Beruflich Dokumente
Kultur Dokumente
Awareness Session
Contracts Management
descon.com
Contents
1. Introduction To Contracts
2. Role Of Contracts Management
3. Potential Claim Clauses
4. EPC Contracts Administration
5. Effective Contracts Administration- Engineering
Perspective
6. Comparative Analysis
INTRODUCTION TO
CONTRACTS
What is a Contract ?
execution
obligations of the parties
Considerations
Fair
and
SITUATION
ethical
approach
WIN-WIN
Types of Contract
Contract types vary according to:
responsibility
assumed by the contractor for the execution of
contract; and
offered
to
the
or
Price competition
Cost analysis & risk assessment
Type and complexity of the requirement
Urgency of the requirement
Period of performance or length of project /
production run
Concurrent contracts
Extent and nature of proposed subcontracting
Contractor
receives
instruction
to
bidder
(ITB)
documents
Contractor
submits
bid
stating
exceptions
/alternatives
Negotiations
on
submitted
bid
and
proposed
exceptions
Finalize
contract
documents
to
signatures
be
ready
for
Frequently used
Carries risk exposure for parties
Sometimes justified when owner not in position to
make official award but working on schedule crunch
ROLE OF
CONTRACTS
MANAGEMENT
Sub-contract
and/or
procurement
contract
administration
Claims
(cost
&
identification,
time)
management,
substantiation,
including
documentation,
Support
dispute
resolution
processes,
including
vendors
Provide
assistance
to
Project
Management
in
contracts
20 %
Align risk strategy with contract strategy
20%
Continued.
3
40 %
Providing cost advise and implement contract variations and
compensations
Maintaining that contract conditions and specifications are
adhered to
20%
POTENTIAL CLAIM
CLAUSES
Liquidated Damages
Variation
Insurance
Force Majeure
Suspension and Termination
Warranty & Extended Warranty
Confidentiality and IP rights
Dispute Resolution
Contractual Risks
MITIGATION
Problematic Areas
Owner
ordered
changes
without
agreed
upon
cost/time adjustments
Delays
performance,
equipment
materials
delivery
Loopholes in Contracts
Continued
EPC CONTRACTS
ADMINISTRATION
EPC
contract
is
designed
to
satisfy
the
lenders
conditions
of
contract
are
not
suitable
under
following circumstances;
Insufficient
Construction
EFFECTIVE
CONTRACTS
ADMINISTRATIONENGINEERING
PERSPECTIVE
Differing interpretations
Excessive change orders as a result of addition ,
deletion or modification of work
The
Contractor
accepts
total
responsibility
for
having
Continued
Scrutiny and Sufficiency of engineering data:
Continued
3. Adjustment of Errors
It allows you to correct errors and omissions in lump sum
rates and prices contained in a tender and adjustments for
changes or data subsequently revised and provided by the
employer.
4. Fixing Employers Responsibilities
The employer shall be responsible for the correctness of the
following portions of the employers requirements and of the
following data and information provided by (or on behalf of)
the employer:
Portions, data and information which are stated in the
contract as being immutable or the responsibility of the
employer,
Definitions of intended purposes of the works or any parts
thereof,
Criteria for the testing and performance of the completed
works,
Portions, data and information which cannot be verified by
COMPARATIVE
ANALYSIS
Balanced Clause
Recommended
Approach
Pre-Bid Data :
CONTRACTOR acknowledges that it has
examined with all due diligence the
PROJECT DOCUMENTS made available to
CONTRACTOR prior to the EFFECTIVE DATE and
confirms that they are sufficient and adequate
for the intended purpose of the PROJECT, and
that they contain no errors, faults,
omissions, or discrepancies that would
result in any VARIATION to the WORKS.
Failure of CONTRACTOR to so notify
COMPANY prior to EFFECTIVE DATE shall not
relieve
CONTRACTOR
of
any
of
its
responsibilities nor shall its liabilities be
diminished under this AGREEMENT.
Pre-Bid Measures:
1) Thorough understanding of
the scope of work and
prepare
a
list
of
information,
in
coordination
with
the
relevant departments, that
may be required for such
kind of project.
