Sie sind auf Seite 1von 91

PRESENTATION

PROJECT MANAGEMENT
Prepared / Presented by:
PROJECT CONTROL DIVISION Karthi

PROJECT CONTROL DIVISION

PROJECT MANAGEMENT

DISCIPLINES of PROJECT MANAGEMENT


CONTRACT MANAGEMENT

CONSTRUCTION MANAGEMENT

RISK MANAGEMENT

FINANCE MANAGEMENT

HUMAN RESOURCES MANAGEMENT

SAFETY MANAGEMENT

LEGAL MANAGEMENT

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
PRESENTATION

CONTRACT MANAGEMENT

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT

TAISEI CORPORATION

CONTENT OF PRESENTATION

Content of Presentation
Part

Name

I.

Introduction of Contract Management

II.

FIDIC based Contracts

III.

Contract Administration

IV.

Claims and Counter Claims

Conclusion of Presentation
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT

TAISEI CORPORATION

Part I: INTRODUCTION

Part I: Introduction of Contract Management


Chapter

Name

1.

Merit of Contract Management

2.

Contract Management Participants

3.

General Types of Contracts

Back to Content of Presentation


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part I: INTRODUCTION
MERIT OF CONTRACT MANAGEMENT

TAISEI CORPORATION

A, Contract Management is PROCESS of managing:


Contracts
Deadlines
Deliveries

Customer satisfaction

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part I: INTRODUCTION
MERIT OF CONTRACT MANAGEMENT

TAISEI CORPORATION

B, Phases of the Contract Management from time point of view:


Pre-award Contract Management involving
preparatory activities with adequate investigations to cover all aspect:
1. that Influence design

3. Study possible technological


alternatives

2. to Minimize uncertainties that


may arise at the time of execution

4. Preparation of detail designs,


construction drawings and estimates

based on above CONTRACT DOCUMENTS are PREPARED

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part I: INTRODUCTION
MERIT OF CONTRACT MANAGEMENT

TAISEI CORPORATION

B, Phases of the Contract Management from time point of view:


Post-award Contract Management
Contractor performs during project execution => Main Topic of Presentation
to fulfill Contractual obligations to Customer, the Contractor need:
To be equipped with latest technology

Proper mobilization

To have sufficient skilled personnel

Efficient schedule control

Expect unforeseeable events and prepare countermeasures

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part I: INTRODUCTION
MERIT OF CONTRACT MANAGEMENT

TAISEI CORPORATION

C, Contract Management influences Companys:


Budget
Customer Service
Operation

Public Image

D, Therefore through proper Contract Management, Company can have


the following benefits:
increase in production and reduced inventory
improvement in product quality and customer satisfaction
reduction in purchasing costs, scheduling conflicts and manufacturing waste
transformation of fixed contract costs into cash that goes directly to the bottom line

Back to Content of Part I


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part I: INTRODUCTION
CONTRACT MANAGEMENT PARTICIPANTS

TAISEI CORPORATION

CONTRACT MANAGEMENT Organization Chart


Project Manager

Administration Manager

Project Control Manager

Construction Manager

Accountant

Contract Engineers

Site Engineers

Quantity Surveyor

Geologists

Schedule Controller
Document Controller

Passive Members

Active Members
Back to Content of Part I
PROJECT CONTROL DIVISION

Passive Members

CONTRACT MANAGEMENT
Part I: INTRODUCTION
GENERAL TYPES OF CONTRACTS

TAISEI CORPORATION

General Types of CONTRACTS


International Contracts

Domestic Contracts

Contract parties in General:


Employer Contractor
Employer Designer/Consultant
Contractor Contractor
(Joint Venture)
Contractor Subcontractor
Contractor Designer/Consultant
Contractor Supplier

Types of Contract in General:


Lump Sum Contract
Item Rate Contract / Remeasurement Contract
Cost plus percentage contracts
Cost plus fixed fee contracts
Maximum Price Contracts
Turnkey Contracts

Back to Content of Part I


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT

TAISEI CORPORATION

Part II: FIDIC based Contracts

Part II: FIDIC based Contracts


Chapter

Name

1.

Background & History

2.

FIDIC Forms of Contracts and its Concepts

3.

FIDIC First Edition 1999 Red Book

Back to Content of Presentation


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
Background & History

TAISEI CORPORATION

FIDIC Background & History:


FIDIC acronym for Federation Internationale des Ingenieurs-Conseils
(International federation of Consulting Engineers).
founded in Ghent, Belgium in 1913 by the national associations of consulting
engineers of Belgium, France and Switzerland
FIDIC has its Secretariat now in Lausanne, Switzerland
one of the first 5 committees established in 1913 was Contract Documents
Committee having the following terms of reference:

a, To monitor Contract documents of interest to Consulting Engineers


regarding:

Construction of objects or works

Maintenance of installation in operation

Erection and installation of works

Supply of materials

b, To inform contractors, suppliers and officials concerning contract documents


recommended by FIDIC

Back to Content of Part II


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


A, Conditions of Contract for Works of Civil Engineering Construction
For Building And Engineering Works
Designed By The Employer
(Red Book)

Edition:

1.

