Beruflich Dokumente
Kultur Dokumente
(B):
The Merseyside and
Corporate project
plan
Current Condition
Changes to DFC
Model
Approachment
Merseyside
Rotterdam
NPV
12.45m
15.5m
IRR
24%
18.0%
PBP
3.78 years
7.95 years
0.022
0.048
Growth in EPS
The Merseyside project had a higher IRR and a much lower payback period. Rotterdam
had a higher NPV by almost half a million pounds, and a larger growth in EPS
09/29/15
Original DCF
Transport Division
09/29/15
EFFECT ON DCF
NPV
= 9.09
IRR
= 22.29%
PBP
= 4 tahun
Impact on EPS
= 0.03
09/29/15
Shutdown Time
09/29/15
09/29/15
09/29/15
EFFECT ON DCF
NPV
: 9.72
IRR
: 22.70%
PBP
: 3 tahun 2 bulan
09/29/15
09/29/15
EFFECT ON DCF
NPV
: 14.36
IRR
: 24.73%
PBP
: 3 tahun 2 bulan
09/29/15
09/29/15
Solutions
There is a conflict existing between these two mutually exclusive projects. Therefore, we will choose the best project
based on the best criterion, which is NPV because NPV assumes reinvestment at the cost of capital and that is
generally the best assumption. Hence, the Rotterdam project should be chosen.
Alternative Solutions
We believe the discount rate should be adjusted. We used the 7% discount rate which was deemed more accurate.
We also accounted for a 3% inflation premium.
Implementation of Alternatives
The expected Net Present value of the Rotterdam project using the revised discount rate and premium is GBP
27.79million. NPV gives explicit consideration to the time value of money and is a good method to evaluate the
project because it assesses all the cost involved. When the NPV of the project is greater than zero, then the firm can
believe that this is an acceptable project. This new NPV shows that the
project is a great investment. If they were to account for full erosion of Rotterdams
business volume, there would still be a positive NPV for Merseyside and above the hurdle rate. The new IRR is
10.5% and this holds the project at an 3.5% higher rate than minimally expected for a project. This IRR represents
the project in a positive light.
09/29/15
Conclusion
James Fawn did have an extremely difficult decision to make.
Although the Merseyside project passed all four criteria for further
consideration, it was NPV
which ultimately prevailed as the superior criterion. Therefore,
Fawn should select the Eustace proposal.
Thankyo
u