Beruflich Dokumente
Kultur Dokumente
OBJECTIVES
Production of steam at desired
parameters and purity
Protection of pressure parts from
corrosion, overheating, thermal
stresses etc
Prevention of furnace explosions
BOILER OPERATION
DIFFERENT PHASES
START UP PROCEDURES
Cold start
Hot start
CARE DURING NORMAL RUNNING
Load changes
Routine checks
OPERATION UNDER ABNORMAL CONDITIONS
SHUTDOWN PROCEDURES
To cold
To hot stand by
BOILER FILLING
All vent valves on feed line,
economiser,drum,headers and
m.s.line are kept open.
All drain and blow down valves are
kept closed.
Do not fill the water above the
boiling point.
Do not fill with excessive cold water.
If possible fill with water 100c above
boiler metal to avoid temp. stresses
BOILER FILLING
Open and close gauge glass cocks
and drains on the water column to
make sure that these connections
are unobstructed and free.
Fill till free jet of water comes out
through economiser vent and drum
vents.
Bring down level in drum to normal
by draining after closing
economiser vent.
STARTING DRAUGHT
SYSTEM
BOILER PURGING
CHECK THE FOLLOWING PURGE PERMISSIVES
ARE SATISFIED
BOILER PURGING
Satisfy purge
permissives
Give purge start
command
Purge on
indicationcomes
Purge complete
indication comes
LIGHTOIL FIRING
Open ignitor oil trip
valve
Open light oil trip
valve
Select light oil firing
in AB elevation
Ensure elevation
permissives
Start one pair of oil
guns
Start second pair of
oil guns
Check 3 out of 4 L.O.
guns are proven on
in timed sequence
DRAIN
TO
S.H.ATTEMPERATION
DRAIN
TO
S.H.ATTEMPERATION
F.C.V.
DRAIN
DRAIN
TO
H.P.HEATER
ECO
.
DRAIN
DRAIN
DRAIN
DRAIN
FEED REGULATING
STATION
DRAIN
ROUTINE CHECKS
Make a round of boiler to inspect
Flame condition/ stability
Pressure parts for leakage
Leakage in air/flue gas paths
Running auxiliaries for abnormal noise
vibration,high bearing temp. etc.
Maintain hourly log. Identify deviations
and take corrective actions
ROUTINE CHECKS
Compare unit operating parameters with
predicted readings.Any deviation should
be reasoned and corrected
Compare local instruments reading with
remote instruments once a day.Any
discrepancy to be corrected
Maintain feed water,steam quality
Ensure flow of sampling water is
maintained
Analyse F.G. through orsat apparatus
once a day
Check fineness of p.f.
ROUTINE CHECKS
Check pr.drop of F.G.,feed water temp before
and after economiser, steam temp at various
stages of S.H., metal temp. of S.H. and R.H.
Carry out soot blowing as and when required
Carry out soot blowing of A.H. once in a shift
Ensure no choking in bunkers
Maintain mill parameters
Empty the bunker if the mill is taken for long
shut down
Ensure satisfactory operation of slag
conveyors slag crushers,fly ash system
ROUTINE CHECKS
BOILER IS COOLED
Internally
Externally
By Radiation
NATURAL COOLING
On tripping of the boiler bring the
drum level to very high level and
stop feeding
After purging stop F.D.and I.D.fans
All the dampers in air and flue gas
path remain in open position
Start up vent in open position
Internal cooling takes place due to
circulation of water inside tubes
Top up water in drum when the
level recedes
NATURAL COOLING
External cooling takes place by
the air flow due to natural
draught effect which is at a slow
rate
Also cooled by radiation
When the pressure drops to
5kg/cm2 open the S.H.,R.H. vents
When the pressure drops to
2kg/cm2 open the drum vents
Natural cooling will take more
time
FORCED COOLING
On tripping of the boiler bring
the drum level to very high
level and stop feeding
After purging do not stop
F.D.and I.D.fans
Adjust air flow according to the
cooling rate desired
Ensure the saturated steam
temperature drop is not more
than 830C per hour
FORCED COOLING
Start up vent in open position
Internal cooling takes place
due to circulation of water
inside tubes
Top up water in drum when the
level recedes
External cooling takes place by
the air flow at a faster rate
according to air flow rate
Also cooled by radiation
FORCED COOLING
When the pressure drops to
5kg/cm2 open the S.H.,R.H.vents
When the pressure drops to
2kg/cm2 open the drum vents
Boiler will be cooled at a faster
rate in forced cooling
Not healthy for boiler as it
induces stresses in boiler tubes
Used only in emergencies
BOX UP
On tripping of the boiler bring the
drum level to very high level and stop
feeding
After purging stop F.D.and I.D.fans
Keep all the vents and drains
including start up vent in closed
condition
As such there will not be any circulation
and so no internal cooling
BOX UP
Cooling can be only through
radiation
Heat inside the boiler can be
retained for more time
Adopted for keeping the boiler
ready for hot start up on shut
down