First Edition in 1957, presently fourth edition from 1987 reprinted with
amendments in 1988 and 1992

Basic Feature: Design is provided by the Employer


Type of Contract: Item Rate Contract / Re-measurement Contract
Note: Fourth Edition reprinted with amendments from the year 1992 was used in
our Sitina Tunel project in Slovakia

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:

B, Conditions of Contract for Electrical and Mechanical Works including


erection on site (Yellow Book)
Edition: First Edition in 1963, presently third edition from 1987
Basic Feature: Design is Contractors responsibility
Type of Contract: Item Rate Contract / Re-measurement Contract
Note: Third edition was used in our Sitina Tunel project in Slovakia

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:

C, Conditions of Contract for Design-Build and Turnkey (Orange Book)


Edition: First Edition in 1995
Basic Feature: Turnkey type of Contract
=> Engineering - Procurement Construction is Contractors responsibility
Type of Contract: Lump Sum Contract
Note: in 1999 replaced by new FIDIC concept => Silver book (explained later)

Common feature of the above mentioned Forms of Contracts


(i.e. RED, YELLOW and ORANGE book) is:
Contract parties: Employer Main Contractor

PROJECT CONTROL DIVISION MIDDLE EAST BRANCH

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


D, Conditions of Sub-contract for Works of Civil Engineering construction
Edition: First Edition in 1994
Basic Feature:
- coming from the RED Book concept, therefore it is most suitable for Civil
Engineering Subcontract Works
- after adjustment, it is possible to use, even if the Main Contractor follows YELLOW
book
- the Main Contractors responsibilities covers with the Subcontractors
responsibilities within his scope of Works
Type of Contract: depends upon the circumstances
Contract parties: Contractor Subcontractor
Note: First Edition was used in our Sitina Tunel project in Slovakia

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


E, Client/Consultant model services agreement (White Book)
Edition: Third Edition from 1998
Basic Feature: General use for the purpose of pre-investment and feasibility
studies, design and administration of contract and project management
Type of Contract: Lump Sum Contract (Schedule of Payments)
Contract parties:
Employer Designer/Consultant
Contractor Designer/Consultant

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


F, Sub-Consultancy Agreement
Edition: First Edition in 1992
Basic Feature:
- This Form of Agreement relates to the Client/Consultant model services
agreement (White book)
- It is Sub-contract Form for the Client/Consultant model services agreement
Type of Contract: Lump Sum Contract (depends on the Client/Consultant Form of
Contract)
Contract parties: Main Designer/Consultant Sub-Designer/Consultant

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


G, Joint Venture (Consortium) Agreement
Edition: First Edition in 1992
Basic Feature:
- can be used irrespective of Form of Contract
Type of Contract:
Contract parties: between Main Contractors, if its Join Venture
Note: Some conditions are used in our JV Agreement

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


H, Tendering Procedure
Edition: First Edition in 1982, Second Edition 1994
Basic Feature:
- useful for the Employer/Engineer/Consultant within the process of Tender
preparation
- possible to use by the Main Contractor

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


J, FIDIC 1999 Four NEW Forms of Contracts

Conditions of Contract for Construction


For Building and Engineering Works
Designed By The Employer
(Red Book)
Edition: New concept following the Fourth Edition of Red book, 1999
Basic Feature: Design by Employer
Type of Contract: Item Rate Contract / Re-measurement Contract
Differences compared to Fourth Edition of RED Book:
- position of the Engineer Fourth Edition independent 1999 Edition fair determination
- different structure Fourth Edition - has 72 Clauses 1999 edition has 20 Clauses

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


J, FIDIC 1999 Four NEW Forms of Contracts

Conditions of Contract for Plant and Design-Build


for Electrical and Mechanical Plant, and for Building and Engineering Works
(Yellow Book)
Edition: New concept following the Third Edition of Yellow book
Basic Feature: Design by Contractor
Type of Contract: Lump Sum Contract
Differences compared to Third edition of YELLOW Book:
-position of the Engineer -Fourth Edition independent 1999 Edition fair
determination
- different structure - Fourth Edition - has 72 Clauses 1999 Edition has 20
Clauses

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


J, FIDIC 1999 Four NEW Forms of Contracts

Conditions of Contract for EPC/Turnkey Projects


(Silver Book)
Edition: First Edition of Silver book
Basic Feature: Engineering, Procure, Construct is Contractors responsibilities
Type of Contract: Turnkey Contracts (similar to Lump Sum Contract)
Note: Successor of Orange book

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:


J, FIDIC 1999 Four NEW Forms of Contracts
First Edition of the New Green Book FIDIC 1999
Edition: First Edition
Basic Feature: Short Form of Contract Agreement
Content:
- General Conditions
- Rules for Adjudication
- Notes for Guidance

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

FIDIC Forms of Contracts and its Concepts:

Common feature of the mentioned Forms of Contracts


(i.e. RED, YELLOW, ORANGE, Subcontract Conditions and WHITE book) is:
Each Form of Contract contain Two Main Parts:
Part I Standard Conditions
Part II Conditions of particular application / Special conditions (in Yellow book)
Adjusting the Standard conditions considering the local conditions

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

Aspects to consider when selecting suitable FIDIC Form of Contract:

Whereas there are so many FIDIC Forms of Contract, developed for


different conditions, the Promoter (Employer or Owner) of the project
should consider following aspects while selecting appropriate form:
1) The allocation of the essential FUNCTIONS found in a construction or
engineering project and in particular the design function
2) The allocation of the RISKS inherent in the projects
3) The allocation of the MANAGEMENT role
4) The method and timing of REMUNERATION for the Contractor