Post-Bid Data:
COMPANY may provide or cause to be provided
to CONTRACTOR after the EFFECTIVE DATE,
supplementary data in addition to the
information that is contained in the EXHIBITS.
COMPANY may also supply further information
as may become reasonably available as
well as information the at CONTRACTOR may
reasonably request. For the avoidance of
doubt,
the
entirety
of
any
such
information provided to CONTRACTOR
under
this
Sub-Article
shall
be
considered as part of normal engineering
development, the incorporation of such
information by CONTRACTOR into its WORKS
for the PROJECT being fully contemplated and
covered within the LUMP SUM PRICE and
The
designers
who
expressed
and
requirements,
SCOPE
OF
with
implied
included
CONTRACTOR
responsible
the
design
SPECIFICATIONS
WORK
AGREEMENT.
financially
comply
in
shall
design
shall
be
requirements,
prepared
by
SPECIFICATIONS
and
this
be
comply
with
good
engineering,
1) Try
to
Limit
2) Do
responsibility
data
provided
CONTRACTOR
the
COMPANY .
extent
applicable
or
which
take
of
is
basic
to
be
by
the
implemented
by
CONTRACTOR
for
COMPANY or not.
Implied
expressed purpose.
of
any
mistake
CONTRACTOR.
an
to
cap
not
specifications,
or
generalized terms.
any
prepared
for
design
Recommended
Approach
experienced
similar
Works.
attributable
The
3) Replace
intended
or
with
to
CONTRACTOR
error.
provided by the
Continued
Stringent Clause
Balanced Clause
/Associated Risks
CONTRACTOR
shall
immediately
upon receipt of all drawings and
specifications , verify and check the
correctness
thereof
and
shall
promptly notify COMPANY in
writing of any errors, omissions , or
discrepancies before commencing
any Works to which the drawings
and
specifications
including
improperly described Works where
such Works are clearly necessary to
carryout the intent thereof or
which is customarily performed
shall not relieve CONTRACTOR of
its obligations to perform such
omitted or improperly described
Works and such Works shall be
performed by CONTRACTOR as if
fully & correctly set forth and
described herein.
Recommended
Approach
1. Fix responsibility
2. Notify Promptly
3. Take indemnity
4. Keep Option to claim any
damage
Balanced Clause
/Associated Risks
The
Employer
shall
have
Recommended
Approach
made
on
subsurface
and
Pre-Bid Measures:
random test
would
be
inspect the
underground
Importance of Surveys
Stringent Clause
Recommended
Approach
deemed
contingencies
and
all
other
2. Importance of SITE ,
circumstances
which
may
affect
to
technical surveys.
performance
under
the
Contract,
the
to
have
extent
obtained
all
reasonably
foreseeable by an experienced
CONTRACTOR,
shared
COMPANY
CONTRACTOR
not
be
reasonable
foreseeable by an experienced
CONTRACTOR.
3. Specifications to be
with
the
all
documents
CONTRACTOR
to
submitted
COMPANY
for
by
its
efforts
reasonable
to
time
respond
unless
within
otherwise
respect
and
were
subject
to
Recommended
Approach
1. Fix time lines for
approvals
1. Importance of
deemed approval
necessary.
2. Follow up
Schedules
Stringent Clause
Balanced Clause
/Associated Risks
Recommended
Approach
1. Resist Acceptance of
such Clause
5%
from
CONTRACTORs
invoiced
2. COMPANY already
charging the
CONTRACTOR with
has
Liquidated Damages
complied
with
its
required
Retention Amount.
SCHEDULE
milestone.
Such
amount
be
can
retained
invoiced
by
3. As a last resort
negotiate on
obligation.
percentage.
Liquidated Damages
Stringent Clause
If
clause
[delay
Balanced Clause
/Associated Risks
Recommended
Approach
company
must
not
Parties should
clearly
and
unambiguously
agree
delay
those
liquidated
damages,
against
damages
at
the
law
that
within
their
the
EPC contract.
contractor
for
the
UNLIQUIDATED
DAMAGES
or
completion.
contractually
removed, It must
be done by very
Detailed
work specific