begin with a quick walk along the entire door-to-door value stream to get a
sense of the flow and sequence of processes.
Always collect current-state information while walking along the actual pathways
of material and information flows.
Begin at the shipping end and work upstream.
Bring your stopwatch and do not rely on standard times or information that you
do not personally obtain.
Map the whole value stream.
Begin your rough sketch by hand and in pencil right on the shop floor as you
conduct your current-state analysis and clean it up later.

Central Electronic Plants Continental Business System


27

Continental AG

Value Stream Mapping


Five steps of drawing the Current Map
I

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Analyze the current state


in five steps:
III.1
Identify
Customer
Requirement
(Takt Time)

III.2
Identify the
Processes &
Gather Process
Parameters and
WIP

Central Electronic Plants Continental Business System


28

Continental AG

III.3
Draw the
Material Flow

III.4
Draw the
Information Flow

III.5
Create the
Timeline

Value Stream Mapping


III.1
Identify
Customer
Requirement
(Takt Time)

III.2
Identify the
Processes &
Gather Process
Parameters and
WIP

III.3
Draw the
Material Flow

III.4
Draw the
Information Flow

Variants within the product family: Which component are we looking for?
Customer takt, customer frequency and requirement fluctuation
Process steps and the related activities up to the completion
Stand alone and related processes

Central Electronic Plants Continental Business System


29

Continental AG

III.5
Create the
Timeline

Value Stream Mapping


Drawing the customer requirements
Customer
18 Variants
Weekly demand
6.000

Takt time =

Customer tact time


24s

available working time per day


customer demand rate per day

5 Shifts per week x 8h x 3.600


6.000 pieces per week

= 24 sec

The customer orders this product each 24s at 5 shifts per week.

Takt time = 24 sec


Central Electronic Plants Continental Business System
30

Continental AG

Value Stream Mapping


III.1
Identify
Customer
Requirement
(Takt Time)

III.2
Identify the
Processes &
Gather Process
Parameters and
WIP

III.3
Draw the
Material Flow

Process steps and the related activities up to the completion


Stand alone and related processes
Important process parameters
Relevant stocks: Quantity of WIP in the system
All data have to be collected locally
Using data from the system like SAP is not allowed!

Central Electronic Plants Continental Business System


31

Continental AG

III.4
Draw the
Information Flow

III.5
Create the
Timeline

Value Stream Mapping


Drawing the process steps
Customer
18 variants
Weekly
requirement
6.000
Customer tact
24s

SMD Side B
SMD-Line
1

SMD Side A
1

CT: Cycle time PT: Process time

Preassembly.
2

Continental AG

ST: Setup time, number of operators

Central Electronic Plants Continental Business System


32

Testing

Assembly
7

Testing
2

Shipping

Definition of different times


CT

Cycle Time

Time interval between the parts or products which are finished


successively because of the process.

VA

Value added Time

Value added time in the process (Processing Time)

NVA

Non Value added


Time

Non value added time in the process

ST

Setup Time

Change over time - last part of further batch to first part of


released new batch

WT

Waiting Time

Average time between material stock entry and consumption

TT

Throughput Time

Material-throughput time from the beginning of a value stream


(with several processes) to the ending: so it is the sum of CT and
WT

Central Electronic Plants Continental Business System


33

Continental AG

Recording the current status


Procurement and
Customer Logistics

Production

Material:
Special parts
Multi usage parts
...
Data:
Frequency of deliveries
Location of the supplier
Replenishment lead time
Stock value (Warehouse,
production consignment
Stock)
Utilization shares
...
Finished Goods:
Boxes per Truck
Frequency of deliveries
Parts per box
'Back-flush' of finished goods
...

Central Electronic Plants Continental Business System


34

Continental AG

Cycle time = Value add + non


vale add
Process time = Value add
time
Lead time ( throughput time) =
Cycle Time + Waiting Time
Changeover time
Lot size / variants
Number of variants (all
product families)
Employees per shift
Parts per tray / carrier
Scrap rate / Rework
First Pass Yield (FPY)
Overall Equipment
Effectiveness (OEE)
Inventory in production
...

Production scheduling

Scheduling
production planning
planning of the production
quantity
capacity planning
...
Control
productions start
scheduling
order control
...