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

1) Allocation of FUNCTIONS:
The following functions are allocated to certain parties:
Promoter/Employer

Engineer
Adjudicator

Financier

Designer

Self financing
A simple lender
A lender in BuildTransfer
A lender in BuildOwn- Transfer (BOT)
A lender in BuildOwn-operate-transfer
(BOOT)
A lender in BuildOwn-operate (BOO)
A lender in Build-Rent-Transfer (BRT)
BLT in leasing rather than renting

Sketch design
Preliminary
design
Final design

PROJECT CONTROL DIVISION

Contractor

Subcontractor,
supplier and
manufacturer

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

2) Allocation of RISK:
Allocation of Risk to party:
-

Which party can BEST FORESEE the risk?

Which party can BEST CONTROL the risk?

Which party can BEST BEAR the risk?

Which party MOST BENEFIT or SUFFER if the risk eventuates?

Details pertaining to RISK are in Presentation RISK MANAGEMENT.

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

2) Allocation of RISK:
FIDIC RISK DIAGRAM
RED BOOK

YELLOW BOOK

Increased Employer Risk


Increased Design Control
Greater Design Certainty

SILVER BOOK

Increased Contractors Risk


Increased Project Price
Greater Time & Cost Certainty

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC Forms of Contracts and its Concepts

TAISEI CORPORATION

3) Allocation of MANAGEMENT ROLE


4) Allocation METHOD and TIMING of REMUNERATION:
Allocation of Management Role & Method and Timing of Remuneration
is closely linked with the RISK sharing.
From the point of RISK sharing. i.e. RISK accepted by the
Promoter/Employer, there are the following categories of contracts:

(a) cost-reimbursable contracts


(b)re-measurement contracts based on unit rates and
prices
(c) lump sum contracts
Back to Content of Part II
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

FIDIC
First Edition
Edition 1999
1999 Red
Red Book:
Book:
FIDIC First
Documents forming the Contract:
Document

Purpose

Priority

Bid

Contractor Tender offer/price


proposal

Pre Tender Correspondences


including addendums

Clarification within the Tender period

Letter of Acceptance

Employer send to successful bidder

Contract Agreement

Agreement between Employer /


Contractor

General Conditions of Contract

Standard FIDIC Form of Red book

Special Conditions of Contract

Adjustments to Local conditions

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

FIDIC First Edition 1999 Red Book:

Documents forming the Contract:


Document

Purpose

General Technical Specifications

Standard specification for particular


type of project

Special Technical Specifications

Adjustments to Local conditions

Drawings

Provided by the Employer

BOQ

Items, Description of Items,


Estimated Quantity priced by the
Contractor

Any other documents forming


part of the contract

Any other document provided by the


Employer along with the Tender
Document such as Geological
reports, Environmental report, etc.

PROJECT CONTROL DIVISION

Priority
6

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

FIDIC First Edition 1999 Red Book:


Contractual obligations
Contractors obligation

Engineer's obligation

Employer's obligations

Two main categories


1, Coming from AGREEMENT
between parties
(as specified in the
CONTRACT CONDITION)

2, The obligations which


apply under APPLICABLE
LAW of Contract

Note: this second category extends in legal terms beyond the Contractors
obligations under the Contract with the employer and in time beyond the
completion of that contract.
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

FIDIC First Edition 1999 Red Book:


Contractual obligations
Contractors obligation

Engineer's obligation

Employer's obligations

MAIN AREAS:
1. CONSTRUCTION & COMPLETION: with DUE DILIGENCE / WITHIN
TIME
2. MATERIAL, PLANT & WORKMANSHIP according to CONTRACT/
INSTRUCTION
3. Provision of SECURITIES (Bank guarantees/Bonds), INDEMNITIES
and INSURANCES
4. Provision of INFORMATION required for EXECUTION / COMPLETION
ALERTING the Employer => IMPORTANT EVENTS / COST
INCREASE / TIME EXTENTION
5. Performance of ADMNINISTRATIVE & other FUNCTIONS
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

FIDIC First Edition 1999 Red Book:


Contractual obligations
Contractors obligation

Engineer's obligation

Employer's obligations

In STAGES:

1st

2nd

Tendering Stage

LETTER OF
ACCEPTANCE
SUBSTANCIAL
COMPLETION of
WORKS

PROJECT CONTROL DIVISION

3rd
AFTER
SUBSTANCIAL
COMPLETION of
WORKS

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

1st - Tendering Stage


Contractors Contractual obligations
Clause

Description of event

Time schedule

Inspect the Site


4.10

Tendering period

Inspect any information


Satisfy himself as to form and nature of the Site
Interpret the data provided by the Employer
Base tender on the data
4.11

Satisfy himself as to correctness and sufficiency of


the tender and of the rates and prices

13.1

Consider the provision in Part II regarding increase


or decrease of cost

Price
Adjustment

Tender Submission, Analyses and Decision on Award


18.1

Agree general terms of insurance


PROJECT CONTROL DIVISION

Insurance

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

1st- Tendering Stage


Contractors Other obligations
Arising from Technical specifications and/or other documents:
We have to pay attention to other documents as well.
Contract Negotiations:
Always there will be a meeting between the Employer and the
Contractor prior to sign the agreement.
The Contractor must carefully put few conditions such as possession of
site, permission from third parties etc.

