Beruflich Dokumente
Kultur Dokumente
June 8, 2015
PROJECT BACKGROUND
Goals, design process, preliminary work
Malcolm Pirnie
Stantec
Boyle | AECOM
April 2006
April 2007
April 2009
Relocate to former
high school parking lot
Project Status
U.S.
U.S. 41
41
2012
Work stops due to
microtunnel issues
2011
Construction
begins
Safety
6
Scope of Work
Microtunnel under existing bridge as designed or at revised
elevations
Scope of Work
Finalize microtunnel design (-16.5 feet)
Redesign Lift Station 87
Microtunnel
jacking pit
Microtunnel
receiving pit
Current
alignment
Alternate
alignment
Benefits
Maintenance of Traffic
Access to Businesses
Microtunnel
jacking pit
Less US 41 Impacts
Hudson
Hudson Bayou
Bayou
OspreyAve.
Ave
Osprey
10
LATEST FINDINGS
12
Comprehensive Geotechnical
Review
0
0
0
0
0
0 0
0
0
0
00
0
0
0
0
1996-2012
0 borings
2013
0 borings
2015
0 borings
0
0
NORTHEA
ST
CORNER
SOUTHWE
ST
CORNER
Original
36" pipe
8.75'
Proposed
36" microtunnel
8.0'
SOUTHEA
ST
CORNER
Original
36" pipe
Proposed
36" microtunnel
8'
Concrete core
Concrete abutment
(surveyed)
Concrete abutment
(interpreted)
Geotechnical Summary
North to
Mound St.
Original pipe
Top of pipe
elevation: -8.5'
Proposed
microtunnel
Top of pipe
elevation: -16.5'
15
RISK MANAGEMENT
Designs, data and assessments
16
17
High
High
Mediu
m
Medium
1:
2:
3:
4:
5:
Impact
Low
PROBABILITY
Low
1:
2:
3:
4:
5:
0 20%
20 40%
40 60%
60 80%
80 100%
< $100 K
$100 K $250 K
$250K $500K
$500 K $1M
> $1M
18
19
Analysis of microtunneling
High jacking force i.e. stuck machine
Environmental impact to Hudson Bayou
Mixed face conditions hard soils on part of machine, soft on another
Unexpected geotechnical conditions
Line and grade deviations outside of tolerances
Pipe breaking
Differing Site Conditions claims
Damage to the bridge
20
21
120
36
25
22
6-8 feet
Forensic/Hyatt (2014)
7 feet
ALTERNATE ROUTES
Methods, plans and other considerations
24
25
Top of
Foundation
Material
(-9.0)
Influent MH
Invert
(-13.08)
Wetwell
Invert
(-13.52)
Hudson
Hudson Bayou
Bayou
OspreyAve.
Ave.
Osprey
26
Regulatory Considerations
Subaqueous
Crossing
Regulations
Florida
Department of
Environmental
Protection (FDEP)
3 Feet Cover
U.S. Army Corps
of Engineers
(USACE)
6 Feet Cover
Top of Pipe
El. -9.00
Open cut
27
Alternate Route 1
36"
Disrupts condos
Permits needed
0 Manhole
Disrupts home
OspreyAve.
Ave.
Osprey
New easement
30"
28
Alternate Route 2
36"
Disrupts condos
Permits needed
New acquisition
Hudson
Hudson Bayou
Bayou
New easement
0 Manhole
24"
30"
29
Alternate Route 3
East of Bridge
Disrupts park
U.S.
U.S. 41
41
36"
Permits needed
Disrupts home
Hudson
Hudson Bayou
Bayou
New easement
0 Manhole
24"
30"
30
Environmental
Documented Lead Contamination (2001 Boyle Report)
Geotechnical Investigations
Borings/Bathymetric
Schedule
31
Operational Impacts
Period submergence of sewer system
- Reduced conveyance capacity
- More frequent pipeline cleaning
- Increased odor potential in neighborhood
Open Cut
Odor
s
Gravity Sewer
Wetwell
33
Surcharge Conditions
Existing Wetwell Design
-TBD ft.
Odor
s
Manhol
e
Gravity
Sewer
Existing
Wetwell
34
Stand-by Pump
Reliability required
35
Open Cut
current est.