Collecting the process parameters and WIP


Name of the station under analysis
Amount of shifts planned on the
station per week
Number of employees working on
the station during one shift
Value added time measured during
one cycle of the machinery or the
person
Ratio of time (in %) during which
one station is able to produce good
part compare to the total open time
requested/planned
Number of parts which are packed
in one e.g. container, pallet,
magazine in front of the process
Average number of parts which are
produced between 2 changeovers
Percentage (or ppm) of parts which
are scraped with the current station
identified as root cause
Percentage (or ppm) of good parts
out of the total number of parts. For
AOI, count the false calls even if
they are not considered in the official
FPY calculation

Central Electronic Plants Continental Business System


35

Continental AG

Amount of identical stations


dedicated to the same process
Amount of hours planned on the
station during one shift
Total time (value added and non
value added) the machinery or the
person needs to complete its cycle
Time necessary to switch from
production of one product reference
to a new one, including the potential
defectives parts associated (Time
from last good product A to first
good product B produced in serial
mode).
Average of the time necessary to
repair a station including support
function travel, diagnosis, repair, and
test time (First good part produced in
serial mode). The time before
support arrival should be included
but is not easy to measure.
Number of parts which are
processed at the same time
Number of products that have to be
produced on the station

Workshop 2: Tasks for Go to Gemba


Collecting the process parameters and WIP
Collection of all necessary data to map the current state of the value stream
Assign roles to members for completing Data box, counting WIP, measuring time
Get an overview of the door-to door value stream
Collect all necessary information for the door-to-door map:
all process steps and inventories from the customer upstream to the supplier
get an overview of external and internal information flows
collect amount of all inventories and buffers
understand all replenishment activities (information and material flow)
Look for improvements as you gather the information
...
Data collection on the defined product family line(s)
collect data on the data sheet for all production/logistic steps
collect information from employees working at the line
...
Go back to Gemba if during mapping you detect missing information

Central Electronic Plants Continental Business System

Value Stream Mapping


Incorporating the process parameters and WIP
Customer
18 variants
Weekly
requirement
6.000
Customer tact
24s

2 We.

SMD Side B
SMD-Line
1
2-shift
CT=8.5mins
PT=37s
ST=15min
Reliability
=85%

SMD Side A
1
630
63

2-shifts
CT= 8mins
PT =13s
ST =15min
Reliability
=80%

350
35

Preassembly.
2
2-shifts
CT= 8mins
PT= 40s
ST=20min
Reliability
= 80%

CT: Cycle time PT: Process time (value add time)

Central Electronic Plants Continental Business System


37

Continental AG

Testing
70
70

ST: Setup time

1
2-shifts
CT= 6.5mins
PT=42s
ST=15min
Reliability
= 95%

Assembly
420
42

7
1-shift
CT=5mins
PT=23s
ST=10min
Reliability
=98%

Testing
280
28

2
1-shift
CT=4.2mins
PT=32s
ST=3min
Reliability
=95%

Shipping
5200

Value Stream Mapping


III.1
Identify
Customer
Requirement
(Takt Time)

III.2
Identify the
Processes &
Gather Process
Parameters and
WIP

III.3
Draw the
Material Flow

III.4
Draw the
Information Flow

From RAW Warehouse to Production


Material flow in the Production: (PUSH/PULL)?

Central Electronic Plants Continental Business System


38

Continental AG

III.5
Create the
Timeline

Value Stream Mapping


Current State with material flow
Supplier

Customer

Elektronic:
Special
treatment

18 variant
Weekly
requirement
6.000
Customer tact
24 s

weekly

daily

SMD Side B
2 We.

SMD Side A

1
2-Shifts
CT=8.5mins
PT= 37s
ST=15min
Reliability=85
%

1
630

2-Shifts
CT = 8mins
PT= 41s
ST=15min
Reliability=80%

350

Preassembly
2
2-Shifts
CT= 8mins
PT= 40s
ST=20min
Reliability=80
%

Testing
70

CT: Cycle time PT: Process time (value add time) ST: Setup time

Central Electronic Plants Continental Business System


39

Continental AG

1
2-Shifts
CT=6.5mins
PT= 42s
ST=15min
Reliability=95
%

Assembly
420

7
1-Shift
CT= 5mins
PT= 23s
ST=10min
Reliability=98
%

Shipping

Testing
280

2
1-Shift
CT= 4.2mins
PT= 30s
ST=3min
Reliability=95
%

5200

Value Stream Mapping

III.1
Identify
Customer
Requirement
(Takt Time)

III.2
Identify the
Processes &
Gather Process
Parameters and
WIP

III.3
Draw the
Material Flow

III.4
Draw the
Information Flow

External communication or information flow


Central production planning
Consumption control
Internal information flow
Organization of job control and scheduling

Central Electronic Plants Continental Business System


40

Continental AG

III.5
Create the
Timeline

Value Stream Mapping


Drawing the information flow
Elect. monthly.
30-daily plan
order weekly

Supplier
Elektronic:
Special
treatment

Production
planning
PPS

30/60/90
forecast
Daily
order

Customer
18 variant
Weekly
requirement
6.000

weekly plan

Customer tact
24 s

weekly

daily
Daily delivery
schedule

SMD Side B
2 We.