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
TAISEI CORPORATION
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book
2nd - LETTER OF ACCEPTANCE SUBSTANCIAL COMPLETION of WORKS
Contractors Contractual obligations
Clause Description of event

Time schedule

Issue of Letter of Acceptance


Initiating Mobilization formalities
Finalizing commitments with Subcontractors and
Suppliers
4.2

Provide security for proper Performance

Performance Security

14.1(d) Provide breakdown for each of Lump Sum items


(The Contract Price)
8.3

Submit Construction schedule (Programme)

14.4

Schedule of Payment - Submit Cash flow

Up to 28 days

Issue of Notice to Commence


18.1

Provide evidence prior to the start of work at the Site General


that required Insurance have been effected
Requirement
for Insurances
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

2nd - LETTER OF ACCEPTANCE SUBSTANCIAL COMPLETION of WORKS


Contractors Contractual obligations
Clause

Description of event

Time schedule

Commencement Date
8.1

Commence the works as soon as reasonably


possible (Commencement of Works)

18.1

General Requirement for Insurances - Provide


Insurance policy

4.1

Carry out Design (to the extend of Contract)


Execute and complete the Works

9.1

Test on Completion Contractors Obligations

10.2

Notice of Substantial Completion - Written


14 days before
undertaking to Finish Outstanding Works within Taking Over Cert.
issuance
Defect Liability Period
Issue of Taking Over Certificate
PROJECT CONTROL DIVISION

Contractors General
Obligations

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

AFTER SUBSTANCIAL COMPLETION of WORKS


Contractors Contractual obligations
Clause Description of event

Time schedule

Issue of Taking Over Certificate = Substantial Completion of Works


4.23

Clear away site and leave clean

14.10

Submit Statement at completion

Within 84 days

End of Defect Liability Period


11.1

Completion of Outstanding Work and


Remedying Defects

On or before the
expiry of the Defects
Notification Period

Defect Liability Certificate


14.11

Submit Draft Final Statement /


Submit Final Statement

14.12

Give Written Discharge

Within 56 days

Final Certificate
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

FIDIC 4th Edition 1987 Red Book:


Contractual obligations
Contractors obligation

Engineer's obligation

Employer's obligations

Two main categories

1, The Engineer as DESIGNER

2, Engineers role in
PRE-CONTRACT and POSTCONTRACT

ENGINEERS DUTIES AND AUTHORITIES:


PROACTIVE DUTIES

REACTIVE DUTIES

PASSIVE DUTIES

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

FIDIC 4th Edition 1987 Red Book:


Contractual obligations
Contractors obligation

Engineer's obligation

Employer's obligations

In principle, most of the Employers obligations are very closely


associated with the Engineers obligations.
All the payment as certified by the engineer shall be made by the
Employer.

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

CLAUSES referring to COMPLETION:


Clause
CLAUSE Title
1.1.3.2

Commencement date

3.3

Supplementary Drawing and Instruction

4.1

Contractors General Responsibilities

4.11

Sufficiency of the Accepted Contract Amount

3.3

Instructions of The Engineer

8.3

Programme to be submitted

8.3

Revised Programme

3.1(c)

Contractor not relieved of duties and responsibilities

6.8

Contractors Superintendence

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

CLAUSES referring to COMPLETION :


Clause
CLAUSE Title
4.8, 4.18,
4.22 & 6.7

Safety Procedures, Protection of Environment, Security of the


Site and Health and Safety

18.2

Insurance of works and Contractors Equipment

17.1

Indemnities

18.3

Insurance against Injury to Persons and Damage to property

18.3(d)

Exceptions

1.13

Compliance with Laws

6.4

Labour Laws

4.14

Avoidance of Interference

8.2

Time for completion

8.4

Extension of Time for Completion

8.7

Delay Damages
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

CLAUSES referring to COMPLETION:


Clause
CLAUSE Title
10.2

Reduction of Liquidated damages

10.1& 10.2

Taking-Over of the Works and Sections / Taking Over of Parts


of the Works

11.1

Completion of Outstanding Work and Remedying Defects

12.4

Omissions

14.9

Payment of Retention Money

14.10

Statement at Completion

11.9

Performance Certificate

19

Damage to Works by Special Risks / Force Majeure

19

Outbreak of war / Force Majeure

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

CLAUSES leading to EXTENTION OF TIME:


Clause
CLAUSE Title
1.9

Delayed Drawings or Instructions

4.12

Unforeseeable Physical Conditions

17.4

Consequences of Employers Risks

4.24

Fossils

7.4

Testing - Engineers determination where tests are not provided for

8.9

Consequences of Suspension

2.1

Right of Access to the Site

8.4

Extension of Time for Completion

8.4

Extension of Time for Completion - Determination

19

Force Majeure - Special Risks

16.1

Contractors Entitlement to Suspend Work

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

CLAUSES referring to SECURITIES, INDEMNITIES & INSURANCE:


Clause
CLAUSE Title
4.2

Performance security

17

Risk and Responsibility

18

Insurance

1.13

Compliance with Laws

17.5

Intellectual and Industrial Property Rights

4.14

Avoidance of Interference

4.15

Access Route

4.16

Transport of Goods

4.17

Contractors Equipment

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

CONTRACTORS ADMINISTRATION FUNCTIONS:


