Beruflich Dokumente
Kultur Dokumente
Impact Assessment
Prof. Sandeep Hegde
is intended as an instrument of
preventive environmental
management. It provides a
framework and an information
basis for decision making on
activities affecting the
environment.
EIA
applies to the assessment of the
environmental effects of those public
and private projects which are likely to
have significant effects on the
environment.
EIA
Project means:
the execution of construction works or
of other installations or schemes
other interventions in the natural
surroundings and landscape including
those involving the extraction of
minerals.
EIA
Development consent means:
the decision of the competent
authorities which entitles the developer
to proceed with the project.
EIA
.. have significant effects on the
environment by virtue inter alia,
of their:
EIA
direct and indirect effects of a project
on the following factors:
Environmental Impact
Assessment (EIA)
with
mandatory
EIA.
The
notification
Environmental
Clearance
Process
Information requirements
Description of the project:
physical characteristics, land-use
requirements during construction and
operation
production processes, materials used
estimate of expected residues and
emissions (water, air, soil pollution, noise,
vibrations, light, heat, radiation, etc.)
Information requirements
Alternatives:
outline of the main alternatives
main reasons for choice, including
environmental effects
Information requirements
Impacts on:
population, fauna, flora, soils, water, air,
climatic factors, material assets incl.
architectural and archeological heritage,
landscape
interrelationship between these factors
Information requirements
Likely significant effects from:
existence of the project
use of natural resources
emission of pollutants, creation of
nuisances, elimination of waste
and the description of the methods
used to assess the effects.
Information requirements
Description of measures:
to prevent, reduce, and where
possible to offset any significant
adverse effects on the
environment.
procedural steps:
EIA Process
procedure:
Phase B
Phase A
Project
Life
Cycle
Phase C
Phase E
Phase D
A. Project
Concept/Identification
Initial stage of the project planning
Basic nature of the project is known
including the site(s) where the project is
being proposed to be implemented
Screen project to determine if project
requires a full EIA
Screening
Screening
Identify environmental issues of concern
Determine whether EIA is needed
Establish need for project
Environmental
impact
Project
Economic
impact
Social
impact
Not require
EIA
Require
EIA
Threshold criteria
Size
Location
Output
Cost/Finances
Environmental
effects
etc.
Impacts
unclear
Impact criteria
Significant but
easily identifiable
impacts
Significant impacts
Sensitive area
B. Pre-feasibility Stage
Scope the project to identify issues/impacts for investigation
Evaluating the
significance of issues
Distribution of information
to interested parties
Initial Assessment of
Impacts
Existing or baseline data:
provide a description of the status and trends of
environmental factors (e.g., air pollutant
concentrations) against which predicted
changes can be compared and evaluated in
terms of importance
C. Feasibility Stage
Conduct the EIA and determine if the project is
viable
Magnitude of impact - indicate whether the impact is
irreversible or, reversible and estimated potential rate of
recovery
Extent of impact - spatial extent of impacts should be
determined
Duration of Impact - arising at different phases of the
project cycle and the length of the impact [e.g. short term
(during construction-9 yrs), medium term (10-20 yrs), long
term (20+ yrs)]
E. Environmental Monitoring
Environmental monitoring provides feedback
about the actual environmental impacts of a
project
Helps judge the success of mitigation
measures in protecting the environment
Ensure compliance with environmental
standards
Facilitate any needed project design or
operational changes
The corporation has already constructed one private dam and there is
no water downstream of this dam. Farmers have neither drinking water
nor water for irrigation. The farmers downsteam recently attacked
mkvdc and it was forced to release water. Imagine what will happen
after all the four dams are constructed, says Shedge of Mugaon
village. A petition in the Bombay High Court challenged allocation of
mkvdcs land in 2006. The petition also said that mkvdc was not meant
for commercial use and Lavasa was a purely commercial venture. The
case is pending.
The company says it is building 12 mini dams in the area that will add
to the current capacity of the Warasgaon lake. These dams will be
built at higher levels increasing the existing catchment capacity. We will
create an additional water catchment of 0.9 thousand million cubic
metres (tmc) of which 0.4 tmc will be used by Lavasa and 0.5 tmc will
be released into the lake, the spokesperson said.