SMD Side A

1
2-Shifts
CT= 8.5mins
PT= 37s
ST=15min
Reliability=85
%

1
630

2-Shifts
CT = 8mins
PT41s
ST=15min
Reliability=80%

350

Preassembly
2
2-Shifts
CT= 8mns
PT= 40s
ST=20min
Reliability=80
%

CT: Cycle time PT: Process time (value add time)

Central Electronic Plants Continental Business System


41

Continental AG

Testing
70

ST: Setup time

1
2-Shifts
CT= 6.5mins
PT= 42s
ST=15min
Reliability=95
%

Assembly
420

7
1-Shift
CT= 5mins
PT= 23s
ST=10min
Reliability=98
%

Shipping

Testing
280

2
1-Shift
CT= 4.2mins
PT= 30s
ST=3min
Reliability=95
%

5200

Value Stream Mapping

III.1
Identify
Customer
Requirement
(Takt Time)

III.2
Identify the
Processes &
Gather Process
Parameters and
WIP

III.3
Draw the
Material Flow

III.4
Draw the
Information Flow

Cycle time
Waiting time of the parts in buffer or stocks
Complete process time
Complete Throughput time

Central Electronic Plants Continental Business System


42

Continental AG

III.5
Create the
Timeline

Value Stream Mapping


Creating the timeline
Preview monthly
30-daily plan
order weekly

Supplier
Elektronic:
Special
treatment

Production
planning
PPS

30/60/90
forecast

Daily
order

Customer
18 variant
Weekly
requirement
6.000

weekly plan

Customer tact
24 s

weekly

daily
Daily delivery
schedule

SMD Side B
2 We.

WT

SMD Side A

2- Shifts
CT= 8.5mins
PT= 37s
ST=15min
Reliability=85
%

630

2-Shifts
CT = 8mins
PT= 41s
ST=15min
Reliability=80%

WT + NVA

PT(VA)

350

Preassembly
2

Testing

2-Shifts
CT= 8mins
PT= 40s
ST=20min
Reliability=80
%

WT + NVA

PT(VA)

70

WT + NVA

PT(VA)

CT: Cycle time PT: Process time (value add time)

Central Electronic Plants Continental Business System


43

Continental AG

Assembly

1
2-Shifts
CT= 6.5mins
PT= 42s
ST=15min
Reliability=95
%

420

WT + NVA

PT(VA)

7
1-Shift
CT= 5mins
PT= 23s
ST=10min
Reliability=98
%
PT(VA)

Shipping

Testing
280

2
1-Shift
CT= 4.2mins
PT= 30s
ST=3min
Reliability=95
%

WT + NVA

PT(VA)

ST: Setup time; TT: Throughput time; WT: Wait Time

5200

WT

TT= WT + NVA

Total PT(VA)

Percentage of Value Add

% Value Add =

Sum of Process Time (VA)


Throughput Time

It is a rate of value adding and not value adding processes within the
material flow. Based on the Percentage, the Future State Map can be
valuated.

Central Electronic Plants Continental Business System


44

Continental AG

Determination of Wait Time


Quantity WIP pieces
Wait Time =

= days of inventory
Daily requirement

Example where daily requirement is 220 pcs.:


Inventory 420 pcs.
Testing

Assembly

440
2-Shifts
CT=6.5mins
PT=42s
ST=15min
Reliability=95%

7
1-Shifts
CT=9mins
PT=31s
ST=10min
Reliability=98%

2 days
6,5 min

Central Electronic Plants Continental Business System


45

Continental AG

9 min

440 pcs
220 pcs

= 2 days

Value Stream Design

1. Mapping Phase

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

Central Electronic Plants Continental Business System


46

Continental AG

3. Implementation
Phase

2. Design Phase

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Value Stream Design


Five steps of drawing the Future State Map
I

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Preparing to create the


Future State:
IV.1
Check ALL
Cycle Times
According to
Customer Takt

IV.2
Check where to
implement
Continuous
Flow

Central Electronic Plants Continental Business System


47

Continental AG

IV.3
Check
application of
FIFO Lanes &
Supermarket

IV.4
Reduce
Scheduling to
One Process
ONLY
(Pacemaker)