Clause
CLAUSE Title
1.1

Definitions

1.7

Assignment

4.4

Subcontractors

1.8

Care and Supply of Documents

1.6

Contract Agreement

4.6

Co-operation

Staff and Labour

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

CONTRACTORS ADMINISTRATION FUNCTIONS:


Clause
CLAUSE Name
4.15

Access Route (to the site and maintenance of)

14.3

Application for Interim Payment Certificates

15.2

Assignment of Benefit of Agreement to Employer incase of


Termination

20.5

Amicable Settlement of disputes to be attempted

7.3

Inspections Give full opportunity to the Employers Personnel


/ Engineer to inspect by giving notice when work is ready

8.11

Prolonged Suspension Entitled for payment if suspension


exceeds 84 days

4.15

Access Route Satisfy as to the suitability of the route, be


responsible to maintain and put up signs

4.16

Transport of Goods Give 21 days notice to the Engineer

4.17

Contractors Equipment Will take the consent of the Engineer


before removal
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book
PAYMENT related CLAUSES:
Clause

TAISEI CORPORATION

CLAUSE Title

1.9

Delayed Drawings or Instructions

4.12

Unforeseeable Physical Conditions

4.24

Fossils

7.4

Testing Engineers requirement for Additional Test

7.3

Inspections Delay by the Engineer

8.9 & 8.10

Consequence of Suspension & Payment for Plant and


Materials in the Event of Suspension

42.2

Right of Access to the site

11.8

Contractor to search

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book
PAYMENT related CLAUSES:
Clause

TAISEI CORPORATION

CLAUSE Title

13

Valuations and Adjustments

14.3(f) &
20.1

Payment of Claims

5.3

Payments to Nominated Subcontractors

14

Contract Price and Payments

15.4

Payment after Termination

17.4

Consequences of Employers Risks (War, rebellion, roit, etc.)

15 & 19.6

Payment if Contract is Terminated

19.7

Release from Performance under the Law

16.4

Payment on Termination

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book
PAYMENT related CLAUSES:
Clause

TAISEI CORPORATION

CLAUSE Title

16.1

Contractors Entitlement to Suspend the Work

13.1

Right to Vary

13.7

Adjustment for changes in Legislation

13.4, 13.7
&14.15

Currency and Rates of Exchange

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

INFORMATION and ALERTS required to be PROVIDED BY the


CONTRACTOR during CONSTRUCTION PERIOD
1, DESIGN INFORMATION
2, PROGRAMME
3, CASH FLOW ESTIMATE
4, GEOLOGICAL AND ARCHEOLOGICAL FINDS
5, DETAILS OF LABOUR AND EQUIPMENT
6, PARTICULARS OF EXTENSION OF TIME
7, EMERGENCY WORK
8, VARIED WORKS

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part II: FIDIC BASED CONTRACTS
FIDIC First Edition 1999 Red Book

TAISEI CORPORATION

INFORMATION and ALERTS required to be PROVIDED BY the


CONTRACTOR during CONSTRUCTION PERIOD
9, CONTEMPORAY RECORDS
10, MEASUREMENT
11, LUMP SUM ITEMS
12, PROVISIONAL SUMS
13, PAYMENT TO NOMINATED SUBCONTRACTOR
14, MONTHLY STATEMENT

Back to Content of Part II


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT

TAISEI CORPORATION

Part III: CONTRACT ADMINISTRATION

Part III: Contract Administration


Chapter

Name

1.

General

2.

Project Records

3.

Project Control Division and its Members

Back to Content of Presentation


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
GENERAL

TAISEI CORPORATION

FACTORS to be CONTROLED within CONTRACT ADMINISTRATION:


Performance

Cost

Time

To CONTROL above mentioned, FOLLOWING IS NECESSARY:


Well understanding of obligations to be fulfilled by the parties
Cooperation between each party
Deployment of right personnel for right job
Timely mobilization
Prompt decision making
Settlement of Payment

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
GENERAL

Contract
Administration
focuses on:

Variation
Procedure
Claim Check
List

TAISEI CORPORATION

Claim
Administration

Project
Records

To be presented in
Part IV Claims
and Counterclaims

Back to Content of Part III

PROJECT CONTROL DIVISION

Preparation of
List of Submittals
by Contractor

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

PROJECT RECORDS
Documentation of FACTS & FIGURES = Key Element
in preparation of CLAIMS
In prevention / defends against CLAIMS

ORAL Interpretation DO NOT SUBSTITUDE Written RECORDS


Written RECORDS IDENTIFY RESPONSIBILITIES

provide SUBSTANTIATION for DELAY & ADDITIONAL COST

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

PROJECT RECORDS
DOCUMENTATION RECORD
is BURDENSOME TASK

PERSON in charge DO NOT


SEE immediate BENEFIT

PERSON in charge
BECOMES NEGLIGENT
FOLLOWING NEED TO BE SPECIFIED / ARRANGED:
DATA to be COLLECTED
COLLECTION INTERVALS
PERSON in charge of RECORDING / CHECKING
SYSTEM OF FORMS FILLING-UP / ITS STORAGE

