Introduction
Mathematical tools have been used for
thousands of years
Quantitative analysis can be applied to
a wide variety of problems
Its not enough to just know the
mathematics of a technique
One must understand the specific
applicability of the technique, its
limitations, and its assumptions
2009 Prentice-Hall, Inc.
12
business.
13
Need for OM
Lots of information, but no decisions.
Enterprise resource planning (ERP) systems and the
Web have contributed to a pervasive information
environment; decision-makers have total access to
every piece of data in the organization.
The problem is that most people need a way to
transform this wealth of data into actionable information
that helps them make good tactical and strategic
decisions.
The role of OM decision methods is to help leverage a
companys investment in information technology
infrastructure by providing a way to convert data into
actions.
2009 Prentice-Hall, Inc.
14
Need for OM
A large nationwide bank is using OM
15
Need for OM
A major retail enterprise is using OM
16
Need for OM
Sears, Roebuck and Company
Manages a U.S. fleet of more than 1,000 delivery
17
Need for OM
OM researchers designed a system to deal with such
18
19
Raw Data
Quantitative
Analysis
Meaningful
Information
1 10
1 11
1 12
step
It is essential to go beyond symptoms and
identify true causes
May be necessary to concentrate on only a few
of the problems selecting the right problems
is very important
Specific and measurable objectives may have
to be developed
2009 Prentice-Hall, Inc.
1 13
Developing a Model
$ Sales
$ Advertising
Schematic
models
2009 Prentice-Hall, Inc.
1 14
Developing a Model
Models generally contain variables
1 15
1 16
Developing a Solution
The best (optimal) solution to a problem
1 17
1 18
in an organization
The impact of actions or changes needs to
be studied and understood before
implementation
tested
1 19
1 20
1 21
analysis approach
Lets look at a simple mathematical
model of profit
Profit = Revenue Expenses
1 22
1 23
1 24
Bagels R Us
Assume you are the new owner of Bagels R Us and you want to
develop a mathematical model for your daily profits and
breakeven point. Your fixed overhead is $100 per day and your
variable costs are 0.50 per bagel (these are GREAT bagels). You
charge $1 per bagel.
- Fixed Cost
- (Variable Cost/Unit)
(Number Sold)
1 25
Breakeven Example
f=$100, s=$1, v=$.50
X=f/(s-v)
X=100/(1-.5)
X=200
At this point, Profits are 0
2009 Prentice-Hall, Inc.
1 26
1 27
or
0 = (s v)X f
Fixed cost
(Selling price per unit) (Variable cost per unit)
2009 Prentice-Hall, Inc.
1 28
Fixed cost
(Selling price per unit) (Variable cost per unit)
2009 Prentice-Hall, Inc.
1 29
Examples
1. Selling price $1.50, cost/bagel $.80,
1 30
Examples
Seeing a need for childcare in her community, Sue decided to
launch her own daycare service. Her service needed to be
affordable, so she decided to watch each child for $12 a day.
After doing her homework, Sue came up with the following
financial information:
Selling Price (per child per day) $12
Operating Expenses (per month)
Insurance 400 + Rent 200 = Total OE $600
1 31
Examples
Applying the formula, we have:
$600/($12-$4) = 75
She has to have a total of 75 children in her program over
the month to breakeven.
If she is open only 20 days per month then she needs
75/20=3.75 children per day on the average.
Expenses per month $600 + 75*$4.00 = $900
Revenue per month 75*$12 = $900
1 32
formulate problems
Models can give us insight and information
Models can save time and money in
decision making and problem solving
A model may be the only way to solve large
or complex problems in a timely fashion
A model can be used to communicate
problems and solutions to others
2009 Prentice-Hall, Inc.
1 33
based on probabilities
1 34
decision support
system for use in
POM and QM
courses
menu of
quantitative
models
Program 1.1
2009 Prentice-Hall, Inc.
1 35
Program 1.2A
2009 Prentice-Hall, Inc.
1 36
Program 1.2B
2009 Prentice-Hall, Inc.
1 37
Program 1.3A
2009 Prentice-Hall, Inc.
1 38
Program 1.3B
2009 Prentice-Hall, Inc.
1 39
Program 1.4
2009 Prentice-Hall, Inc.
1 40
Program 1.4
2009 Prentice-Hall, Inc.
1 41
Developing a model
Fitting the textbook models
Understanding the model
2009 Prentice-Hall, Inc.
1 42
Developing a solution
Hard-to-understand mathematics
Only one answer is limiting
1 43
Implementation
Not Just the Final Step
Lack of commitment and resistance
to change
Management may fear the use of
1 44
Implementation
Not Just the Final Step
Lack of commitment by quantitative
analysts
An analysts should be involved with
1 45