Beruflich Dokumente
Kultur Dokumente
Material Requirement
Planning
Prof. Sanjay Choudhari
Indian Institute of Management
Indore
Strategic capacity
planning
Sales and Operations
(aggregate) planning
Master Production
Schedule
Material Requirement
Planning
Order Scheduling
Hierarchy
Aggregate Production plan for shirts (Forecast + Customer orders )
Months
Jan
Feb
Shirts Productions
980
950
200
400
100
100
100
200
100
150
100
200
200
MRP
Program
Calculate and schedule all inputs to MPS
The McGraw-Hill Companies, Inc.,
Demand Characteristics
Clipboard
Pivot (1)
Spring (1)
Rivets (2)
Finished clipboard
Pressboard (1)
MRP Inputs
Master Production
Schedule (MPS)
3
Inventory
transactions
Inventory
records
Other
sources
of demand
2
MRP
explosion
Bills of
Materials
(BOM)
Engineering
and process
designs
Material
requirements
plan
Feb
3
150
150
120
Shirts M
Shirt L
200
Aggregate
production plans
for Shirts family
200
670
120
200
200
670
Bill of Materials
A record of all components of an item
Shows the parent-component relationship with production
sequence
The usage quantities are derived from engineering and
process design
End items
Intermediate items
Subassemblies
Purchased items
10
Demand Characteristics
Clipboard
Pivot (1)
Spring (1)
Rivets (2)
Finished clipboard
Pressboard (1)
11
Pressboard
(1)
Top Clip
(1)
Level 0
Clip Assy
(1)
Bottom Clip
(1)
Rivets
(2)
Pivot
Level 1
Spring
(1)
Level 2
(1)
The McGraw-Hill Companies, Inc.,
12
Inventory Record
Inventory transactions are the basic building blocks of upto-date records
Transactions include releasing new orders, receiving
scheduled receipts, adjusting due dates for scheduled
receipts, withdrawing inventory, canceling orders,
correcting inventory errors, rejecting shipments, and
verifying losses and stock returns
Inventory records divide the future into time periods called
time buckets
Keep track of inventory levels and component
replenishment needs
13
Inventory Record
The time-phase information contained in the inventory
record consists of:
Gross requirements
Scheduled receipts
Projected on-hand inventory
Planned order receipts
Planned order releases
Projected on-hand
inventory balance
at end of week t
Inventory on
hand at end of
week t1
Scheduled
or planned
receipts in
week t
Gross
requirements
in week t
14
15
time
Processing
Materials
Waiting
time
time
16
Lot-for-lot (L4L)
Economic order quantity (EOQ)
Least total cost (LTC)
Least unit cost (LUC)
Which one to use?
The one that is least costly!
17
Advantages of MRP
It processes massive amount of information and
presents in a useful and comprehensible form to the
managers.
It helps bring order out of chaos and reduce the workin-process inventories in the system
It serves as a useful tool to keep track of all the
interactions involved in a multistage production
system.
18
19
Shortcomings of MRP
MRP is fundamentally driven by the assumption that
all required information is known with certainty.
Uncertainties arise due to
Differences between estimated demand and actual demand
Variations in production lead times.
Unreliability in the yields of the processes.
20
Given
Giventhe
theproduct
productstructure
structuretree
treefor
forA
Aand
andthe
thelead
leadtime
timeand
and
demand
demandinformation
informationbelow,
below,provide
provideaamaterials
materialsrequirements
requirements
plan
planthat
thatdefines
definesthe
thenumber
numberof
ofunits
unitsof
ofeach
eachcomponent
componentand
and
when
whenthey
theywill
willbe
beneeded
needed
Product Structure Tree for Assembly A
A
B(4)
D(2)
C(2)
E(1)
D(3)
F(2)
Lead Times
A
1 day
B
2 days
C
1 day
D
3 days
E
4 days
F
1 day
Total Unit Demand
Day 10 50 A
Day 8
20 B (Spares)
Day 6
15 D (Spares)
The McGraw-Hill Companies, Inc.,
21
First,
First, the
the number
numberof
of units
units of
of A
A are
arescheduled
scheduled
backwards
backwards to
to allow
allowfor
fortheir
theirlead
lead time.
time. So,
So, in
in the
the
materials
materials requirement
requirement plan
plan below,
below,we
wehave
haveto
toplace
place
th
an
an order
orderfor
for50
50 units
units of
of A
A on
on the
the 99th day
day to
to receive
receive
them
them on
on day
day 10.
10.
Day:
A Required
Order Placement
10
50
50
LT = 1 day
22
Next,
Next,we
weneed
needto
tostart
startscheduling
schedulingthe
thecomponents
componentsthat
thatmake
makeup
up
A.
A. In
Inthe
thecase
caseof
ofcomponent
componentB
Bwe
weneed
need44Bs
Bsfor
foreach
eachA.
A.
Since
Sincewe
weneed
need50
50As,
As,that
thatmeans
means200
200Bs.
Bs. And
Andagain,
again,we
weback
back
the
theschedule
scheduleup
upfor
forthe
thenecessary
necessary22days
daysof
oflead
leadtime.
time.
Day:
A Required
Order Placement
B Required
Order Placement
20
LT = 2
A
B(4)
D(2)
20
50
200
10
50
200
Spares
4x50=200
C(2)
E(1)
D(3)
F(2)
The McGraw-Hill Companies, Inc.,
Finally,
Finally,repeating
repeatingthe
theprocess
processfor
forall
allcomponents,
components,we
wehave
havethe
the
final
finalmaterials
materialsrequirements
requirementsplan:
plan:
Day:
A
LT=1
B
LT=2
C
LT=1
D
LT=3
E
LT=4
F
LT=1
Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
20
20
50
200
23
10
50
200
100
55
20
400
55
400
20
200
100
300
300
200
200
200
A
Part D: Day 6
B(4)
D(2)
C(2)
E(1)
D(3)
40 + 15 spares
F(2)
The McGraw-Hill Companies, Inc.,