DOCUMENT FLOWCHART is HELPFULL


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

CATEGORIES of PROJECT RECORDS / FILES:

LEGAL FILES:

CORRESPONDENCE

Contract documents
(Condition of Contract)
Specifications,
(e.g. GTS,STS etc.)
Change orders
Related materials

Chronological files
for all INTERNAL and
EXTERNAL
CORRESPONDENCE

SUBJECT-MATTER
FILES:
Subject-matter files
for each
subcontract,
construction phase,
or other readily
identifiable unit of
the project

E.G. - Exchange Loss


- Temp. Stock Yard
- Acceleration
- Time Extension
- Monthly Progress
Report
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

PROJECT RECORDS / FILES should specifically INCLUDE at least


following:
1) Record for Works Progress and Schedule
2) Daily Report
3) Cost Record for Labour, Equipment, Materials
4) Project Photographs
5) Project Diary
6) Tests Report
7) Variation Order
8) Drawing Change Log
9) Incoming and Outgoing Correspondence Log

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


1) WORK DISRUPTION REPORT (WDR)
Purpose: Reporting DISRUPTION WORK occurred, in the course of daily
construction activities
Flowchart:
Site Engineer /
Forman prepare
WDR

Chief Engineer /
Construction
manager review
WDR

Contract Engineer / Proj.


Contr. Manager record
WDR to WD Log incl.
details (QS,Time Impact)

Engineer receive Notice


on Work Disruption
Note:

If WORK DISRUPTION is due to Employer/Engineer Risk =>


Contractor raise CLAIM.
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


2) AVOID VERBAL INSTRUCTION (AVI)
Purpose: Reporting of VERBAL INSTRUCTIONS (VI) received from
Engineer / Employer
Flowchart:
Site Engineer
record VI to
DAILY REPORT

Chief Engineer /
Construction
Manager
prepare AVI

Contract Engineer /
Engineer / Proj. Contr.
Manager review AVI
alt. put record to
VARIATION LOG
AVI from Notice to
Employer/Engineer

Note:
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


3) REQUEST FOR INFORMATION (RFI)
Purpose: Request for Additional INFORMATION / CLARIFICATION /
INSTRUCTION to be provided by Employer/Engineer
Flowchart:
Site Engineer /
Chief Engineer
request INFO/
CLARIFICATION

Note:

Contract Engineer
prepare RFI Form
& record it to RFI
Log

Notice to Employer /
Engineer

RFI Log is essential tracking system monitoring status of all RFI


(IDENTIFICATION OF OUTSTANDING)
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


4) DAILY REPORT (DR)
Purpose: Recording of essential daily events of given day & shift
Flowchart:
Individual Site
Engineers
prepare DAILY
REPORT

Chief Engineer review


DR and select
IMPORTANT
INFORMATION

Contract Engineer check


CONTENT of IMPORTANT
INFO; TAKE STEPS
according to CONTRACT
Note:

Construction
Manager review
IMPORTANT
INFO

Notice to
Employer/Engineer

IMPORTANT INFORMATION:
WEATHER
TEMPERATURE
WORK EXECUTED

WORK COMMENCEMENT
DISRUPTION
ACCIDENT

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


5) DRAWING LOG (DL)
Purpose: Control system
Tracking/Comparison of SCHEDULED and ACTUAL DATES of:
DRAWING RECEIPT
DRAWING ISSUE
Identification of MISSED SUBMITTAL DATES => early ALERT
for DELAY

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


6a) MANPOWER DAILY REPORT (MDR)
Purpose: Recording of total MANPOWER for PROJECT COST CONTROL
Flowchart:
Forman/Site
Engineer prepare
MDR

Chief Engineer
check MDR

Construction
Manager approve

Cost Control
Engineer/Quantity
Engineer for Data
Processing

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


6b) TIME CARD (TC)
Purpose: Recording of WORKING HOURS for calculation of PAYMENTS &
WAGES
Flowchart:
Forman record
WORKING
HOURS on TC

Site Engineer
review TC

Section Manager
approve TC

Personal Manager
prepare WAGES
Note:

MDR & TC both relate to LABOUR recording Administration


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


7) EQUIPMENT DAILY REPORT (EDR)
Purpose: Recording of DAILY OPERATING HOURS per EQUIPMENT
Flowchart:
OPERATOR / DRIVER
CONTROLER records
Operating hours

EQUIPMENT
CONTROL
ENGINEER review

PROJECT
CONTROL
MANAGER
approve

Cost Control
Engineer for Data
Processing

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


8) MATERIAL ISSUING REPORT (MIR)
Purpose: Recording of MATERIAL CONSUPTION / NECESSITY for
PROJECT COST CONTROL
Flowchart:
Store Controller
prepare MIR

Purchase
Manager check
MIR

Cost Control
Engineer for Data
Processing

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT RECORDS

TAISEI CORPORATION

FORMS used within PROJECT RECORD ADMINISTRATION:


9) PROJECT PHOTOGRAPHS + PHOTOGRAPH INDEX
Purpose:

Recording is helpful for:


Accurate Asses of Work Progress
Dispute Settlement
Future Claims
Good Public Relations

Back to Content of Part III


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT CONTROL DIVISION - MEMBERS

TAISEI CORPORATION

PROJECT CONTROL DIVISION ORGANIZATION STRUCTURE

Project Control Manager

Contract Engineer

Quantity Surveyor

PROJECT CONTROL DIVISION

Document Controller

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT CONTROL DIVISION - MEMBERS

TAISEI CORPORATION

Project Control Manager

RESPONSIBILITY to the Project Manager

HOLD overall RESPONSIBILITY of SECTION

CO-ORDINATION with Other Section Heads for Effective Functioning

TEAM DEVELOPMENT with his Experience

PERFORM as CONSULTANT in the Organisation

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT CONTROL DIVISION - MEMBERS

TAISEI CORPORATION

Contract Engineer

STUDY the Contract Documents (CC, GTS, STS etc.)

PREPARE the STATEMENT of SUBMITTALS / APPROVALS requirement


from Engineer

CO-ORDINATION with Construction Division (Method statements,


Quality etc.)

VARIED Works Identification => Notice to Engineer

CLAIM Identification => prepare FACTS and GROUND

STUDY INCOMING CORRESPONDENCE

PREPARE OUTGOING CORRESPONDENCE in cooperation with Project


Manager
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT CONTROL DIVISION - MEMBERS

TAISEI CORPORATION

Contract Engineer

Prepare KEY DATES of CONSTRUCTION:


(Commencement date, Possession of Sites, other important dates)

Prepare NEW CONTRACTS

ORGANIZATION of MEETINGS (Weekly, Monthly)

SCHEDULE CONTROLLING with the Engineer and the Subcontractors

INFORM concern DIVISIONS of any CONTRACTUAL LACKINGS

MONITOR status of other CONTRACTUAL ADMIN. ISSUES


(Bank Guarantees, Retention money etc.)

Preparation of ADDENDUMS to Contract / Subcontract


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT CONTROL DIVISION - MEMBERS

TAISEI CORPORATION

Quantity Surveyor

STUDY: - BOQ & Description of items


- Measurement/Payment part of Technical specifications

Prepare MONTHLY STATEMENT in coordination with Site Engineers

CLAIM of PROVISIONAL PAYMENT (non-approved Varied works)

PRICE INDICES collection & CLAIM of PRICE ADJUSTMENT

Subcontractor/Other parties INVOICE evaluation

QUANTITY PREPARATION (revised drawing)

RECONCILIATION TABLE
(certified QUANTITY Engineer vs. Subcontractor)

Preparation of REVISED CONTRACT PRICE


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT CONTROL DIVISION - MEMBERS

TAISEI CORPORATION

Quantity Surveyor
Flow chart of Preparation of Monthly statement (Invoice)
Subcontractor submit
SUMMARY OF WORKS
23rd day of Actual month
Contractor prepare
SUMMARY OF WORKS
Submissions of SITE
DIARIES to Engineer
26th of Actual month
Substantiation of
SUMMARY OF WORKS
APROVAL
BY
ENGINEER

Preparation/Submission
of INVOICES Object wise
Signature of INVOICES
Object wise by the
Engineer / Contractor

Finalization of INVOICE
SUBMISSION to the
EMPLOYER
8pcs / 7th day of next
month after actual

Preparation/Submission
of CLAIM FORM,
COVER LETTER,
OBJECT SUMMARIES,
GENERAL ITEMS,
INVOICE for whole
PROJECT
Signature of SUBMITTED
documents

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part III: CONTRACT ADMINISTRATION
PROJECT CONTROL DIVISION - MEMBERS

TAISEI CORPORATION

Document Controller

CORRESPONDENCE SUBMISSION to relevant parties

CIRCULATION of incoming / outgoing correspondences

DOCUMENT CONTROL RECORD Updation

MONTHLY PROGRESS REPORT preparation to Employer / Internal

DRAWING Control

ASSISTANCE to QS within MONTHLY STATEMENT / INVOICE


submission

ASSISTANCE to CONTRACT ENGINEER within REMINDERS / REPLIES


to Various parties

Keeping RECORDS of QUALITY CONTROL, SITE DIARY etc.


Back to Content of Part III
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT

TAISEI CORPORATION

Part IV: CLAIMS AND COUNTERCLAIMS

Part IV: Claims and Counterclaims


Chapter

Name

1.

Definition

2.

Claim Administration

3.

Variation Procedure

Back to Content of Presentation


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
DEFINITION

TAISEI CORPORATION

Literal meaning of CLAIM:


A statement that something is true
that you have no definite proof

Back to Content of Part IV


PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
CLAIM ADMINISTRATION

TAISEI CORPORATION

ORIGIN of CLAIM:
ADVERSE OBSTRUCTIONS
or CONDITIONS
ENCOUNTERED

MAIN PURPOSE OF
CONTRACT :
DISTRIBUTE RISK
AMONG PARTIES
EMPLOYER
vs.CONTRACTOR

RISK

For example:
NON-DELIVERY or DELAY IN
DELIVERY OF MATERIAL/
APPROVAL/ DRAWING
ABNORMAL RAINFALL
etc.