IV.5
Identify Other
Areas for
Improvement

Value Stream Design


Key Questions:
1. What is the customer takt time?
2. Where can you use continuous flow?
3. Will you produce into a finished goods supermarket, or make to order?
4. Where do we need a supermarket pull?
5. Which process should be the pacemaker in the chain?
6. How should the product mix be leveled to the pacemaker?
7. Which process improvements are necessary?
8. Consider other improvement tools SMED etc

Central Electronic Plants Continental Business System


48

Continental AG

Workshop: Analysis of Current State Map


Analysis of the current material and information flow identifying waste along the value
stream and potential areas of improvement
Approach:
Identify unnecessary planning steps
Identify unnecessary inventory and buffers
Identify replenishment methods (push, Kanban, pull)
Review Cycle Time, Process Time, OEE per workstation
Identify bottle neck processes and pacemaker
Review customer requirements (Customer Takt)
....
Target:
Knowledge of Customer Takt, Throughput time, Cycle time, Process time
Identification and common understanding of obvious problems
Brainstorming on possible improvements for value stream design

Central Electronic Plants Continental Business System


49

Continental AG

Value Stream Design

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Should optimize the value stream


Ensure that the Cycle Time is equal to or better than Customer Takt
Is the source of action for the action plan

Central Electronic Plants Continental Business System


50

Continental AG

Review

Value Stream Design


Five steps of drawing the Future State Map
I

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Preparing to create the


Future State:
IV.1
Check ALL
Cycle Times to
ensure
Customer Takt
is achieved

IV.2
Check where to
implement
Continuous
Flow

Central Electronic Plants Continental Business System


51

Continental AG

IV.3
Check
application of
FIFO Lanes &
Supermarket

IV.4
Reduce
Scheduling to
One Process
ONLY
(Pacemaker)

IV.5
Identify Other
Areas for
Improvement

Guidelines for a Lean Value Stream:


Takt Time
Produce to customer takt time.
Takt time is how often you should produce one part or product, based on the rate of
sales, to meet customer requirements.

Takt time =

available working time per day


customer requirement rate per day

Used to synchronize the pace of production with the pace of sales, particularly at the
pacemaker process
Reference number that gives you a sense for the rate at which a process should be
producing
Helps you see how you are doing and what you need to improve

Central Electronic Plants Continental Business System


52

Continental AG

Value Stream Design


Five steps of drawing the Future State Map
Production Planning

II

Selection
of
Product
Family

III

Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Preparing to create the


Future State:
IV.1
Check ALL
Cycle Times
According to
Customer Takt

IV.2
Check where to
implement
Continuous
Flow

Central Electronic Plants Continental Business System


53

Continental AG

IV.3
Check
application of
FIFO Lanes &
Supermarket

IV.4
Reduce
Scheduling to
One Process
ONLY
(Pacemaker)

IV.5
Identify Other
Areas for
Improvement

Guidelines for a Lean Value Stream:


Continuous Flow
2. Develop continuous flow wherever possible.
Continuous flow is the most efficient way to produce. It refers to producing one piece at
a time, with each item passed immediately from one process step to the next without
stagnation in between.

Make one Move one!

The mapping icon to indicate continuous flow is simply the process box. So if you
introduce more continuous flow in your future state, then two or more current state
process boxes would combine into one box on the future state map.

Central Electronic Plants Continental Business System


54

Continental AG

Results Interaction in Value Stream Design:


Line Organization and One Piece Flow
Before
Produktionsplanung
Production
Planning

Ex
am
ple

After
AP 1

AP 2

1
15 Schichten
ZZ: 70 s
Stapelverarbeitung
30 Stck

1
15 Schichten
ZZ: 45s
Stapelverarbeitung
30 Stck

150

Transportweg:
100m

40

AP 3

AP 4

AP 5

90

15 Schichten
ZZ: 65s
Stapelverarbeitung
30 Stck

Transportweg:
50m

15 Schichten
ZZ: 65s
Stapelverarbeitung
30 Stck

Transportweg:
250m

10

15 Schichten
ZZ: 45s
Stapelverarbeitung
30 Stck

Transportweg:
150m

AP 6
70

1
15 Schichten
ZZ: 60s
Stapelverarbeitung
30 Stck

Transportweg:
25m

Line assembly
combination of line
Buffer between workstations
6 workstations

Production
Planning
Produktionsplanung

AP 1

AP 2

AP 3

AP 4

AP 5

AP 6

15 Schichten
ZZ: 70s
keine
Stapelverarbeitung

15 Schichten
ZZ: 70s
keine
Stapelverarbeitung

15 Schichten
ZZ: 65s
keine
Stapelverarbeitung

15 Schichten
ZZ: 70s
keine
Stapelverarbeitung

15 Schichten
ZZ: 60s
keine
Stapelverarbeitung

15 Schichten
ZZ: 60s
keine
Stapelverarbeitung

Workstation

U-cell-assembly
flexible line
no buffer: One Piece flow
1-4 employees

Central Electronic Plants Continental Business System


55

Continental AG

Material Flow

Value Stream Design


Implementation of Continuous Flow
Elect. monthly.
30-daily plan

30/60/90
forecast

PPS

order weekly

Supplier

Production
planning

Daily
order

Electronic:
Special
treatment

Customer
18 variants
Weekly
requirement
12.000
Customer tact
50s

weekly
daily
Daily Plan

SMD Side B
SMD-Line
1,5

SMD Side A
FIFO

2-shifts
CT= 8.5mins
PT= 37s
ST=15min
Reliability
=85%

1,5
2-shifts
CT=8mins
PT =41s
ST =15min
Reliability
=80%

WT + NVA

PT(VA)

FIFO

Preassembly.
2
2-shifts
CT=8mins
PT=40s
ST=20min
Reliability
= 80%

WT + NVA

Continental AG

Assembly

2-shifts
CT=6.5mins
PT=42s
ST=15min
Reliability
= 95%
WT + NVA

PT(VA)
PT(VA)
CT: Cycle time PT: Process time (value add time)

Central Electronic Plants Continental Business System


56

Testing
FIFO

Daily delivery
schedule

WT + NVA

2-shifts
2.4mins
PT=48s
ST=0min
Reliability
=100%

Testing
FIFO

1
2-shifts
CT=4.2mins
PT=42s
ST=3min
Reliability
=95%

WT + NVA

PT(VA)
PT(VA)
PT(VA)
ST: Setup time; TT: Throughput time; WT: Wait Time

FIFO

Shipping

5200
3200

WT

TT= WT + NVA

Total PT(VA)

Value Stream Design


Five steps of drawing the Future State Map
I

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Preparing to create the


Future State:
IV.1
Check ALL
Cycle Times
According to
Customer Takt

IV.2
Check where to
implement
Continuous
Flow

Central Electronic Plants Continental Business System


57

Continental AG

IV.3
Check
application of
FIFO Lanes &
Supermarket

IV.4
Reduce
Scheduling to
One Process
ONLY
(Pacemaker)

IV.5
Identify Other
Areas for
Improvement

Value stream design FIFO Lanes


To reduce and control inventories, consider creating a FIFO Lane
FIFO (First In First Out)
Consider a FIFO lane when:
There is a large difference in cycle time and the supplying machine can produce another
product

Possible Impacts

Preassembly.

3-shifts
CT=8mins
PT=15s
ST=20min
Reliability
= 80%

Testing.

FIFO

3-shifts
CT=6.5mins
PT=42s
ST=15min
Reliability
= 95%

FIFO Lane must be sufficient to cover:


Changeover
Other delays

Downtime TPM (MTTR)


Setup time
Machine reliability (OEE)
Reworking (FPY)
Capacity for other streams /
references
Lot size working time / bin
working time (max. Qty)
Information flow

Central Electronic Plants Continental Business System


58

Continental AG

Transport time

Value stream design Supermarket


Use Supermarket /Pull Systems to control production where continuous flow is not
possible.
Some processes are designed to serve multiple product families.
Processes are operated with different shift models.
Some processes are far away and shipping one piece at a time is not realistic
Some processes have too much lead time or are too unreliable to couple directly to
other processes in a continuous flow
Production KANBAN

Withdrawal KANBAN

Supplying
Process

Customer

Process

Product

Product

SUPERMARKET

Central Electronic Plants Continental Business System


59

Continental AG

1. Customer Process goes to


supermarket and withdraws what it
needs when it needs it.
2. Supplying Process produces to
replenish what was withdrawn.

