Construction challenges

INTRODUCTION
A circular railway of 57.9 km metro system on two corridors
Phase-I 12.9 km - Rajajinagar to Jayanagar
Phase - II 11.2 km-Hudson Circle to Krishnaraja puram.
Phase III
Phase IV

INTRODUCTION
CLIENT :

BANGALORE METRO RAIL COROPORATION


LIMITED
CONSULTANT: RITES
L&TS SCOPE : REACH -III - 3 STATIONS

REACH- IV -3 STATIONS

METRO ROUTE MAP

East West Corridor

:
18.10 kms
North-South Corridor :
24.20kms
Total
:
42.30 kms
Elevated
:
32.85 kms
At grade (at ground level)
00.65 kms
Under ground
08.80 kms
Gauge
standard gauge
Traction
750 v Dc third rail
No of stations
39(31 elevated,8 Ug)
Travel time
33/44 mins (end to end)
Head way
4 mins at start ; later 3 mins

CHALLENGES IN NAMMA METRO


CONSTRUCTION:

1. Traffic volume & diversion


2. Deep excavation (6 m from road level)
3. Local Public issues / Project Affected People
4. Existing utilities
5. safety
6. Environmental aspects
7. Space constraints (Stacking ,Transporting

&Erection Of Precast Girder)


8. Media Focus (Increased spot lights )
9. Quality of skilled labour

Challenge: 1. Traffic Volume & Diversion


Safety of public & workmen

Productivity
Progress

STAGE 1
12M
6M

6M

Both the footpaths are demolished


and Constructed for temporary
road

STAGE 1
PIER
ERCT THE BARRICATION

MAKE THE TEMPORARY ROAD

6M

EXISTING PATHWAY TO BE DEMOLISHED

6M

L&T TRAFFIC MARSHALS ENGAGED WITH SIGNAL


TORCH (FLUORESCENT LIGHT) AT NIGHT SHIFT
BLINKER LIGHTS

Challenge 2 : Deep Excavation

Challenge: 3 Project affected people


a) Pre-construction stage
Land acquisition/litigation

b) Construction stage,
Noise pollution
Air pollution
Traffic diversion
Utility diversion
Working hours

Challenge: 4 Existing utilities


Identification of utilities
Interfacing with various agencies ( Govt / Non

Govt)
(BBMP,BWSSB,BESCOM,KPTCL,BSNL etc)

Challenge 5: safety

Safety

Pep talk conducted for


Traffic Marshals and
Workmen

Traffic signage and painted Hard barricading


boards with Reflective ballet posts

Ballet post

Challenge 6: Environmental

aspects
Some of the environmental components
considered under this are

1. Trees
2. Air pollution
3. Noise levels
4. Soil erosion and pollution
5. Disposal of excavated soil and debris
6. Maintaining of roads/Drainages

Challenge : space constraints


Impacts
Casting ,stacking& transportation
Erection scheme

Stacking ,Transportation & Erection Of Precast Girder


A major concern with girder erection is the security and stability of the superstructure
During all phases of erection with respect to construction conditions, wind loads and construction loads.
Stacking of the girders until the erection part comes & delivery of precast concrete girders to the site
Erection of precast girders with the traffic flow
.

Taking the above things in consideration L&T made a detailed


erection scheme.

Erection Methodolgy for R4 06082009.ppt

Challenge 9 : Quality of skilled


labour

Resource