MBTS3900
Local MBTS Commissioning
introduction
www.huawei.com

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

MBTS Commissioning by using


Flash Drive

This section describes how to load a software package or data


configuration files from an already prepared USB flash drive to a
base station.

We Need:

USB flash drive and MBTS configuration File.


Copy the BTS configuration in flash drive.
Plug-in USB Flash drive in UMPTb board.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

MBTS Commissioning & Strategy


There are Two major ways for Commissioning the MBTS
Flash Drive Method
LMT Method
Note:
First the Engineer will move to the site and get the ESN from the BBU during the preinstallation & provide it back to Huawei Integration Team (OMCR).
The NI team will activate the DHCP Function and assign the IP to the BTS.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Introduction to the Ports of UMPTb2

Universal Main Processing & Transmission unit with 4E1 and 2FE/GE
interface UMPTb2
The Universal Main Processing & Transmission unit (UMPT) is a main
control and transmission unit commonly used by the BBU3900.

UMPT

The UMPT performs the following functions:


Performs configuration management, device management,
performance monitoring, and signaling processing.
Processes signaling and manages resources for other boards in the
BBU.
Provides the USB port, transmission port, maintenance port for
transmitting signals, automatically upgrading software, and
maintaining the BBU on the LMT or M2000

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

MBTS Commissioning by using


Flash Drive

This section describes how to load a software package or data


configuration files from an already prepared USB flash drive to a
base station.

We Need:

USB flash drive and MBTS configuration File.


Copy the BTS configuration in flash drive.
Plug-in USB Flash drive in UMPTb board.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

ABIS over IP configuration by using


LMT
Connect the laptop to the BTS.
As per provided plan Configure the MBTS by using LMT
software

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Basic Steps for start the


configuration

Check the BTS Hardware and Powered ON.


Check the transmission status with transmission engineer, the
port for BTS should be defined in the transmission side.
Ping test from RTN or GPON to the BSC gateway is OK.
If the transmission is ping able, go to the site and connect the LAN
cable between the transmission FE port and UMPT FE0 port.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

USB Flash Drive for MBTS


Commissioning
Plug the USB flash drive into the USB port of the
computer.
Create a folder named Site 1 in the USB flash drive.
create a folder named MBTS (the name is the site name )
in the folder Site 1.
Copy the PreCfg.ini file to the folder ,you can get the
TransCfg.ini file from the BSC integration Team.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

If the light on the USB flash drive is on and the RUN indicator on the
main control board is blinking fast (0.125s on and 0.125s off) after the
USB flash drive is connected to the main control board, the base
station starts loading the software and data configuration files from
the USB flash drive.
If the light on the USB flash drive is off and the RUN indicator on the
main control board keeps blinking slowly (1s on and 1s off) after the
USB flash drive is connected to the main control board, the USB flash
drive or the USB port on main control board is faulty.
Wait for the base station to automatically load and activate the
software and data configuration files, and restart. Then verify that the
loaded software and data configuration files have taken effect.
The local engineer can observe the status of the RUN indicator on the
main control board to determine the loading status of the software and
data configuration files, as provided in the following table. For a
single-mode base station, this step takes about 15 minutes. For a
multimode base station, this step takes about 25 to 30 minutes. It is
recommended that the local engineer observe the status of the RUN
indicator after this duration.
Remove the USB flash drive after the base station enters The loading
succeeds status.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Check the status of the MBTS, make sure the UMPT board is
power on and working normal.
Put the USB flash into the USB port of the UMPT.

Do not remove the USB flash drive during the period from
plugging in the flash drive to the duration of normal operation
of the base station. Otherwise, the file load fails.
Check with BSC integration team whether the BSC can Ping to
the BTS IP.
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Use LMT for MBTS Commissioning


To use the LMT to log in to the base station, perform the following
steps:
Connect the LMT to the base station.
USB-Ethernet adaption cable to connect the Ethernet port on
the computer where the LMT is installed to the UMPT in the
BBU3900.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Laptop IP settings

Set your computer IP address like below: IP address is


192.168.0.47,subnet mask is 255.255.255.0

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Login in the MBTS LMT

In the address box of the browser, enter the IP address of the


main control board for local maintenance. The default IP
address is 192.168.0.49
Enter the user name, password, and verification code in the
User name, Password, and Verification code text boxes,
respectively. Set User type to Local.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Configuring the FTP Server


You can download the base station software, data
configuration file, and license from an File Transfer
Protocol (FTP) server to the local maintenance terminal
(LMT).
1. Download the FTP server software. (Optional. Perform this step only when there is
no FTP server at the LMT computer.)
2. In the upper right corner of the LMT main window, click FTP Tool. The File
Download-Security Warning dialog box is displayed.
3. Click Save to save the FTP server software SFTPServer.exe to the LMT computer.
4. Double-click SFTPServer.exe. SFTPServer.exe is decompressed into an SFTPServer
folder.
5. Open SFTPServer. Double-click SFTPServer.exe to start the FTP server. The icon is
displayed on the right side of the taskbar after the FTP server is started.
6. Configure the FTP server.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Double-click . The FTP server configuration dialog box is displayed.

Set User name, Password, Working directory, the default user name is admin
and the default password is hwbs@com. Set Working directory to the root
directory of the FTP server, which is D:\FTP, and retain default values for other
parameters.
Click OK. The FTP server is successfully configured

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Loading Software, Data Configuration File,


and Commissioning License on the LMT

This section describes how to load the software, data


configuration file, and commissioning license to a base station.

1. In the LMT main window, click Device Maintenance.


2. In the navigation tree, choose BTS Maintenance > Common
Maintenance > Software Management. Double-click Software
Management (The Software Management tab page is displayed)
The version MBTS V100R008C00SPC100 is used as an example.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Set parameters related to FTP Server Configuration on the Software


anagement.
Select tasks based on scenarios.

Click Execute

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

MML Mode

Run the DLD SOFTWARE command to download the software and Boot
Rom.
Run the DLD CFGFILE command to download the configuration file.
Run the ACT CFGFILE command to activate the configuration file. If EFT is set
to AFTER_RESET, the operation takes effect only after the base station resets.
Run the ACT SOFTWARE command to activate the software and Boot Rom.
Run the INS LICENSE command to download and install the license file.
After the base station restarts, run the LST VER command to check
whether all modes have been loaded with the software of the target
version. If not, run the DLD SOFTWARE command to redownload the
software and then run the ACT SOFTWARE command to activate the
software.
If no operation is required on the LMT, log out of the LMT according to the
following steps: Click Logout in the toolbar in the LMT main window. The
Confirm dialog box is displayed.
Click Yes. The LMT is disconnected from the base station. A dialog box for
logging in to the LMT is displayed.
Close the browser to exit the LMT
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

SDT Tool

SDT

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential