Beruflich Dokumente
Kultur Dokumente
BY PERFORMANCE
Discharge of contract
Meaning
> Contract is terminated
> Parties are released / discharged from
contractual obligations
NOTE:
Dispute arise where X demand performance
of contract, but Y claimed he was discharged
from contractual obligation to perform
GENERAL RULE
1. Each party to the contract has contractual
obligations to perform. Eg
a. Sale Agreement :
> Seller deliver the goods according to the terms /
specification stated.
> Buyers obligation is the payment when
contract is performed
b. Employment agreement:
When does Employers duty to pay salary
arise?
2. Order of performance
Question of who is to perform 1st
Sec 53 : when the order of performance of
contract for reciprocal promise is fixed by
the contract, they shall be performed in that
order
>>> Question of construction of terms on
WHO is the 1st person to perform the
contract
Held
1. Order n sequence: S 53 Contract Act;
look at nature of transaction
2. Only registered owner of land can apply
for licence. Vendor (R) has breached
primary obligation.
Consequence of non
compliance
Deviation / non performance = breach of contract.
>> Party in breach is not entitled to payment.
Reason: Contract was not fully performed as
per the terms
>> Where non performance is inexcusable,
contract breaker faced a claim of breach of
contract
>> Effect: Injured party is entitled to terminate all
future obligations under contract
Case: Re Moore v Landauer
Re Moore v Landauer
B ordered goods to be packed 30 cans per
box. B rejected goods delivered & refused to
pay. 50% were packed 24 cans per box. S
sued B for breach of contract.
Defence: S had not performed the terms of
contract
Held: No discharge of contract by performance
i. Breach of term ie condition by Seller.
ii. Seller was not entitled to payment. Did not
perform the contract according to the terms
iii. Buyer was entitled to repudiate the contract &
reject the goods
Effect of judgements
Strict application of complete & precise
performance of entire contracts
Criticism:
> unjust enrichment for Paying party
who had benefitted from the contract
Msian position
Kunchi Rahman v Goh Bros (1978)
FACTS
Contract worth $71000 was made with Pl to
supply & lay pipes between Mak Mandin & Prai
for $ 16580. Work was not completed despite
reminders given. D incurred expenses. Another
contractor was hired to complete the work.
Claim for payment was made by Pl. Def
counterclaimed for damages
Issues
> Was Contractor entitled to the contract sum?
How much?
> Was the contract substantially performed?
Note:
English law was followed. Ratio decidendi of
Bolton v Mahadeva was applied
Held
Agreement was an entire contract. Pl had
substantially performed / completed the
contract. Entitled to claim balance of
payment [ $11,000]
Def was also entitled to counterclaim for the
defects & cost to complete the contract [ ie $
22,000]. Damages awarded will diminish /
reduce amount claimed by Pl. Amount after
adjustment : $6047
Pls claim was dismissed
EXCEPTION 2
Divisible Contracts :
> Obligations broken down into smaller units
eg
i. building contracts ---payment according
to percentage of work done
ii. Employment contract----salary paid at
intervals eg on daily or weekly basis
Divisible Contracts
Difference from entire contract
> Separate payment for performance by
instalment
Question : How much to pay ?
Tong Aik v Eastern Mineral (1963 )
EXCEPTION 3
Prevention of Performance of Contracts
Unfair to disallow claims for portion of work done
Party who prevent performance of contract
committed breach of contract
Performing party allowed to sue payment on
quantum meruit: basis
Planche v Colburn [1831]
EXCEPTION 4
Acceptance of partial performance
Inference of new contract. Implied contract to
pay for work done
No entitlement to original contract price. Right
to payment on quantum meruit
Innocent partys option to accept or reject
incomplete / partial performance of contract
Case: Sumpter v Hedges
Smith Construction Co Ltd v Phit
Kiritvana [ 1955]
Examples
i. Sale of goods
S11 SOGA, 1957: Stipulation / term as to time
of payment is not deemed as of the essence.
Stipulation as to time of delivery of goods
Case: Himatsing v Joitaram
ii. Sale of land :
Generally , time is not important, unless it is
specified that time is of the essence
Jamshed Khodaram Irani v Burjoji [1913] PC
Issues:
Relevance of additional work given by
Resp?
Was the extra time to perform the work =
a waiver of the term that time is of the
essence?
continue
where there was no such provision in the
agreement ,means he had waived his
right to rescind the contract & the right to
treat himself as discharged
3. The term / stipulation as to time ceased to
be of the essence of the agreement.
reason: Acquiescence in the
continuance of the work
Extension of time:
What is the legal implication?
CONSIDER:
Extension of time:
What is the legal implication?
3. If the performing party breached the
contract [ ie did not complete the contract
despite the new time extended ] , can the
parties rely on the original date of
performance?
4. Must there be insistence on time being of
the essence of contract [ for the new time /
date] ?
FACTS
App [P] entered into a sale and purchase
agreement dated 11 October 1989 with
the Resp [V] to purchase land at the
agreed price of RM550,000. At the time of
execution of the agreement, App had paid
Resp RM50,000.
By cl. 3(a) App was to pay the balance of
RM500,000 on or before 9 January 1990.
.
3. He applied to Bank for a loan of
RM800,000. It was approved on 26 June
2000. However, until 21 July 2000, ie the
date of the termination of the agreement,
the lands had not been redeemed by
Resp
4. Under cl 22 of the SPA, time shall be of
essence of the agreement
Issues
(i) whether the App [V] were entitled to terminate
the SPA and to forfeit the deposit for the noncompliance by the Resp [P] of the condition to
redeem the property within the time stipulated
[YES]
(i) whether the Resp was entitled to insist on the
App continuing with the SPA when the
respondent himself failed to redeem the
property within the stipulated time.
[ NO]
THE END