Beruflich Dokumente
Kultur Dokumente
Probabilistic PERT
PERT Assumptions
Assumption 1
A critical path can be determined by using the mean
completion times for the activities.
The project mean completion time is determined solely
by the completion time of the activities on the critical
path.
Assumption 2
There are enough activities on the critical path so that
the distribution of the overall project completion time
can be approximated by the normal distribution.
Assumption 3
The time to complete one activity is independent of the
completion time of any other activity.
(120-76)/6
(7.33)2
90
15
5
20
21
25
14
28
30
45
7.33
1.00
0.33
3.00
1.00
2.33
2.00
1.33
4.67
3.67
53.73
1.00
0.11
9.00
1.00
5.43
4.00
1.77
21.81
13.47
85.66
2 85.66
9.255
2.
3.
X values, xL, the lower confidnce limit, and xU, the upper
confidnce limit, such that P(X<xL) = .025 and P(X>xU) = .025
4.
5.
Excel Solutions
NORMDIST(194, 194, 9.255, TRUE)
NORMINV(.025, 194, 9.255)
NORMINV(.975, 194, 9.255)
NORMDIST(180, 194, 9.255, TRUE)
Enter a, m, b instead of
Call Solver
Click Solve
Go to PERT OUTPUT worksheet
Call Solver
Click Solve
To get a cumulative
probability, enter
a number here
Analysis of Additional
Sales Personnel Training
Sales personnel training (Activity H) is
not a critical activity.
Thus any reduction in Activity H will not affect
the critical path and hence the distribution of
the project completion time.
Analysis of Additional
Technical Staff Training
Technical Staff Training (Activity F) is on
the critical path so this option should be
analyzed.
One of three things will happen:
The project will finish within 180 days:
Klonepalm will net an additional $1 million
P(X >
The Calculations
.065192
.676398
X $0
.729561
$270,559
X $400000
$159,152
$ 65,192
X $1000000
Additional
Training
= 189
= 9.0185
.159152
$291,824
.111287
.258410
$
Total = $335,751
Total = $450,976
Review
3-Time Estimate Approach for PERT
Each activity has a Beta distribution
Calculation of Mean of each activity
Calculation Variance and Standard Deviation
for each activity