36 Inch (Phase 1)
$11.0 M
$6.5 M
$16.0 M
$13.3 M
$5.0 M
$5.0 M
Land Acquisition
& Legal
$4.0 M
Environmental
$6.2 M
$1.0 M
$32.0 M
$36.0 M
24 Inch (Phase 3)
Total Estimate
Open Cut notes: Hudson Bayou crossing assumes variance from state and federal regulation requirements; Land
Acquisition & Legal estimated based on city input; Environmental from 2001 Hudson Bayou Stormwater Study
36
Previous Bid
January 2011
indexed to 2015
Current
estimate
Difference
36 Inch
(Phase 1)
$1.5 M
$1.7 M
$11.0 M
$9.3 M
Lift Station 87
(Phase 2)
$5.4 M
$6.1 M
$16.0 M
$9.9 M
24 Inch
(Phase 3)
$2.7 M
$3.0 M
$5.0 M
$2.0 M
Total Estimate
$9.6 M
$10.8 M
$32.0 M
$21.2 M
Analysis of differences
$9.3 M: 36 Inch (Microtunnel)
Quotes from recent negotiation attempts
Analysis of differences
$8.9 M: Upgrades
Category 3 storm surge protection
Operating redundancies
Totally enclosed for all operation & maintenance activities
Safe working environment for staff
Climate change provisions
Deeper wetwell/operational efficiencies
Site preparation
39
NEXT STEPS
40
Sequencing of
Construction
Additional
Advantages
U.S.
U.S. 41
41
Risk Management
Minimize Disruption to
Existing Utilities
Cost Controls
Hudson
Hudson Bayou
Bayou
Maintenance of Traffic
41
Construction Plan
Three
Phases
Phase 1
36 inch pipe
Phase 2
LS 87 construction
Demolition of
Lift Station 7
and park
restoration
Phase 3
24 inch pipe
Lift Station 7
42
Construction Challenges
Limited site access
Construction zone restrictions
Minimize impacts to Luke Wood Park
Maintenance of traffic
Minimize service disruptions
43
Microtunneling
Work Zone
LS site
driveway
Jacking shaft
work zone
U.S.
U.S. 41
41
Receiving shaft
work zone
Construction
support
work zone
Jacking shaft
work zone
Hudson
Hudson Bayou
Bayou
44
MICROTUNNE
L ALIGNMENT
JACKI
NG
SHAFT
BENTONITE
MIXER
BAKER TANK
MICROTUNNEL
JACKING SHAFT
WORK ZONE
PIP
E
CONTR
OL
BOOTH
GENERATO
R
STORAGE
SOIL
SEPARATION
PLANT
HUDSO
N
BAYOU
CR
AN
E
STORA
GE
45
41
US
ER
GEN R
O
LS SITE
DRIVEWA
Y
AT
N
CRA
E
E
PIP
PIPE
STORA
GE
AREA
O
NT
BE TE
NI ER
X
MI
AG
OR
ST E
IL
N
SO TIO
RA T
A
P AN
E
S PL
G
KIN
JAC AFT
SH
N
CO
TRO
L
O
BO
TH
OFFIC
E
TRAIL
ER
MICROTUNNE
L ALIGNMENT
46
APPROVED
SITE PLAN
47
C
ur
re
nt
D
es
ig
n
Bid Phase
Start
Finish
36 inch
(Phase 1)
July
2015
June
2017
Lift Station
(Phase 2)
Sept.
2016
June
2019
24 inch
(Phase 3)
Jan.
2019
Aug.
2020
2015
2016
2017
2018
2019
2020
Q
1/
2
Q
1/
2
Q
1/
2
Q
1/
2
Q
1/
2
Q
1/
2
Q
3/
4
Q
3/
4
Q
3/
4
Q
3/
4
Q
3/
4
Q
3/4
48
Project Goals
Environmental stewardship
- Improve service and system reliability
- Storm protection (Category 3 hurricane)
- Offset potable water demands with reclaimed water
49
50
51
Discussion
53
Option 1
54
Option 2
55
Option 3
56
Staff Recommendation
Option 3
Bond debt while maintaining CIP funding level
57
Discussion