Raise of CLAIM
by CONTRACTOR or
EMPLOYER
Additional/ Reduced PAYMENT

PROJECT CONTROL DIVISION

TIME Extension

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
CLAIM ADMINISTRATION

TAISEI CORPORATION

SOURCE of CLAIM:
No.
Source Name

Remark

1)

Authorities, Instructions, Approvals of


the Engineer including Engineer's
Representative

2)

Discrepancy or description of contract


documents

3)

Underground and physical conditions

4)

Time for completion, construction


method and temporary work plan

5)

Setting-out, exploratory excavation and


boreholes

6)

Possession of site

Delay, Third party rights

7)

Occurrence of Employer's risks or force


major

War, Rebelien. Missile

8)

Arising of damage and insurance

Variation of Geology

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
CLAIM ADMINISTRATION

TAISEI CORPORATION

SOURCE of CLAIM:
No.
Source Name

Remark

9)

Damage to third party (crack, noise,


traffic, fishery etc)

Damage to adjacent houses,


buildings etc.

10)

Test and inspection (attendance on


inspection, excess inspection, results,
timing, contents)

11)

Labour, working hours, night and rest day Extention of working hours to
work, foreign labour, local preference)
accelerate the progress

12)

Supply of samples

13)

Increase or decrease of quantities in BQ

14)

Variations, additional works, scope


change

Different character of the


Works

15)

Completion and taking-over (list of


outstanding works, date of certificate)

Issue of Taking Over


Certificate

More samples than required

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
CLAIM ADMINISTRATION

TAISEI CORPORATION

SOURCE of CLAIM:
No.
Source Name

Remark

16)

Statement and payment

17)

Suspension

Disruption of Works due to


Employer fault

18)

Employer supplied materials


(electricity and water)

Interruption in delivery/supply

19)

Fluctuation of materials and labour

20)

Works done by other contractors

21)

Changes or enactment of legislation

22)

Design

23)

Licenses and permission

24)

Defects liability

Delay in completion

25)

Currencies and rate of exchange

Exchange loss/gain

Change of VAT, tax, levy

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
CLAIM ADMINISTRATION
CLAIM PROCEDURE:

TAISEI CORPORATION
Procedures
according to
CONTRACT

Occurrence of
Adverse Condition

Forecast of Additional Cost


and/or Delay in progress
resulted from Condition

Notice of Occurrence to
Engineer/Employer

Recognition of Entitlement
with Contract Documents

Keep and maintain records

Recognition of Extend of
Claim

Notice to Claim

Preparation of Claim
Documents Facts, Record,
Ground Quantum

Submission of Claim /
Documents

Preparation/
substantiation
of CLAIM

Claim Negotiation
Back to Content of Part IV
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
VARIATION PROCEDURE

TAISEI CORPORATION

To PROPERLY COMPLETE the WORKS


The ENGINEER has RIGHT to make CHANGES of:

FORM

QUALITY

QUANTITY

IT REPRESENTS:
Increase or decrease of the Work quantities
Deletion of a part of the Works
Changes in the specification, levels, dimensions

LIMITATION:
- VARIATION are ONLY WORKS necessary for the Purpose of the Works
PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
VARIATION PROCEDURE

TAISEI CORPORATION

ISSUE of VARIATION:
VARIATION shall be made IN WRITING

IF made VERBALLY => CONTRACTOR shall confirm VERBAL VARIATION


through AVI Form (AVOID VERBAL INSTRUCTION explained before)
Under FIDIC: Variation shall be made in form of:
INSTRUCTION BY ENGINEER

Additional Cost / Expenses shall be VALUED Using:


A) RATES/ UNIT
PRICES set in
CONTRACT

B) PRO-RATA RATES
from CONTRACT
RATES
PROJECT CONTROL DIVISION

C) NEW RATES

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
VARIATION PROCEDURE

TAISEI CORPORATION

ISSUE of VARIATION:
Under FIDIC: Contractor execute Engineers Instruction
WITHOUT VARIATION ORDER

CONTRACTORs CLAIM on:


A) ADDITIONAL COST
Contractors INTENTION:
to contend the application of
HIGHER RATES since in the
CONTRACT RATES is included the
DISCOUNT made during negotiation

B) TIME EXTENSION
ENGINEERs INTENTION:
NOT to ADMIT VARIATIONS and
ARGUES it is WITHIN the ORIGINAL
SCOPE of the works.

PROJECT CONTROL DIVISION

CONTRACT MANAGEMENT
Part IV: CLAIMS AND COUNTERCLAIMS
VARIATION PROCEDURE

TAISEI CORPORATION

CLAIMS by the EMPLOYER:


Cl.
CLAUSE Name
10.3

Performance Security

16.2

Engineers at Liberty to Object

22.1

Damages to persons and property


due to Contractors fault

29.1

Interference with Traffic and


Adjoining properties

30.1

Avoidance of Damage of Roads

30.3

Transport of Materials or Plant

39.2

Default of Contractor in Compliance

47.1

Liquidity Damages for Delay

49.4

Contractors Failure to Carryout


Instructions

63.1

Default of Contractor
Back to Content of Part IV
PROJECT CONTROL DIVISION

Remark

CONTRACT MANAGEMENT

TAISEI CORPORATION

CONCLUSION OF PRESENTATION

THANK YOU VERY MUCH


FOR YOUR KIND ATTENTATION AND PATIENCE
WITHIN THE PRESENTATION OF:

CONTRACT MANAGEMENT

NEXT PRESENTATIONS:
RISK MANAGEMENT
LEGAL MANAGEMENT

PROJECT CONTROL DIVISION

Das könnte Ihnen auch gefallen