Value Stream Design


Further Optimization Supplier management
Elect. monthly.
30-daily plan
order weekly

Supplier

30/60/90
forecast

Production
planning
PPS

Daily
order

Electronic:
Special
treatment

Customer
18 variants
Weekly
requirement
12.000
Customer tact
50s

weekly

Materials availability problems


=> installation supplier Kanban
Daily plan

supermarket/kanban
SMD Side A

SMD
Side B
SMD-Line
1,5

FIFO

2-shifts
CT= 8.5mins
PT= 37s
ST=15min
Reliability
=85%

1,5
2-shifts
CT=8mins
PT =41s
ST =15min
Reliability
=80%

WT + NVA

PT(VA)

FIFO

Preassembly.
2
2-shifts
CT=8mins
PT=40s
ST=20min
Reliability
= 80%

WT + NVA

Continental AG

FIFO

WT + NVA

Assembly
3

2-shifts
CT=6.5mins
PT=42s
ST=15min
Reliability
= 95%

PT(VA)
PT(VA)
CT: Cycle time PT: Process time (value add time)

Central Electronic Plants Continental Business System


60

Testing
FIFO

Daily delivery
schedule

WT + NVA

2-shifts
2.4mins
PT=48s
ST=0min
Reliability
=100%

Testing
FIFO

Shipping

1
2-shifts
CT=4.2mins
PT=42s
ST=3min
Reliability
=95%

WT + NVA

PT(VA)
PT(VA)
PT(VA)
ST: Setup time; TT: Throughput time; WT: Wait Time

WT

TT= WT + NVA
Total PT(VA)

Value Stream Design


Five steps of drawing the Future State Map
I

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Preparing to create the


Future State:
IV.1
Check ALL
Cycle Times
According to
Customer Takt

IV.2
Check where to
implement
Continuous
Flow

Central Electronic Plants Continental Business System


61

Continental AG

IV.3
Check
application of
Supermarket

IV.4
Reduce
Scheduling to
One Process
ONLY
(Pacemaker)

IV.5
Identify Other
Areas for
Improvement

Guidelines for a Lean Value Stream:


Pacemaker Process
4. Try to send the customer schedule to only one production process
By using supermarket pull systems, typically only one point the Pacemaker Process
In your door-to-door value stream needs to be scheduled
How you control production at this process sets the pace for all upstream processes
Note that material transfers from the Pacemaker Process downstream to finished
goods need to occur as a flow!

dule

Process

S c he

Process

Customer
FLOW

Process

Process

Central Electronic Plants Continental Business System


62

Continental AG

Process

FIFO

Customer

Value Stream Design


Five steps of drawing the Future State Map
I

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Preparing to create the


Future State:
IV.1
Check ALL
Cycle Times
According to
Customer Takt

IV.2
Check where to
implement
Continuous
Flow

Central Electronic Plants Continental Business System


63

Continental AG

IV.3
Check
application of
Supermarket

IV.4
Reduce
Scheduling to
One Process
ONLY
(Pacemaker)

IV.5
Identify Other
Areas for
Improvement

Other Areas for Improvement


Elect. monthly.
30-daily plan
order weekly

Supplier

Production
planning
PPS

30/60/90
forecast

Daily
order

Electronic

Customer
18 variants
Weekly
requirement
12.000

Small reliability
=> totally Productive maintenance
weekly

Customer tact
50s

Long Cycle times & Changeover times


=> SMED - Single Minutes Exchange of Die

daily

Daily plan

SMD Side B
SMD-Line
1,5

SMD Side A
FIFO

1,5

max
3-shifts8.5mins 70
PT=37s
ST=15min
Reliability
=85%
WT + NVA

PT(VA)

3-shifts
CT=8mins
PT =41s
ST =15min
Reliability
=80%
PT(VA)

Preassembly.
2

FIFO

max
70

3-shifts
CT=8mins
PT=40s
ST=20min
Reliability
= 80%

WT + NVA

Testing
FIFO

max
140

Continental AG

525

WT + NVA

CT: Cycle time PT: Process time (value add time)

64

Assembly

3-shifts
3-shifts
CT=6.5mins
CT=2.4mins
PT=42s
PT=48s
ST=15min
ST=0min
Reliability
Reliability
= 95% WT + NVA =100%

