MED H&S Plan for Construction sites.


The aim of this Plan is:
-

Until last year each country was working with different HS Plans,
different versionsFrom a SBU point of view, was not under
control!

Avoid general HS Plans .

One HS Plan must be specific for the work to be done, explaining


the different phases, preventive actions, requirements, legal
references

Standardization of the HS Plan.

All Modules except MOD III, will be the same for every country.
This means that, MED will control the revisions of the rest of
Mocules except MOD III. This will be responsibility of the
countries.

MED H&S Plan; Structure.


MOD. I

For EPC contracts.


For S&I.

MOD.II

Specific for Civil & Electrical works

MOD. II

Specific for the installation of the WTG; V90/100 & 112.

MOD. III

Specific for each country; Summary of Vestas and legal requirements.

MOD. IV

Risk Assesmment

Emergen-
cy Plan

MED Emergency plan + Appendix I & II

Others; IRFs, Lifting plans,Report of the Civil works.

MED H&S Plan for Construction sites.


MOD. I, BOP; (Balance of Plant)
General information about the scope, characteristics of the project,
information of the project about client, Vestas responsible, WTGs,
connection of evacuation line to the subestation of the facility

MOD. I S&I; Same than previous with different scope.


MOD. II; BOP;
-

Description of the works:


- Civil works: Leveling, excavations, foundations, reinforcing,
installation of embebed cylinders, anchor cage
- Electrical works: Portable machinery,(generators,
iluminations)five golden rules,safety distance by arc flash,
gruonding systems, preventive actions by task, transmision
line.

MED H&S Plan for Construction sites.


MOD. II, S&I( Supply and Installation)
Descriptions of the phases;
-

Unloading on site.
Signaling, fencing, barricades
Preparation and Installation of main components
HV Wire
Ladder, safety line, elevator
Energization

-
MOD.III;
-

Specific for Vestas & Legal requirements;


This is the only one which is responsibility of each country.
They must have this document updated taking into account local
law. Also, is mandatory to have adapted this document before start
any work in new countries.
Sustainability is responsible of this updating.

MED H&S Plan for Construction sites.


MOD. IV( Risk assesmment)
Preventive action taking into account the different phases included in
the HS Plan.

Emergency Plan and Appendix Iⅈ


Appendix I
- MED Emergency plan; standard for all the countries.
- Appendix I: Example:
Appendix I

Appendix II;
- This must be placed inside each turbine after the installation, during
the commissioning.
Appendix II

Others;
Annexes to HS Plan;
What is an annex to HS Plan? Document including a WKI/procedure &
RA explaining how to do a work step by step.
When do we need to work out an annex? If the work to be done is not
include in the HS Plan.
Who must check if the works are included in the HS Plan? PM is
accountable.
Who must work out the WKI/procedure? PM is accountable.
Who must work out the RA and annex? Local HSE Coordinator from
Vestas.
How can we establish a method to ensure that we are covered all the
time? Trough weekly meetings, Normally on Thursday afternoon.

Annexes already done:


-

Continuous Auger Piles; EN.


Guardrail installation; EN
Assembly of the METMAST;EN
Typhon preparedness
Safety in tree felling and pruning
Aggregate and Concrete Plant

IRFs: Inspection report forms.


-

Must be filled by the responsible of the installation company on site, or Installation


supervisor(Vestas).
Always, MUST be verified before the lifting.
All of these IRFs must be kept during the installation of the WF by Vestas, or in any
case by the Subcontractor, for this case, Vestas will ensure this way of working.

Night shift work;


-

Follow WKI for artificial lighting. This WKI explain the material needed, ilumination
towers, portable lightining, luximeter, etc. How to do, where

Possible problems for the implementation of the HS Plan;


1. Different structure defined by local legislation.

For this case, the HSE coordinator will adapt these contents to local law including
same information.
Will create a doc. including correspondences of both docs.

2. Maybe the HS Plan is responsability of each subcontractor and Main contractor doesn
t develope this plan.

Two possibilities:
o
o

We send our HS Plan to the subcotractor and they change Vestas Logo by theirs.
Or, Sustainability will compare our HS Plan with theirs ir order to ensure that the
requriements are the same, in any case MOD. II for Installation of the WTG will be
ours.

DESCRIPTION OF THE POINTS TO BE CONSIDERED before &


during the Project:
Before work starts:
Request HSE professional

Request of the HS Plan

Safety care service


specification_EN.docx

Preliminary information to create the Safety Plan;


1

Basic project data

Name of WF
Project Manager and Installation Supervisors of Vestas
Main Contractor/s
Flowchart of companies (Customer, main contractors, subcontractors)

Scope of the project:

Scope of contract; EPC, Supply and Installation, Supply, supervision and commissioning,
Type of WTG, model, Number of WTGs, Hub height and type of foundation (Anchor cage?)

Legal requirements of the country.

Mod.III EN.doc

All reference to legislation, royal decrees, laws, technical standards, directives, etc. that are
applicable to a construction site as described herein must be included in Module III so that the
relevant ones are included for each area. In any event, this document shall never be used in its
standard form. It must be adapted to the characteristics of each project, taking into account possible
variations, building system changes.

Costumer data:

Name of the company,

Human resources

Minimum and maximum people working in the WF in the different phases of the project; civil works,
electrical works, transmission lines, Installation of WTGs, commissioning.(estimate).

Substation

Where is main substation where the WF substation will be connected? Or where is going to be
connected the evacuation line?
- Name
and address of the Electrical company?

Budget

xxx , If its possible the amount involved in HSE.

General information of the location of


the WF.

WF Location, address.

Project manager(contact person/s by area)

Length of the roads into the WF.


Lay outs of the WF with the position of the WTGs, Coordinates of WTGs
Lay out of the substation of the WF.
Meteorological tower, Y/N
Information needed to fill the annexes of the Emergency plan: Interesting numbers, coordinates,
nearest hospital, etc (Usually this information is obtained by the EHS coordinator who perform the
HS Plan)
N of Rev. "Vestas Civil works specification annexed to the contract." If apply.

Information requested after the


beginning of the project.

Compaction test of crane paths. (Ones the paths are finished.)


Lifting plans of the crane company by WTG. To be delivered to our PM before starting of lifting .
These Lifting plans should be attached to ours.

10

HSE professional 3rd party

The PM will be accountable of this recruitment following the document Safety care service
specifications VSEGSPEC.

Company, employee and machinery documentation

Special resources when faced with medical emergencies

Ordering health and safety equipment

During work:
Access control and staff on site

HSE and toolbox meetings


- Kickoff meeting
- Weekly meetings.
- Tool box meetings.

- Signaling, barricades.
During operations where main components are being mounted, access roads
must be blocked as follows:
For erecting of T1 and T2: Maximum height of crane for lifting the "T" section, plus 30 mts.
For erecting of T3, T4, (T5 to T6 towers of 119 m and 7 for towers of 140 meters) Nacelle, blades and hub (if mounted
above) they shall refer the hub height plus 40 mts.
Both for point 1 to 2, will be measured from the base of the turbine.
For more information about see Summary guide, attached.

Lifting plans

Microsoft Word
97 - 2003 Document

Inspection of ladders, safety line and elevators

Incident reporting
How does the IDB works?
What FR are you using?
Exercise; Create an incident and upload it into the IDB
Have you received training about Incident management?

Das könnte Ihnen auch gefallen