PT(VA)

Central Electronic Plants Continental Business System

Daily delivery
schedule

PT(VA)

PT(VA)

Testing
FIFO

max
5

1
3-shifts
CT=4.2mins
PT=60s
ST=3min
Reliability
=95%

WT + NVA

PT(VA)

ST: Setup time; TT: Throughput time; WT: Wait Time

Shipping
FIFO

WT

TT= WT + NVA
Total= PT(VA)

Workshop: Design Phase


Development of the future Value Stream Map (VSD)
Improvement of the current material and information flow eliminating the identified waste
along the value stream
Approach:
Adjust all process steps to the customer requirements (Customer takt)
Balance Cycle Time, Process Time, OEE per workstation
Eliminate push by using flow or pull principles
Eliminate unnecessary planning steps
Define the method for handling raw materials and finished products
....
Target:
Calculation of the new Throughput time, Cycle time, Process time
Common understanding of obvious problems
Elimination of waste and implementation of all possible improvements using CBS methods
and tools

Central Electronic Plants Continental Business System


65

Continental AG

Value Stream Mapping

1. Mapping Phase

II
Selection
of
Product
Family

3. Implementation
Phase

2. Design Phase

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

VI

V
Design of
future
state

Action
Plan

Review

Completing a Current State Map and a Future State Map is of no value


(waste) without an Action Plan to implement and a Review Plan to
ensure the Action Plan is being implemented

Central Electronic Plants Continental Business System


66

Continental AG

Value Stream Implementation


Five steps of drawing the Future State Map
I

II
Selection
of
Product
Family

III
Selection
of
Value
Stream
Leader

IV
Mapping
of
current
state

Design of
future
state

Future State Map


Steps to reach the future state
Responsible Persons
Schedule

Central Electronic Plants Continental Business System


67

Continental AG

VI

V
Action
Plan

Review

Action Plan
How do you eat an elephant?
The Future State Value Stream cannot be implemented overnight and in one go.
Consider the loops in the Future State Value Stream in planning implementation.
Plan the actions, identify milestones, define due dates and assign responsibilities
Actions can be categorized as follows:
Completion within 30 days
Completion within 90 days
Completion longer than 90 days
Documentation is a must!
Use the Project Charter
Use the A3/A4 Report
https://workspace1.conti.de/content/00009902/default.aspx
This link will take you to the Project Platform for the latest version of the Charter and A3 forms

Central Electronic Plants Continental Business System


68

Continental AG

Project Charter - One Pager

Central Electronic Plants Continental Business System


69 / CBS by CEP / Project review training Continental Automotive GmbH

Action Plan (Sample Template)


Action List

Milestone

Due Date

Responsible

Phase 1 (Completion within 30 days)

Phase 2 (Completion within 90 days)

Phase 3 (Completion longer than 90 days)


Central Electronic Plants Continental Business System
70

Continental AG

h is
c
i
h
ur
w
o
e
y
lat ly in
p
Tem ctive
n
fe
la
f
P
e
ion used tion
t
c
A
a
nd n and ganiz
a
or
Use know
ll
we

Example Roadmap
Nov.

Dez.

Jan.

Feb.

Mrz

Apr.

Mai

Ex
a

Kick off
VSM Workshop
Dimension/
Supermarket/ Kanban

mp
le

Collecting data and


installation of Kanban in
the housing area
Final release of concept

Start of implementation

Layout planning,
Kanban cards

Continuous
Improvement

Training of employees
Kanban Board & cards
Kick Off Roll out
Final presentation pilot
implementation
Roll out planning

Roll out

Activities plant xyz

Central Electronic Plants Continental Business System


71

Continental AG

Workshop


2 Project description /Background

6 Future state, counter measures, savings/benefits

3 Problem statement / Current situation

s://workspace1.conti.de/content/00009902/default.aspx

4 Goal statement / Objective

7 Confirmation of effect

5 Root cause analysis

8 Follow up actions, read across


....

Central Electronic Plants Continental Business System

Summary
Value stream design helps to see the material and information flow in order to
understand and holistically optimize the complete process

Guideline for a lean value stream:


1.

Produce according to customer takt

2.

Establish continuous flow everywhere is possible

3.

Use supermarket - pull where continuous flow is not possible

4.

Try to make production planning only at one process within the value stream

5.

Release production orders at the pacemaker process

6.

Flow where you can, Pull where you must

Central Electronic Plants Continental Business System


73